  1. Slide 1: Safety Standards for BESS Interconnection

    Safety Standards for BESS Interconnection Presented by Hydro One & Fire & Risk Alliance

  2. Slide 2: Agenda

    Agenda Emergency Introduction Evolution of Risks and Preparedness to Standards Technology Setbacks and Response

  3. Slide 3: Team

    Robert Reinmuller Quyen Diep Ajay Garg Farooq Qureshy Hemant Barot Team

  4. Slide 4: Team

    Anthony Natale Derek Post Noah Ryder Jeffrey Reetz Team

  5. Slide 5: Anthony Natale

    Anthony Natale • CERTIFICATIONS: • Fire Instructor I, II - ProBoard Certified New York State • Incident Command System Instructor FEMA Cert E-449 • Incident Command System 100, 200, 300, 400, 700 & 800a • All Hazards Liaison Officer – FEMA Certification • Incident Management Level 3 New Jersey DFS •

  6. Slide 6: Overview

    Overview Section 1

  7. Slide 7: Introduction

    Introduction Develop Fire Protection & Risk Assessment Standard

  8. Slide 8: Introduction and Purpose

    Applicable Codes Community Risk Introduction Purpose and Standards Assessment BESS Classification Fire Protection Explosion Minimum Design and Spatial System Mitigation Documentation Separation Requirements Requirements Commissioning Operations and Decommissioning Emergency Plan Maintenance Plan Pla

  9. Slide 9: Interconnection Safety Standard

    Interconnection Safety Standard

  10. Slide 10: Closing the Gap Between Technology & Safety

    Closing the Gap Between Technology & Safety

  11. Slide 11: No Risk to Transmission Assets from BESS Failure

    No Risk to Transmission Assets from BESS Failure

  12. Slide 12: Requirements

    Requirements Section 2

  13. Slide 13: Fire Propagation Analysis

    Fire Propagation Analysis Successful Results

  14. Slide 14: Battery Chemistry

    Battery Chemistry Nickel Manganese Cobalt Vs Lithium-Iron Phosphate

  15. Slide 15: Manageable Hazards

    Manageable Hazards

  16. Slide 16: Nickel Manganese Cobalt (NMC)

    Nickel Manganese Cobalt (NMC)

  17. Slide 17: Nickel Manganese Cobalt (NMC)

    Nickel Manganese Cobalt (NMC)

  18. Slide 18: Lithium Nickel Manganese Cobalt Oxide vs Lithium Iron Phosphate

    LITHIUM NICKEL MANGANESE COBALT OXIDE LITHIUM IRON PHOSPHATE NMC LFP

  19. Slide 19: UL 9540A Test Hierarchy

    UL 9540A Test Hierarchy + Whether cell can exhibit thermal runaway * Thermal runaway characteristics {] - Gas composition (flammability) Cell Level Test + Propensity for propagation of thermal runaway Module Level Test + Heat and gas release rates (severity/duration) + Flaming/deflagration hazards I

  20. Slide 20: Module Test

    Module Test

  21. Slide 21: No Fire Propagation Beyond the Module

    No Fire Propagation Beyond the Module

  22. Slide 22: Hazard Mitigation Analysis (HMA)

    Hazard Mitigation Analysis (HMA)

  23. Slide 23: Explosion Mitigation

    Explosion Mitigation APS, Surprise AZ - April 19th, 2019

  24. Slide 24: No Provisions for NFPA 68/69 Compliance

    No Provisions for NFPA 68/69 Compliance 24

  25. Slide 25: NFPA 68

    NFPA 68

  26. Slide 26: NFPA 69

    NFPA 69

  27. Slide 27: NFPA 68 or NFPA 69 Analysis

    NFPA 68 or NFPA 69 Analysis Powin Stack 360 53-ft Dual-Duct Roof C1D1 Exhaust Fan Explosion Prevention Analysis Powin Stack 360 53-ft Dual-Duct Roof C1D1 Exhaust Fan Explosion Prevention Analysis SUPPORTS NFPA 69 ANALYSIS

  28. Slide 28: Number of Cells Required to Reach LFL

    Number of Cells Required to Reach LFL

  29. Slide 29: NFPA 855 Requires Explosion Control Method

    NFPA 855 Requires 1 Explosion Control Method NFPA 68 NFPA 69

  30. Slide 30: Tesla Explosion Control

    Tesla Explosion Control 22 Roof Vents w/ 12 Sparkers

  31. Slide 31: Failure Modes & Effects Analysis

    Failure Modes & Effects Analysis

  32. Slide 32: Fire Risk Assessment

    Fire Risk Assessment Community Risk Assessment

  33. Slide 33: Required Setbacks

    Required Setbacks

  34. Slide 34: Substation Setback

    HV Station ASK / 230kV / 500kV Substation Setback 115kV / 230kV / 500kV g Min Setback BES Facility Connected toa Station

  35. Slide 35: Transmission Corridor Setback

    Transmission Corridor Setback

  36. Slide 36: Setback Table

    Item # Hydro One Facilities Hydro One Setback Distance1,2 1 Hydro One – 500 kV Right of Way (ROW) 150 meters 2 Hydro One – 230 kV ROW 100 meters 3 Hydro One – 115kV ROW 60 meters 4 Hydro One – 500 kV Substation 300 meters Setback Table 5 Hydro One – 230 kV Switching Substation 200 meters 6 Hydro One

  37. Slide 37: Assessments

    Up to 400m from Up to 250m from Required Assessments Stations Property Lines ROW Line • Hazard Mitigation Analysis (HMA) o Code Review o UL 9540 Listing Required Required o UL 9540A Test Report o Fault Condition Assessment Assessments • Fire Risk Assessment (FRA) o Community Risk Assessment Required

  38. Slide 38: Detection

    Detection

  39. Slide 39: FACP to Central Station Monitoring

    FACP to Central Station Monitoring

  40. Slide 40: First Responder Station

    First Responder Station Gas Readings Purge Control FACP Data

  41. Slide 41: Fire Suppression

    Fire Suppression Changing Tactics

  42. Slide 42: Why Do We Extinguish Fires?

    Why Do We Extinguish Fires ? Life Safety & Preservation of Property

  43. Slide 43: What They Think & What Actually Happened

    What They Think & What Actually Happened

  44. Slide 44: Thermal Runaway Vent Pressure

    Thermal Runaway Vent Pressure 100 psi

  45. Slide 45: Single Failure Loss

    Single Failure Loss

  46. Slide 46: Spatial Separation

    Spatial Seperation

  47. Slide 47: Do Not Install MV Skid Between Containers

    Do Not Install MVSkid Between Containers

  48. Slide 48: Exposure Control

    Exposure Control

  49. Slide 49: Vegetation Management

    Vegetation Management

  50. Slide 50: Required Plans

    Standard for Req ul red P | ans the Installation of Stationary Energy Storage Systems 2023

  51. Slide 51: Commissioning Plan

    Commissioning Plan | Commissioning / Testing Process details COMMISSIONING Safety and Reliability Focus Base line measurements Operations Safety “Voltage *IR scan of connections and *Capacity batteries Fault current protection testing Fire suppression testing «Ramp rate *Charge time *Discharge time

  52. Slide 52: Operations & Maintenance Plan

    Operations & Maintenance Plan

  53. Slide 53: Decommissioning Plan

    Decommissioning Plan © WARTSILA FIRES RISK ALLIANCE Wartsila GridSolv Quantum ESS Decommissioning Plan REY 0) Da ay 2003 SCpUR SA ee eee a porter roms = decommissioning of Wartsita's GridSolv Quantum (485 Sorrpart Place, Sue 1600 energy storage system battery installations. poaspcaeealt -_ nipuaanor

  54. Slide 54: Emergency Response Plan

    FIRE& RISK. ALLIANCE. Emergency Response Plan Dry Bridge BESS Chesterfield County, Virginia Battery Energy Storage System This plan has been developed to assist the ical em conders with important safety and emergency response information Emergency Psat aid Response Plan Rev_02 re donlreperpeerimicis

  55. Slide 55: Fire Department Training

    Fire Department Training Hazards & Response Tactics for BESS Emergencies

  56. Slide 56: Familiarization Tours

    Familirarization Tours

  57. Slide 57: Design Documentation

    • Recommended documents to be submitted to Hydro One: • Hazard Mitigation Analysis (HMA) • Code Review • UL 9540 Listing • UL 9540A Test Reports • Fault Condition Assessment • Fire Risk Assessment (FRA) Design • Community Risk Assessment • Air/Gas Dispersion Study Documentation • Fire Protection Des

  58. Slide 58: Next Steps

    Next Steps Hydro One will post the Fire Protection Risk and Response Standard (FPRRAS) on the Transmission Connected Generator page by 21st July 2023. Your comments are expected before 4th August 2023 For any questions or comments, please email us with a Subject Line “BESS Setback Enquiry” to: large

  59. Slide 59: Questions

    Questions