  1. Slide 1: Structural Steel and Concrete Analysis Through 3D Scanning

    STRUCTURAL STEEL AND CONCRETE ANALYSIS THROUGH 3D SCANNING Joshua Engelbrecht Philip Lorenzo VDC Engineer Software Developer j Join the conversation #AU2015

  2. Slide 2: Summary

    Summary  Current State of the Industry  Why Scan during Construction?  Best Practice Workflows  Capture  Compute  Create  Benefits, Values  Code Compliance  How you can contribute

  3. Slide 3: Class summary

    Class summary As a General Contractor McCarthy has integrated laser scanning as a Quality Control measure to ensure that we are providing the best client experience possible. In this presentation we will be covering what laser scanning is, why the construction industry is starting to utilize it's po

  4. Slide 4: Key learning objectives

    Key learning objectives At the end of this class, you will be able to:  Logistically Analyze How to Carry Out Field Scanning  Understand Field & Office Best Practices for Laser Scanning Workflows  Apply Expedited Data Analysis Workflows for:  Steel Monitoring  Concrete Topography  Concrete Mon

  5. Slide 5: When are people typically scanning?

    When are people typically scanning? August 2015

  6. Slide 6: Why scan during construction?

    Why scan during construction? As opposed to many who scan during preconstruction as-built modeling • Margin for Error • Cost of Mistakes • Costs of Delays • Overall Quality • Overall Value

  7. Slide 7: What are we scanning for?

    What are we scanning for?  Beam Camber Monitoring (Pre vs. Post Pour)  Floor Flatness  Steel Placement Elevation Verification  As-built Modeling  In-Wall & Over-Head Utilities

  8. Slide 8: Why do we scan?

    Why do we scan?  Increased Efficiency  Quality Enhancement  Risk Management  Waste Reduction Why does McCarthy scan in- house?  Better understanding of required deliverables  Better control over Schedule  Better integration with BIM processes (local coordinates)  Competition and Standardizat

  9. Slide 9: Laser Scanning vs. Conventional Survey Methods: Steel Monitoring

    Laser Scanning vs. Conventional Survey Methods (Then vs. Now) Steel Monitoring Conventional Survey Laser Scanning

  10. Slide 10: Laser Scanning vs. Conventional Survey Methods: Floor Flatness

    Laser Scanning vs. Conventional Survey Methods (Then vs. Now) Floor Flatness/Floor Leveling Conventional Survey Laser Scanning

  11. Slide 11: Our Tools

    Our Tools AutoCAD Rithm International "— Building on (a BUILDER INSPECTOR AUTODESK UNIVERSITY 2015 A AUTODESK.

  12. Slide 12: Our Strategy – Minimum Viable Workflow

    Our Strategy – Minimum Viable Workflow Constantly work together to minimize the amount of steps and clicks from scan to deliverable, WITHOUT compromising on quality and accuracy Benefits:  Trainability  Repeatability  Scalability  Risk/Uncertainty  Bottlenecks  Costs

  13. Slide 13: Best Practice Workflows

    Best Practice Workflows #AU2015 Capture – Compute - Create

  14. Slide 14: Field Scanning – What to look for? Jobsite Conditions

    Field Scanning – What to look for? Jobsite Conditions For Optimal Data Collection:  Dry conditions (NO WATER)  Minimal Debris  Pallets & Material Clear  Clear Line of Sight  Correct Job-phase (i.e. For steel, cannot be fireproofed)  Minimal Foot Traffic  No Rain or Airborne Dust Why is it imp

  15. Slide 15: Field Scanning – Scheduling

    Field Scanning – What to look for? Scheduling (Job-Site Phases) Mobilizations vs. Essential Data  Capture FF/FL & Overhead Steel Simultaneously  Deck Pour Sequencing Timing  FF/FL Scanning ASAP  Monitoring Based on Design Timeline  Post Pour Camber Based on Fireproofing Schedule Capture – Compu

  16. Slide 16: Field Scanning – Fireproofing Scheduling Issue

    Field Scanning – What to look for? Fireproofing Scheduling Issue New Stanford Hospital Project Palo Alto, CA Level 1 Overhead Steel: - 178,313 ft2 & 11,326 LF Main Steel - Fireproofing carried out before Post-Pour Camber scanning - Had to poke through fireproofing & shoot elevations with Total Stati

  17. Slide 17: Target-Less Registration (Cloud to Cloud)

    Target-Less Registration (Cloud to Cloud) Benefits: • Easier to Train • More Free Time • Tracking/Planning • Simultaneous Scan/Registration Pro-tips: • >50% overlap each 80/20 Rule: • Scan at a faster rate (lower Field Scanning drives 80% of the results resolution), shorter distances Office Registra

  18. Slide 18: Aligning Scan Data: Survey Control

    Aligning Scan Data to Model Coordinates Method 1: Survey Control (“Best Practice” or “The Divine Privilage”) Benefits:  Potentially easier (with experience)  Global Accuracy Challenges:  Potentially painful (in-experienced surveyor)  Time/Schedule  Expensive Capture – Compute - Create

  19. Slide 19: Aligning Scan Data: Field Grid Offsets and Benchmarks

    Aligning Scan Data to Model Coordinates Method 2: Field Grid Offsets and Benchmarks Considerations:  May not always be available X Benefits:  No need for robotic Y Total Station  $1200-$2000 cost savings per mobilization  Prevent 1-3 days of delay Z Capture – Compute - Create

  20. Slide 20: Aligning Scan Data: Model Best Fit

    Aligning Scan Data to Model Coordinates Method 3: Model “Best Fit” Considerations:  Only for certain deliverables  May be creating more liability  Need to ensure scans are leveled Benefits:  Same cost and schedule benefits (if done right)  Less field time Capture – Compute - Create

  21. Slide 21: Structural Steel Deliverables

    Structural Steel Deliverables Steel and Fabrication and Erection Tolerances Installation Cambers Capture – Compute - Create

  22. Slide 22: Structural Steel Camber Analysis

    Structural Steel Camber Analysis Camber: +.04’ Elevation: 100.00’ Elevation: 100.04’ Elevation: 100.00’ Capture – Compute - Create

  23. Slide 23: Structural Steel Monitoring

    Structural Steel Monitoring • Pre: Verify Design Camber to installation of steel is correct • Post: Ensure performance of steel is correct Capture – Compute - Create

  24. Slide 24: Steel Monitoring – Design vs. Field Camber

    Steel Monitoring – Design vs. Field Camber Value New Stanford Hospital Project Palo Alto, CA Level 3 Overhead Steel:  67,280 sq ft Concrete 4,368 LF Steel  Distance from finish floor to steel = 30’ Total Station & Philly Rod Method  8 Mobilizations for 64 Manhours  3 Points on each main beam mem

  25. Slide 25: Intra-operative MRI system – Kaiser Oakland Medical Center

    Intra-operative MRI system – Kaiser Oakland Medical Center “IMRIS...alignment is within a millimeter of optimum. This is the best steel installation IMRIS has seen in the last five years of worldwide equipment placements.” Jim Kautz, Sr. Project Manager, Kaiser Permanente National Facilities Service

  26. Slide 26: Concrete Flatness – What is it?

    Concrete Flatness – What is it? +3/8 inch -3/8 inch Capture – Compute - Create

  27. Slide 27: Capture – Compute – Create

    Flooring Material: Concrete Grinding: • Door Undercuts $1-$2/square foot $4-$5/square foot • Deck to Deck Heights • Prefabricated Walls with MEP Capture – Compute - Create

  28. Slide 28: Value - Downstream Effects on Concrete

    Value - Downstream Effects on Concrete Low spots detected in Procedure Room, might affect mobile computer station Pre-emptive Quality Control - Door-Swings Capture – Compute - Create

  29. Slide 29: Where has McCarthy scanned Concrete?

    Where has McCarthy scanned Concrete? Kaiser Oakland Kaiser South Bay Stanford Adult Hospital 13 levels - 980,000 sqft 4 floors, 320,000 sqft 8 levels - 824,000 sqft Many more to come… UC Berkeley Lower SF Bay Area UCSF Parnassus Sproul Housing Authority

  30. Slide 30: Concrete Monitoring – Shoring/Reshoring Cantilever

    Concrete Monitoring – Shoring/Reshoring Cantilever What is it? Cantilevered decking is reinforced with shoring, propping up the cantilevered end based on design deflection. The shoring transfers the loading down to the next level, hindering any downward displacement of the cantilevered section. Once

  31. Slide 31: Concrete Monitoring – Shoring/Reshoring Cantilever Case Study

    Concrete Monitoring – Shoring/Reshoring Cantilever Case Study New Stanford Hospital Project Palo Alto, CA Cantilevered Towers  Level 4 Cantilevered at exterior 30’ bay  Exterior bays were shored prior to concrete deck pours  Once all pours were complete & concrete design strength reached for Leve

  32. Slide 32: Concrete Monitoring – Shoring/Reshoring Cantilever Case Study

    Concrete Monitoring – Shoring/Reshoring Cantilever Case Study New Stanford Hospital Project Palo Alto, CA Cantilevered Towers  Scanned for FF prior to shoring removal  Check for rise in elevation between interior supported bays and exterior cantilevered sections  Scanning for FF after shoring rem

  33. Slide 33: Wet Concrete

    Wet Concrete  One Scan Workflow  No Registration  Feedback to concrete crew  Positive Correlation between fixing and next day condition  <7 minute from scan to deliverable Capture – Compute - Create

  34. Slide 34: Building Code Compliance

    Building Code Compliance Down/Out Measurements Achieve better FF/FL Results the next day = Passed Inspections • FF20 • FF50 • FF 90 Capture – Compute - Create

  35. Slide 35: ASTM 1155 Floor Flatness

    ASTM 1155 Floor Flatness Well known laser screeding company ran FARO next to a Dipstick® floor profiler and a total station F – number comparison • FARO FF =36.02 • Total Station FF = 35.99 • Dipstick ® FF = 36.37 • Result: 1% difference between FARO and floor profiler • Now official ASTM 1155 (2014

  36. Slide 36: Why?

    Why? • Pass Inspection • Prevent Litigation UC Berkeley Lower Sproul Fire-Marshall Initiated Stair Survey Capture – Compute - Create

  37. Slide 37: Case Study: Cost Analysis – Scan vs no scan

    Case Study: Cost Analysis – Scan vs no scan Kaiser Oakland Medical Center $900-$2300 per mistake (overall + • Hundreds of penetration/Floor downstream effects) • Additional drilling required for $2000-$3000 per entire floor of scanning major penetration offsets 10 mistakes prevented = ~5x-10x ROI ($

  38. Slide 38: How you can contribute – New Standard Creation

    How you can contribute – New Standard Creation “Level of Accuracy” E06 Committee

  39. Slide 39: ReCap

    ReCap  Current State of the Industry  Why Scan during Construction?  Best Practice Workflows  Benefits  Code Compliance  How you can contribute

  40. Slide 40: Questions?

    Questions? Joshua Engelbrecht Philip Lorenzo VDC Engineer Product Manager Jengelbrecht@McCarthy.com Philip@Rithm.io Booth: 1131