1414 Degrees Ltd. · ASX:14D

1414 Degrees — Tactic 2026

11 slides from 1414 Degrees's conference presentation, Jul 29, 2026

  1. Slide 1: Conference Presentation - Tactic 2026

    29 July 2026 ASX:14D CONFERENCE PRESENTATION - TACTIC 2026 1414 Degrees Ltd (ASX: 14D) ("1414 Degrees" or the "Company) attaches the presentation to be delivered by Chief Technology & Operations Officer, Dr Peter Yaron, at the Tactic 2026 Conference in Port Augusta, South Australia, later today on 2

  2. Slide 2: Aurora Energy Precinct

    For personal use only AURORA ENERGY PRECINCT Firmed power, land and transmission designed for the AI era. Peter Yaron, Chief Technology & Operations Officer 29/07/26 Tactic 2026, Port Augusta. 1414 Degrees Limited 2026

  3. Slide 3: Why Aurora, Why Now

    WHY AURORA, WHY NOW Power + Transmission + Fibre + Water + Land = For personal use only Everything major industrial energy users need in one place Aurora was conceived as an energy precinct. The rapid growth of AI and advanced computing has created a new class of infrastructure customer seeking the

  4. Slide 4: What Is the Aurora Energy Precinct

    WHAT IS THE AURORA ENERGY PRECINCT For personal use only A development-ready energy precinct built for large energy users Key Infrastructure • Approved 140 MW / 280 MWh BESS • Renewable generation • 275 kV transmission corridor • 33 kV distribution connection • Fibre telecommunications • Water Locat

  5. Slide 5: What's Happened Since 2025

    WHAT’S HAPPENED SINCE 2025 Aurora has spent years building approvals and infrastructure pathways. For personal use only Today we're focused on turning those approvals into outcomes for the Upper Spencer Gulf. AEMO acceptance of Transmission connection Practical 33 kV Generator Performance progressin

  6. Slide 6: What's First, What's Next?

    WHAT’S FIRST, WHAT’S NEXT? For personal use only NEAR TERM 33 kV distribution line connection • Practical pathway to commence development activities before larger transmission infrastructure is completed • EV charging • Modular data centres • Site services • Early construction activity LONG TERM 275

  7. Slide 7: A Staged Pathway to Gigawatt Scale

    A STAGED PATHWAY TO GIGAWATT SCALE For personal use only Heads of Agreement signed with a prospective AI infrastructure developer for staged deployment of up to 1 GW of data centre capacity at Aurora. STAGE 1 — INITIAL CAMPUS DEVELOPMENT • Indicative 17 MW campus, drawing on the 33 kV connection alr

  8. Slide 8: Why Is Aurora Attracting AI Interest

    WHY IS AURORA ATTRACTING AI INTEREST For personal use only ✓ Reliable scalable energy supply – backed by BESS and renewable generation ✓ High-capacity communications networks ✓ Reliable water supply ✓ Land with room to expand ✓ Long-term investment horizons Aurora combines these requirements in a si

  9. Slide 9: What Aurora Could Mean for the Region

    WHAT AURORA COULD MEAN FOR THE REGION For personal use only Potential opportunities across: • Equipment hire • Civil construction • Maintenance services • Electrical works • Security • Earthworks • Professional services • Transport and logistics • Engineering & professional services • Accommodation

  10. Slide 10: From Approvals to Delivery

    FROM APPROVALS TO DELIVERY For personal use only Aurora has spent years establishing approvals, infrastructure pathways and strategic partnerships. The next phase will turn that foundation into projects, construction activity and long-term economic opportunities for the Upper Spencer Gulf. We welcom

  11. Slide 11: Thank You

    For personal use only THANK YOU Peter Yaron, Chief Technology & Operations Officer 1414 Degrees Limited auroraenergyprecinct.com.au info@auroraenergyprecinct.com.au

1414 Degrees — Tactic 2026 on 6ix