Boral — Corporate Update (December 2019)
23 slides from Boral's corporate update, Dec 5, 2019
Slide 1: Boral Berrima Cement
Build something great™ BORAL BERRIMA CEMENT 5 December 2019 > Community Liaison Group meeting Berrima Cement Works New Berrima
Slide 2: Agenda
Agenda ˃ Site inspection ˃ Welcome, administration and safety moment ˃ Operations ˃ Environment ˃ Planning ˃ Community ˃ General business
Slide 3: Welcome, administration and 'safety moment'
Welcome, administration and ‘safety moment’ ˃ Welcome and re-introductions ˃ Safety moment ˃ Previous meeting of the Community Liaison Group ˃ 26 September 2019 ˃ Note: Presentations and meeting notes from previous meetings are also available from the Cement Works website – www.boral.com.au/berrimac
Slide 4: Operations
Build something great™ BORAL BERRIMA CEMENT > Operations
Slide 5: Operations, People, Safety
Operations, People, Safety ˃ Production: After a challenging year, November saw the site’s production get back on track. ˃ Exceeded budgeted volumes during the course of the month. ˃ We will be working through the Christmas-New Year period in order to ‘catch up’ on lost time during 2019. ˃ The kiln
Slide 6: Dust mitigation and management progress
Dust mitigation and management progress ˃ The ‘real time’ monitor has been ordered, with the aim to install it by the end of the year. This will include direct telemetry to the control room. ˃ The Air Quality TARP has been prepared. ˃ The EPA issued Boral with a ‘Show Cause’ regarding the dust incid
Slide 7: Operations: New water cart
Operations: New water cart ˃ Our new 30000L water cart is almost ready for deployment. ˃ Replaces former 7000L cart at a cost of around $250 000. ˃ Has cannon fitted for targeted spraying. ˃ New filling station built – former cart took 30-40 minutes to fill, new cart will take 5. ˃ Training for staf
Slide 8: Solid Waste Derived Fuels (SWDF)
Solid Waste Derived Fuels (SWDF) ˃ The SWDF shed extension is now complete but not yet operating. ˃ Crane programming issues are delaying finalisation of the project.
Slide 9: Environment
Build something great™ BORAL BERRIMA CEMENT > Environment
Slide 10: Air Quality Management
Air Quality Management ˃ Recent stack monitoring. ˃ Stack testing undertaken on 31 July was in compliance for all parameters. 31/07/2019 Parameter – Kiln 6 (EPA ID. 2) Unit Limits R007956 Mercury mg/m3 0.05 0.0088 Type 1 and type 2 substances mg/m3 0.5 <0.079 Solid particles mg/m3 50 47 Nitrogen oxi
Slide 11: Air Quality Management
Air Quality Management ˃ Dust Deposition – graph of historical results and gauge location map.
Slide 12: Air Quality Management
Air Quality Management ˃ Ambient Air Monitoring Program – HVAS.
Slide 13: Environmental overview
Environmental overview ˃ Water quality monitoring. ˃ Due to the ongoing impact of the drought, no discharges have been recorded for the most recent period. ˃ Three recent submissions to the NSW Department of Planning, Industry and Environment (DPIE). ˃ Solid Waste Derived Fuels (SWDF) first year ass
Slide 14: Then and now – 2014 v 2019
Then and now – 2014 v 2019 ˃ The picture on the left was taken just after the trees were planted during April 2014. The one of the right was taken during October from the same point. ˃ Trees originally planted as part of site Landscape Management Plan.
Slide 15: Planning
Build something great™ BORAL CEMENT BERRIMA > Planning
Slide 16: Planning
Planning ˃ MOD 11 – Use of HiCal 50. ˃ MOD 11 was approved on 25 October 2019. ˃ Approval now permits blending of HiCal 50 (carbon anode) at 4% with coal and use during start-up conditions. ˃ Licence variation submitted to the EPA. ˃ Anticipating commencing use in early 2020 once the EPA variation i
Slide 17: Planning
Planning ˃ MOD 13 - SWDF hours of delivery. ˃ Ultimately, we want to reduce the effects of traffic movements in the site area. ˃ We are aiming to achieve this by dispersing the amount of vehicle movements we add to local roads. ˃ This will result in more consistent delivery of SWDF materials to the
Slide 18: Community
Build something great™ BORAL CEMENT BERRIMA > Community
Slide 19: Community
Community ˃ Habitat corridor proposal. ˃ Internal discussion held following meeting in North Sydney. ˃ Supportive of concept however more information required. ˃ Will require Cement line management endorsement, multi-year project if supported, resource dependant.
Slide 20: Community
Community ˃ Previously reported support for the Southern Highlands Kennel and Obedience Club (20 Oct) and annual Harper’s Mansion Garden and Plant Fair (27 Oct). ˃ Both events conducted successfully on respective dates. ˃ A note that community contribution may be more limited during 2020 due to reso
Slide 21: General business
Build something great™ BORAL BERRIMA CEMENT > General business
Slide 22: General business and contacts
General business and contacts ˃ Items of general business ˃ Next meetings ˃ Community Liaison Group – Mar 2020?. ˃ Next ‘Whole of Community’ meeting – Jul-Aug 2020 unless needed earlier. ˃ Boral Berrima Cement contacts: ˃ Berrima Cement Works Reception 4860 2222 / madeline.westnidge@boral.com.au ˃ P
Slide 23: Thank you for your attendance
Build something great™ BORAL BERRIMA CEMENT > Thank you for your attendance