Orezone Gold Corporation · TSX:ORE

Orezone Gold — Investor Presentation (July 2011)

31 slides from Orezone Gold's investor presentation, July 2011

  1. Slide 1: Expanding the Largest Undeveloped Gold Deposit in Burkina Faso

    Expanding the Largest Undeveloped Gold Deposit in Burkina Faso July, 2011

  2. Slide 2: Forward Looking Statements

    Forward Looking Statements This Presentation may contain “forward-looking information” which may include, but is not limited to, statements with respect to: political conditions and government regulations in foreign countries; timing of the receipt of governmental approvals and/or acceptances; targe

  3. Slide 3: Background

    Background Orezone Resources Orezone Gold 1995 - 2009 2009 (ORE.T (ORE T ) Essakane Same team 1 5 Æ 5.3 1.5 53M Moz + 3 gold projects Bomboré 0.9 Æ 3.5 Moz Æ ? Permits Financing Construction ( 1.6 M&I + 1.9 Inf ) Market Cap Buys Orezone (OZN.T) Jan 2009 : $ 20 M J $350 M July 2011 : $ 280 M 3

  4. Slide 4: Investment Highlights

    Investment Highlights 1 Potential world-class gold deposit, in Burkina Faso • 11 km long with 1.6 Moz M&I + 1.9 Moz Inferred • 35,000 oz/vertical meter, with avg. drill depth to date of 60 m • Goal: +250,000 oz/year by 2015 2 Veteran team has discovered, developed, operated & sold gold co’s • Engine

  5. Slide 5: Summary: Gold Resources

    Summary: Gold Resources Category Tonnes Grade Gold Content (millions) (Au g/t) (ounces) Bomboré Measured & Indicated 60.9 0.81 1,589,000 Inferred 60.6 0.96 1,873,000 Sega Measured & Indicated 8.3 1.69 450,400 Inferred 2.9 1.58 147,300 Bondi Measured & Indicated 4.1 2.12 282,000 Inferred 2.5 1.84 149

  6. Slide 6: Capital Structure

    Capital Structure Shares Issued 83.4 million Shares Fully Diluted 89.5 million (no warrants) Directors & Management Interest 5% Top Institutional Shareholders ~50% • Passport Capital • AGF • JP Morgan • IG • Van Eck ETF • UBS • Beutel Goodman • BMO • Tocqueville • TAL • First Eagle • RBIM • Standard

  7. Slide 7: Experienced Team

    Experienced Team Senior Management Years Experience Ron Little P.Eng Founder, CEO & President 25 Pascal Marquis PhD, PhD P.Geo P Geo SVP Exploration 25 Sean Homuth CA CFO 10 George McTaggart MBA VP Corporate Development 25 Joe McCoy MBA VP Administration 25 Board of Directors Ron Little Founder, CEO

  8. Slide 8: Burkina Faso

    Burkina Faso 16 Million people. French speaking. 1987 Stable democracy 2004 Modernized mining code 22% Birimian greenstone belts 6 New gold mines since 2007 Global ranking in “Current Mineral 6th Potential Index Index” (Fraser Institute, 2010) 4th Largest African gold producer by 2012 Re-elected Cap

  9. Slide 9: Geological Setting: Birimian Greenstone Belt

    Geological Setting: Birimian Greenstone Belt Trans-crustal structure: Markoye-Tiébélé Fault Large deposit association 200 km Essakane 5.9 Moz IAMGOLD 1 1 Moz Taparko 1.1 High River Bombore 3.5 Moz Orezone Kiaka 4.3 Moz Volta Youga 0.8 Moz Endeavour 9

  10. Slide 10: Bomboré Overview

    Bomboré Overview Reservoir N 11 km Heap Leach Pad Waste W t Rock Pit 11 km 168 km² Shells 2010 Resource Update (NI 43-101) Meas. & Indicated 60.9 Mt 0.81 g/t 1.6 Moz I f Inferred d 60 6 Mt 60.6 0 96 g/t 0.96 /t 1 9 Moz 1.9 M 10

  11. Slide 11: Bomboré Pit-Shell Cross-Section

    Bomboré Pit‐Shell Cross‐Section W E Looking North 100 m Oxide Fresh Heap CIL Pit Leach Pit Drilling at Depth 11

  12. Slide 12: New, Positive Results at Depth

    New, Positive Results at Depth Gold mineralization continues at depth Maga Main Zone Au Grades >0.5 0.5 g/t >0.2 g/t 100 m 12

  13. Slide 13: Preliminary Economic Assessment: Summary

    Preliminary Economic Assessment: Summary • G Mining Services Inc. (Montreal) completed Preliminary Economic Assessment 1 of Bomboré Gold Project – G Mining history in country building Essakane (6 Moz) – Bomboré: Heap Leach & CIL standalone comparisons – Based on Oct 2010 NI 43 -101 resource update (

  14. Slide 14: PEA Base Case Highlights

    PEA Base Case Highlights $1000/oz gold pit shell, $1100/oz gold in revenue, $80/bbl oil, all other costs are current market Description Heap Leach CIL Mineral Resource in mine plan (ounces) 1,171,529 2,506,608 Average Grade (g/t) 0.83 0.94 Maximum Throughput (million tonnes) 5.8 9.3 Mi Life Mine Lif

  15. Slide 15: PEA Highlights (continued)

    PEA Highlights (continued) $1000/oz gold pit shell, $1100/oz gold in revenue, $80/bbl oil, all other costs are current market Description Heap Leach CIL Total Project NPV (0%) ($M) $166.7 $320.3 NPV (5%) ($M) $88.3 $124.8 IRR 14.7% 10.2% Orezone (90%) (1) NPV After tax (0%) ($M) $105.0 $207.6 NPV Af

  16. Slide 16: Mineral Resources Used In PEA Mine Plan

    Mineral Resources Used In PEA Mine Plan Heap Leach CIL Category Fresh Sap p + Lat Transition Total Sap p + Lat Transition Total R k Rock Tonnes (kt) 21,848 8,439 30,288 26,496 8,504 11,017 46,016 Indicated Grade (g/t) 0.80 0.86 0.82 0.74 0.93 1.16 0.87 In-situ koz 564 232 796 626 254 410 1,290 Tonne

  17. Slide 17: Gold & Oil Price Sensitivity

    Gold & Oil Price Sensitivity Base Current Gold ($1000 /oz pit shell) Case Price Scenario Æ 1 2 3 4 5 6 7 8 Gold Price ($/oz) $900 $1000 $1100 $1200 $1300 $1400 $1500 $1700 Oil Price ($/bbl) $60 $70 $80 $90 $100 $110 $120 $140 H Heap L Leach h (90% tto O Orezone)) NPV After tax (0%) ($M) -41.0 36.2 1

  18. Slide 18: Estimated Annual Gold Production

    Estimated Annual Gold Production ($1000 /oz pit shell) Year Æ 1 2 3 4 5 6 7 8 9 10 Total Heap Leach Gold Prod’n (koz) 148 129 117 124 110 117 133 66 944 Head Grade (g/t) 0.98 0.85 0.77 0.82 0.73 0.78 0.88 0.79 0.83 CIL Gold Prod’n (koz) 305 255 226 253 227 222 244 234 184 34 2,185 Head Grade (g/t) 1

  19. Slide 19: Unit Processing Costs by Rock Type

    Unit Processing Costs by Rock Type ($/tonne) Laterite / Transition Weighted Heap Leach Saprolite Average Energy $1.01 $1.11 $1.03 Labour $1.15 $1.15 $1.15 Materials ate a s & Reagents eage ts $4.62 $ 6 $3.76 $3 6 $4.39 $ 39 Total $6.78 $6.02 $6.57 Saprolite Transition Fresh Rock Weighted CIL Average

  20. Slide 20: Initial Project Capital Costs

    Initial Project Capital Costs Description Heap Leach CIL Infrastructure $13.6 $19.5 Water $9.4 $15.6 Power $4.9 $38.8 Mining $50 7 $50.7 $129 9 $129.9 Process Plant $34.9 $98.4 Indirects $40.2 $48.8 Pre-production & General Services $29.0 $103.1 Contingency $22.0 $45.4 Total ($ millions) $204 7 $204

  21. Slide 21: Operating Costs for Each Base Case Scenario

    Operating Costs for Each Base Case Scenario Heap Leach CIL Total T t l Costs C t Avg. Cost A C t Avg. Cost A C t Total T t l Cost C t Avg. Cost A C t Avg. Cost A C t Category $M $/t milled $/oz $M $ /t milled $ /oz Mining $254.4 $5.79 $268 $633.7 $7.64 $290 P Processing i $286 5 $286.5 $6 52 $6.52 $

  22. Slide 22: Key Factors to Improve Economics

    Key Factors to Improve Economics • 170,000 m of Drilling Æ Resource Update N – 140% increase in total drilling – Improve I continuity ti it andd lower l strip t i ratio ti – Upgrade inferred to measured and indicated – Increase resources • Optimized pit shells with higher gold price 11km – Current P

  23. Slide 23: Bomboré Schedule

    Bomboré Schedule 2011 2012 2013 2014 2015 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Drilling: Infill & Expansion x x x x x x Prelim Economic Assess’t x Resource Update x Full Feasibility Study x Permitting x x Construction x x x x x x x Production x x x x Our Goal: + 250,000 oz / yr 23

  24. Slide 24: Comparable gold deposits?

    Comparable gold deposits? Kinross Tasiast Orezone Bomboré Mauritania Burkina Faso 7.5 km 2010 p pitshell 11 km 2010 CIL p pitshell 300 m Depth of drilling 60 m Average drilling depth to date 32,000 oz Gold per vertical meter 35,000 oz Gold per vertical meter 9.7 Moz @ 1.3 g/t 3.5 Moz @ 0.9 g g/t Tim

  25. Slide 25: Sega Gold Project

    Sega Gold Project Near-surface, heap leachable gold deposit adjacent to Kalsaka mine (Cluff Gold) • 313 km² project area • 455,000 455 000 oz Indicated • 147,000 oz Inferred • Grade 1.7 g/t • 7 pittable deposits • Heap leach potential • 10,000 m drilling – Q3 • Scoping study – ongoing 25

  26. Slide 26: Bondi Gold Project

    Bondi Gold Project Near-surface, heap leachable, with potential at depth • 4 km trend, open along strike • 282,000 oz Indicated • 150,000 oz Inferred • Average Grade 2.0 g/t • Higher Grades up to 20g/t Zone Z2 Drill Hole Highlights Results over 4g/t Hole # from to m g/t Section BRC130 80 8.0 16.0 16

  27. Slide 27: Uranium - Niger

    Uranium ‐ Niger New discovery adjacent to producing mines Niger: 3rd largest uranium producing region worldwide by 2014 • Brighton Energy Corp 67% owned by Orezone Gold • 5 permits Æ 4,000km² 4 000km² • Adjacent to operating mines (Areva) • Adjacent to GoviEx (Friedland) • Along main structures / Fa

  28. Slide 28: Corporate Social Responsibility

    Corporate Social Responsibility Water for Communities • Support communities by establishing water and sanitation services • Over $650,000 raised and spent to date for water projects / Ryan’s Well Foundation Education and Training • $190,000 invested to date • Collaborative research with Universities

  29. Slide 29: Comparables

    Comparables Orezone provides upside opportunity 9.0 Millions of Ounces of Gold $185 8.0 Enterprise Value $130 7.0 per Ounce 6.0 $50 $82 50 5.0 $55 Inferred 4.0 M&I 3.0 P&P $206 $289 2.0 1.0 0.0 Ampella Gryphon Orezone Keegan Volta Rainy River Perseus 2 .0 g g/t 2.1 1.0 1.1 1.0 1.0 1.1 Average g Grad

  30. Slide 30: Growing Analyst Coverage

    Growing Analyst Coverage Target Institution` Analyst Update (CDN) Cosmos Chiu Jun-2011 $7.50 Nicholas Campbell J n 2011 Jun-2011 $6 75 $6.75 Brad Humphrey Apr-2011 $6.10 Andrew Breichmanas Jun-2011 $5.50 Brian Christie Jun-2011 $5.00 30

  31. Slide 31: Orezone Gold Corporation

    Orezone Gold Corporation 290 Picton Avenue, Suite 201 Ottawa, Ontario, Canada www.orezone.com info@orezone.com Toll Free: 1-888-673-0663 Tel: 1-613-241-3699