Diatreme Resources Limited · ASX:DRX

Diatreme Resources — Mineral Sands Conference 2016

33 slides from Diatreme Resources's conference presentation, March 2016

  1. Slide 1: Mineral Sands Conference – Diatreme Golden Sands

    Slide 1: Mineral Sands Conference – Diatreme Golden Sands

    Mineral Sands Conference Melbourne – March 2016 DIATREME – GOLDEN SANDS

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    DISCLAIMER the style of mineralisation and type of deposit under consideration DISCLAIMER and to the activity which he has undertaken to qualify as a Competent This presentation contains certain forward-looking statements and Person as defined in the 2012 Edition of the ‘Australasian Code for foreca

  3. Slide 3: Presentation Outline

    Slide 3: Presentation Outline

    Presentation Outline Diatreme Resources Experience counts Cyclone Project Key milestones delivered Mineral sands outlook Zircon supply deficit forecast Strong project pipeline Tick Hill, Cape Bedford Conclusion Diatreme ready to go

  4. Slide 4: Experienced Team

    Slide 4: Experienced Team

    Experienced Team Experienced management team focused on streamlining operations with focus on key projects: Neil McIntyre – CEO, 25yrs experience in banking, finance, resources Ian Reudavey – Chief Geologist, 25yrs in exploration & mining, 15yrs mineral sands Phil McMurtrie – Project Manager, 40yrs

  5. Slide 5: Skin in the game

    Slide 5: Skin in the game

    Skin in the game DRX— Capital Structure Directors Position Shares on Issue 809.8 Million William Wang Chairman Options on Issue (Listed) 0 Million Andrew Tsang Non Executive Director Options on Issue (Unlisted) 41.3 Million Daniel Zhuang Non Executive Director Share Price (20th March 2016) A$0.015 M

  6. Slide 6: Australian Focus

    Slide 6: Australian Focus

    Australian Focus Mineral Sands Cape Bedford Metals Tick Hill Clermont Grays Hill Cyclone

  7. Slide 7: Diatreme's Flagship – Cyclone Project, WA

    Slide 7: Diatreme's Flagship – Cyclone Project, WA

    Diatreme’s Flagship – Cyclone Project, WA

  8. Slide 8: Cyclone Project – Investment Fundamentals

    Slide 8: Cyclone Project – Investment Fundamentals

    Cyclone Project – Investment Fundamentals • JORC Resource: Currently 211Mt @ 2.3% HM (Cyclone + Cyclone Extended) • JORC Reserve: Cyclone 140Mt @ 2.5% HM containing 1 Mt Zircon; • CAPEX of $A146 million and annual average OPEX of $A80 million (reductions in CAPEX of $A77 million by adoption of best

  9. Slide 9: Cyclone Project Builds Momentum

    Slide 9: Cyclone Project Builds Momentum

    Cyclone Project Builds Momentum Water Supply Extensive groundwater aquifer discovered beneath Cyclone Dec 2013. First bore complete (>40 l/s). Pump test required for bore-field design. Mine and Haul Road Environmental studies complete and Public Environment Report submitted in November 2014; PER pro

  10. Slide 10: Cyclone Mining Lease & Site Layout

    Slide 10: Cyclone Mining Lease & Site Layout

    Cyclone Mining Lease & Site Layout Mining Lease M69/141 has been granted for the Cyclone Ore Reserve (dark red) and the operational activities that will occur around it. These activities include wet concentrating, tailings disposal, HMC stockpiles, offices, workshops, infrastructure and services. Cy

  11. Slide 11: Cyclone Project Milestones

    Slide 11: Cyclone Project Milestones

    Cyclone Project Milestones Schedule Date Pre-Feasibility Study Completed - March 2012 Definitive Feasibility Study (most permits) Q3 2016 Project Financing Q1 2017 Construction & Development Q3 2017 Mining & Production Q2 2018

  12. Slide 12: Proposed Mining Methods

    Slide 12: Proposed Mining Methods

    Proposed Mining Methods —— a CYCLONE DEPOSIT Year 2 Rehabilitation Slurry Pipeline . Diatreme Resources Limited

  13. Slide 13: PFS Mining Proposal

    Slide 13: PFS Mining Proposal

    PFS Mining Proposal Strip Ratio 1.1: 1 Mining Rate (Dry) 1,300 tonnes per hour – 2 x Dozer traps Mine Site 26 Tonnes / Hour HMC production Wet Concentration Plant Product 147,000 t PA @ 98.5% HM Concentrate Transport - Road 240km - 4 trucks x 110 tonnes to Forrest Transport - Rail 1,000km OPTIONS Mi

  14. Slide 14: Preferred Transport Option

    Slide 14: Preferred Transport Option

    Preferred Transport Option HMC loaded into containers at Cyclone. 33 tonne per container. 240 kilometre truck transport by road CYCLONE 1,100 kilometre rail transport from from Cyclone to Forrest rail siding in 100 Forrest siding to Port Pirie in 3,000 Road Rail tonne loads. tonne loads Forrest Pert

  15. Slide 15: Cyclone Project 2016 Financial Estimates

    Slide 15: Cyclone Project 2016 Financial Estimates

    Cyclone Project 2016 Financial Estimates • Cyclone Project including Cyclone Extended • Evaluation based on sale of HMC CIF China • 14 year mine life at 10 Mt per year • Average annual production of 155 kt HMC (A$139 M/year) • A$146M capital cost estimate and annual operating cost A$80M HMC Price (U

  16. Slide 16: DRX Recent Significant Announcements

    Slide 16: DRX Recent Significant Announcements

    DRX Recent Significant Announcements • Dec. 2015: Cyclone Ore Reserve increased by 47%, mine life lengthened to 14 years following incorporation of acquired Cyclone Extended resource • Quarterly report Jan. 2016: Project substantially de-risked, with award of Mining Lease, agreement with Traditional

  17. Slide 17: Cyclone Project Fundamentals

    Slide 17: Cyclone Project Fundamentals

    Cyclone Project Fundamentals • Tertiary Beach Strandline Deposit – Thick, multiple strands resulting in broad mining widths (~400m) and 1:1 strip ratio – Low slimes (4.5% -53µm) – Low oversize (5.1% +2mm) – Sandy ore (d50 of 225µm for Beach) – Coarse grained HM (d50 of 170µm for Beach) • High Value

  18. Slide 18: Cyclone Project Fundamentals

    Slide 18: Cyclone Project Fundamentals

    Cyclone Project Fundamentals • Sufficient reserves to support extensive mine life – 14 years at 10Mt pa – Strand mineralisation gives options for high grading – Substantial resource base to support potential long term expansion • Support of Traditional Owners to develop project – Strong relationship

  19. Slide 19: Zircon Supply Deficit Forecast

    Slide 19: Zircon Supply Deficit Forecast

    Zircon Supply Deficit Forecast ZIRCON SUPPLY CHALLENGE IN 3 YEARS “Zircon from existing producers declining due to depletion and decline in grade and assemblage…Absent new investment there is a zircon supply challenge within 3 years” (Iluka Resources, 19 February 2016) MARCH 2016: CHINA RAISES GROWT

  20. Slide 20: Asia's Urbanisation Continues

    Slide 20: Asia's Urbanisation Continues

    Asia’s Urbanisation Continues Urbanisation set to increase demand for mineral sands, including zircon: WORLD BANK REPORT, JANUARY 2015 • Almost 200 million people moved to urban areas in East Asia from 2000-10 • Overall proportion of urbanites rose from 29% to 36% - but less than 1% of region’s tota

  21. Slide 21: Diatreme's Project Pipeline

    Slide 21: Diatreme's Project Pipeline

    Diatreme’s Project Pipeline

  22. Slide 22: Exploration Overview

    Slide 22: Exploration Overview

    Exploration Overview • Consolidation of exploration tenure – currently 8 exploration properties (incl. 1 application) and 4 ML, down from 29 (incl. 13 applications) in March 2014 • Mineral sands exploration tenure comprises Cyclone (WA), Yeppoon (Qld) and Cape Bedford (Qld application) • Tick Hill G

  23. Slide 23: Cape Bedford, QLD

    Slide 23: Cape Bedford, QLD

    Cape Bedford, QLD Cape Bedford Cape Bedford, QLD Silica Sand, Heavy Mineral Sands EPM Application Conditions for grant agreed with Traditional Owners Size: 554 sq. km

  24. Slide 24: Cape Bedford, QLD

    Slide 24: Cape Bedford, QLD

    Cape Bedford, QLD Large sand dune system with known silica sand and mineral sand occurrences over an area 50km x 15km in dunes up to 100m high. Historical exploration indicates HM mineralised horizons in sand mass High grade silica in previous drilling samples. Samples indicate areas with a high val

  25. Slide 25: Cape Bedford, QLD

    Slide 25: Cape Bedford, QLD

    Cape Bedford, QLD . Diatreme Resources Limited

  26. Slide 26: Cape Bedford, QLD

    Slide 26: Cape Bedford, QLD

    Cape Bedford, QLD Mineralisation on the current beach shedding from the dunes

  27. Slide 27: Cape Bedford, QLD

    Slide 27: Cape Bedford, QLD

    Cape Bedford, QLD Major dune field with high grade silica sand overlying heavy mineral sand exploration targets

  28. Slide 28: Tick Hill Gold Project, QLD

    Slide 28: Tick Hill Gold Project, QLD

    Tick Hill Gold Project, QLD Tick Hill, Qld Gold 3 Granted ML’s Tick Hill Size: 3.9 sq. km

  29. Slide 29: Tick Hill Gold Project

    Slide 29: Tick Hill Gold Project

    Tick Hill Gold Project Tick Hill Gold Mine (circa 1993) looking easterly Produced 500,000 oz. gold from 700,000 tonnes of ore at 22.6g/t Au

  30. Slide 30: Potential For Near-Term Cash Flow

    Slide 30: Potential For Near-Term Cash Flow

    Potential For Near-Term Cash Flow • Maiden Mineral Resource announced January 2016 for Tick Hill tailings material, estimated at 630kt at 1.08 g/t Au containing 680kg (22,000 troy oz) gold • Scoping Study confirms viability of standalone operation processing tailings resource; 20-month operation usi

  31. Slide 31: Diatreme – Delivering Value

    Slide 31: Diatreme – Delivering Value

    Diatreme – Delivering Value • Flagship project, Cyclone now advancing through final de-risking process as Diatreme builds a platform for further investment • Potential for near-term cash flow for shareholders from Tick Hill Gold Project tailings operation • Attractive project pipeline, including Cap

  32. Slide 32: Supplementary Information – Cyclone Resource Estimate

    Slide 32: Supplementary Information – Cyclone Resource Estimate

    Supplementary Information CYCLONE RESOURCE ESTIMATE - ASX Release 9 April 2015 HM Head Grade Material HM HM Slime OS Zircon Category cut-off Zircon HiTi Alt Ilm Si TiOx Mt % Mt % % Kt % % % % % MEASURED 2.0 69 3.7 2.55 3.6 3.8 1.05 1.17 0.48 0.82 729 MEASURED 1.5 102 3.1 3.13 3.9 4.4 0.87 0.96 0.40

  33. Slide 33: Supplementary Information – Cyclone Reserve Estimate

    Slide 33: Supplementary Information – Cyclone Reserve Estimate

    Supplementary Information CYCLONE RESERVE ESTIMATE - ASX Release 14 December 2015 Head Grade Zircon Reserve Material HM HM Slime OS cut-off Zircon Rutile Leuc HiTi Alt Ilm Si TiOx Category Mt % Mt % % Zircon % % % % % % % Kt PROBABLE 0.4 140 2.5 3.54 4.5 5.1 0.71 0.07 0.17 0.58 0.32 0.57 1,000 TOTAL

Source: Internet Archive copy of diatreme.com.au