Slide 1: Corporate Presentation
C O R P O R AT E P R E S E N T AT I O N T S X – V : I P T │ F R AN K F U R T : I K L
Slide 2: Cautionary Disclaimer
Cautionary Disclaimer Forward Looking Statements Except for historical information, this presentation may contain certain “ forward-looking” statements and information relating to IMPACT that are based on the beliefs of IMPACT management, as well as assumptions made by and information currently avai
Slide 3: Why IMPACT Silver?
Why IMPACT Silver? Profitable silver production from two 100%-owned adjacent mineral districts in south-central Mexico Corporate focus is building the Company from earnings and internal capital Strong cash position of $16.0 million as of December 31, 2012, no debt and 90% of revenues from silver Con
Slide 4: Financial Highlights – Year Ended December 31, 2012
Financial Highlights – Year Ended December 31, 2012 • Market cap: C$78 Million • Warrants: Nil • Cash position: C$16.0 Million • Debt: Nil • Shares outstanding: 68M (FD 75M) • Cash flow per share²: $0.05 ($000’000’s CDN except of EPS) 2012 2011 2010 2009 Revenue $15.9 $24.3 $16.7 $12.2 Mine operatin
Slide 5: Board of Directors
Board of Directors Frederick W. Davidson, CA – President & CEO, Director • 35+ years mining & corporate finance experience • Founding President of IMPACT Silver Corp. & Energold Drilling Corp. • Held senior management positions at Erickson Gold Mines Ltd. and Mt. Skukum Gold Mines. George A. Gorzyns
Slide 6: Project Location & Overview
Project Location & Overview District Location in Mexico Central zone of land package 4
Slide 7: Growth in Production
Growth in Production Mines in Production • San Ramon Mine • Capire Mine (open-pit) • Noche Buena Mine • Cuchara-Oscar Mine Dec 31 Dec 31 Dec 31 Dec 31 2012 2011 2010 2009 Silver production (oz) 620,515 833,607 750,259 823,571 Gold production (oz) 629 676 600 810 Lead production (t) 463 731 734 969 Z
Slide 8: Zacualpan & Capire Silver Districts
Zacualpan & Capire Silver Districts Zacualpan District Capire District Valle de Oro Area Production in 2013: • San Ramon Mine • Noche Buena Mine • Cuchara-Oscar Mine • Capire Mine Exploration: • Valle de Oro area El Gigante Vein Carlos Pacheco Vein Huatecosco Vein • Zacualpan District La Condesa Vei
Slide 9: Royal Mines of Zacualpan – Prolific Mining History
Royal Mines of Zacualpan – Prolific Mining History The Royal Mines of Zacualpan is one of the oldest mining districts in the Americas, with 485 years of recorded mining history IMPACT bought the Zacualpan assets in 2006 and consolidated ownership of the entire district for the first time in its hist
Slide 10: One Land Package, Two Production Centres
One Land Package, Two Production Centres Guadalupe Production Centre Capire Production Centre The Guadalupe Processing Plant is rated at 500 The Capire pilot plant is rated at 200 tpd with the tpd and has been the main production centre potential to produce 200,000 ounces of silver per since 2006. y
Slide 11: One Land Package, Multiple Mines
One Land Package, Multiple Mines San Ramon Mine – Restarted production in early 2008. Currently 53% of total production. Large veins and stockworks of high grade epithermal mineralization. Noche Buena Mine – Commenced production in 2010. Currently 31% of total production. Large epithermal veins loca
Slide 12: New Mine Production: Cuchara-Oscar Mine
New Mine Production: Cuchara-Oscar Mine Oscar is a high-grade silver vein corridor linking the past-producing Cuchara Mine and the Santa Lucia zone Production at Cuchara-Oscar began in February 2013, with mineralization feeding the nearby Guadalupe Mill Utilizing the legacy Cuchara Mine infrastructu
Slide 13: Cuchara-Oscar & Santa Lucia Zone Drill Highlights
Cuchara-Oscar & Santa Lucia Zone Drill Highlights A Selection of Oscar Vein Drill Highlights Drill Hole To (m) From (m) Interval (m) Ag (g/t) Au (g/t) Pb (%) Zn (%) Z11-64 36.60 43.20 6.60 223 0.08 0.18 0.52 Z11-69 0.70 3.35 2.65 408 0.62 0.73 1.12 Z11-74 21.35 22.35 1.00 1,875 0.74 2.65 6.88 Z12-05
Slide 14: New Capire Mine and Production Centre
New Capire Mine and Production Centre Area of defined N Open-pit NI 43-101 Resource 200 tpd pilot mill 3D model of Remains planned open for open-pit expansion Mill Tailings facility Capire open-pit 3D model Capire open-pit Mine and Pilot Plant 2012 2015 & 2016 2013 & 2014 Construction Define plans t
Slide 15: NI 43-101 Mineral Resource Estimate – Capire Mine
NI 43-101 Mineral Resource Estimate – Capire Mine Published: February 2011 Metal Content for Capire Mine Ag (oz) Au (oz) Cu (lb) Pb (lbs) Zn (lbs) Measured 3,529,969 14,146 3,389,275 18,234,678 46,140,820 Indicated 3,694,066 16,300 3,693,733 19,029,800 49,522,173 Measured & Indicated (M&I) 7,224,035
Slide 16: Recent Capire Drill Highlights
Recent Capire Drill Highlights Drill From To Interval Ag Au Pb Zn Cu Hole (m) (m) (m) (g/t) (g/t) (%) (%) (%) C12-06 78.25 80.30 2.05 507 1.81 2.20 4.02 0.41 including 79.30 80.30 1.00 929 3.27 2.77 5.27 0.63 and 105.70 110.80 5.10 183 0.20 1.05 2.45 0.13 C12-21 83.35 110.10 16.75 153 0.40 1.14 2.71
Slide 17: Capire Exploration
Capire Exploration VMS mineralization in Capire District is predominantly silver-rich with zinc, lead, copper and gold credits District covers the same stratigraphy as the Campo Morado VMS belt, where Nyrstar N.V. is in commercial production on the G-9 deposit Several VMS targets in close proximity
Slide 18: Geology
Geology Veins in the METAL ZONING IN ORE SHOOTS Zacualpan Depth Strike Length Mining Level District tend to be 150-420 m (500-1400 ft) silver-rich near Surface (0m / 0 ft) Silver-rich at top Cuchara-Oscar Mine the top (commonly 1,000+ g/t) 200 – 1,000+ g/t Ag Noche Buena Mine Increasing San Ramon Mi
Slide 19: Valle de Oro – Drill Highlights
Valle de Oro – Drill Highlights A Selection of Carlos Pacheco Drill Highlights Drill Hole From (m) To (m) Interval (m) Au (g/t) Ag (g/t) Cu (%) Z08-68 Top of intercept - 85.74 2.90 19.6 68 0.29 including Top of intercept - 85.74 1.0 49.7 59 0.31 Z12-13 192.30 199.00 6.70 3.84 28 0.54 including 192.3
Slide 20: Rapid Exploration To Mine Development
Rapid Exploration To Mine Development A cornerstone of IMPACT’s success has been rapid mine development to increase mill throughput and generate near-term cash flow EXPLORATION AND MINE DEVELOPMENT PROCESS FLOWCHART: RESEARCH FIELD WORK DRILLING MINE DEVELOPMENT MINE Compile old Surface & Drilling i
Slide 21: Exploration Targets
Exploration Targets An abundance of attractive exploration targets to drive organic growth and potentially advance into production Zacualpan District Capire District • Mirasol • Cruz Blanca • La Condesa • Santa Rita • Santa Efigenia • Manto Rico • Guadalupe Valle de Oro Area Dominican Republic • Car
Slide 22: Summary of Operations
Summary of Operations IMPACT’s goal is to build a multimillion ounce precious metals producer with multiple mines feeding multiple processing centers 1. Zacualpan District • The San Ramon, Noche Buena, Cuchara- Oscar Mines currently feed the 500-tpd Guadalupe Processing Plant 1 2. Capire Production
Slide 23: Future Plans & Goals 2014 & Onward
Future Plans & Goals 2014 & Onward • Define expansion plan 2013 for the Capire Mine and Processing Centre • Begin production at both the Cuchara-Oscar Mine (completed) and the Capire Mine and Processing • Continue exploration and Centre (completed) expansion of mining activities with the aim to esta
Slide 24: Explore. Produce. Profit!
Why IMPACT Silver? Strong cash position & zero debt Expanding silver Proven history of production profitable mining with two new success mines put production in Explore. Q1 2013 Produce. Profit! Tight share Numerous structure and small exploration market cap for a targets to This statue of a miner i
Slide 25: Contact Us
Contact Us Telephone: 1 604 681 0172 Email: inquiries@impactsilver.com www.impactsilver.com TSX-V: IPT