Denbury — Investor Day (December 2022)
40 slides from Denbury's investor day presentation, Dec 13, 2022
Slide 1: Carbon Capture, Utilization, and Storage (CCUS) Business Outlook
Carbon Capture, Utilization, and Storage (CCUS) Business Outlook
Slide 2: Today's Agenda
2 TODAY’S AGENDA Opening Comments Mark Allen CCUS Strategy / Overview Chris Kendall Commercial Development Nik Wood Outlook / Summary Chris Kendall Q&A DEN Management
Slide 3: Cautionary Statements
Cautionary Statements 3Denbury Inc. Forward-Looking Statements: The data and/or statements contained in this presentation and the accompanying webcast that are not historical facts, including, but not limited to, statements regarding possible or assumed future cash flows and EBITDA (a non-GAAP measu
Slide 4: CCUS Strategy / Overview
4 CCUS Strategy / Overview Chris Kendall Director, President and Chief Executive Officer
Slide 5: Denbury – A Unique Carbon Solutions Company
MT ND WY TX LA MS DENBURY – A Unique Carbon Solutions Company 5Denbury Inc. Enterprise value: $4.1 Bn YE21 Oil & gas reserves: 192 MMBoe 2022E Sales volumes: ~47.5 MBoe/d Existing CO2 pipelines: 1,300+ Miles 2022E Total CO2 sourced: 14 Mmtpa; ~30% industrial 2021 Scope 1, 2 emissions: Net negative 2
Slide 6: CCUS – A Proven Pathway to Significantly Reduce CO2 Emissions
CCUS – A Proven Pathway to Significantly Reduce CO2 Emissions 6Denbury Inc. Denbury Owned / Managed Processes CAPTURE TRANSPORT STORE / UTILIZE MONITOR / VERIFY SEQUESTRATION OTHER USESENHANCED OIL RECOVERY (EOR) CCUS is an effective, low-cost solution using proven technology to capture CO2 emission
Slide 7: Decarbonization Relies on CCUS
Decarbonization Relies on CCUS 7Denbury Inc. Source: International Energy Agency (2022), Net Zero by 2050, IEA, Paris • Massive expansion in CCUS to meet IEA Net Zero Emissions (NZE) Scenario – CCUS identified as 2nd largest contributor to NZE (2021) behind wind & solar • CO2 capture largely driven
Slide 8: Bipartisan Support for CCUS Development
Bipartisan Support for CCUS Development 8Denbury Inc. Infrastructure Investment and Jobs Act – approved December 2021 • $6.5 B in carbon management funding – carbon capture technology, carbon storage validation, carbon utilization, direct air capture • Office of Clean Energy – $3.5 B carbon capture
Slide 9: Increasing CCUS Scale With IRA and Technology
0 10 20 30 40 50 60 70 80 90 A m m o n ia C h e m ic a ls C e m e n t R e fi n e ri e s G a s P o w e r S te e l P e tr o c h e m C o a l P o w e r Industry Capture Cost per Metric Ton $ per tonne Current §45Q Previous §45Q Source: Great Plains Institute, Transport Infrastructure for Carbon Capture
Slide 10: Substantial Anticipated Market Growth for Ammonia
Substantial Anticipated Market Growth for Ammonia 10Denbury Inc. 2020 2050 IEA Net Zero Emissions (NZE) Energy/hydrogen carrier Power generation Marine fuel Traditional demand Blue Ammonia Ammonia production whereby CO2 byproduct is captured and stored securely underground 185 575 Annual Global Ammo
Slide 11: U.S. Gulf Coast – A World-class CCUS Opportunity
11Denbury Inc. • The Gulf Coast has one of the highest concentrations of stationary CO2 emissions • Advantaged for greenfield projects – Access to low-cost natural gas feedstock, waterways and deepwater ports, supportive regulatory policy • Expandable CO2 pipeline infrastructure already in place – D
Slide 12: Denbury Carbon Solutions Strategy
Denbury Carbon Solutions Strategy 12Denbury Inc. Advancing decarbonization by providing the industry’s most efficient, most reliable CCUS service network; driving value for our communities and our stakeholders ESTABLISH FIRST MOVER ADVANTAGE; LEVERAGE EXISTING CO2 ASSETS AND SKILLS CAPTURE SIGNIFICA
Slide 13: We are Best Positioned to Lead in CCUS
We are Best Positioned to Lead in CCUS 13Denbury Inc. Focused Strategy Financial Strength Advantaged Infrastructure Deep Expertise Denbury combines four key elements for CCUS success Focused Strategy • Historic CO2 EOR operations underpin future growth strategy centered on CCUS Advantaged Infrastruc
Slide 14: Substantial DEN Growth from Extensive CCUS Negotiations
Substantial DEN Growth from Extensive CCUS Negotiations Outlook for DEN CCUS Volumes CO2 transport & storage volumes (Mmtpa) 14Denbury Inc. 0 25 50 75 100 125 Current Agreements Ongoing Negotiations 2030 Plan Future Potential Actively engaged with customers covering ~55 Mmtpa of brownfield / greenfi
Slide 15: Key Takeaways from Today
Key Takeaways from Today 15Denbury Inc. • DEN U.S. Gulf Coast CO2 pipeline network expandable to transport ~150 Mmtpa for long- term storage • 2 new sequestration sites in MS and LA expand portfolio to ~ 2 B tonnes; First Class VI permit submitted in November 2022 • DEN outlook for 2030E Volumes 50
Slide 16: Sustainably meeting energy needs – now and into the future
Sustainably meeting energy needs – now and into the future
Slide 17: Commercial Development
17 Commercial Development Emissions / Pipelines / Storage Nik Wood Sr. Vice President, CCUS
Slide 18: U.S. Gulf Coast – Major Source of Existing CO2 Emissions
70 58 26 22 14 11 P o w e r G e n P e tr o c h e m R e fi n in g N G P ro c e s s in g H y d ro g e n A m m o n ia U.S. Gulf Coast – Major Source of Existing CO2 Emissions Denbury Inc. 18 U.S. Gulf Coast Emissions w/in 30 Miles of DEN Pipelines CO2 (Mmtpa) ~240 Mmtpa within 30 miles of DEN Gulf Coas
Slide 19: Rocky Mountains – An Emerging CCUS Opportunity
Denbury CO2 pipelines Other CO2 pipelines Stationary CO2 emissions Rocky Mountains – An Emerging CCUS Opportunity Denbury Inc. 19 Source: 2021 EPA Greenhouse Gas Reporting Program data MT ND WY • Nearby emissions primarily from power generation – 9 Mmtpa existing with multiple proposed greenfield pr
Slide 20: CCUS Commercial Structures
Types of Emissions Agreements Transportation Transportation & Storage Capture, Transportation, Storage Leverage DEN pipeline system to move CO2 to 3rd party storage Connect lateral to industrial customer; move CO2 to DEN owned and operated secure storage Turnkey operation for customers who prefer fu
Slide 21: Existing Transport & Storage Agreements
20 Mmtpa Under Existing Transport & Storage Agreements 2 2 5 7 19 20 3Q21 4Q21 1Q22 2Q22 3Q22 4Q22 To-date DEN executed agreements Planned location Industry type CO2 volume (Mmtpa) Expected start date Wyoming hydrogen facility WY Hydrogen Up to 1 2024 / 2025 Infinium S TX Low carbon fuels 1.5 2025 G
Slide 22: Clean Hydrogen Works – Ascension Clean Energy Project
Clean Hydrogen Works – Ascension Clean Energy Project 22 FEED Study Sign Offtake Agreements Secure Capital Commitment Final Design & Construction On Production 2024 Final investment decision 2027 Plant commission & start up Block 1 Timeline 1,700-acre site – West bank of Mississippi River in Donalds
Slide 23: DEN Competitive Advantage – CO2 Transportation
DEN Competitive Advantage – CO2 Transportation 23Denbury Inc. • >1,300 miles of existing DEN CO2 pipelines (approximately 25% (1) of existing U.S. total) – Specifically built for purpose of moving CO2 – High efficiency and flexibility through supercritical operating pressure w/ ANSI 900 rating • Tra
Slide 24: Current Flow of CO2 Through DEN Gulf Coast Pipeline System
Current Flow of CO2 Through DEN Gulf Coast Pipeline System 24Denbury Inc. Source: 2021 EPA Greenhouse Gas Reporting Program data Green Pipeline current capacity 16 Mmtpa Pipeline Size (in) Distance (miles) Green 24 320 NEJD 20 183 Delta 24 108 Free State 20 86 West Gwinville 18 51 Other Va
Slide 25: Network Approach Significantly Expands Green Pipeline Capacity
Network Approach Significantly Expands Green Pipeline Capacity 25Denbury Inc. Green Pipeline Capacity CO2 (Mmtpa) • Green Pipeline capacity expandable to >50 Mmtpa; Network approach provides greatest reliability and volume capacity – Emissions can move multiple directions on same pipeline, subject t
Slide 26: Future Potential – Optimized Network to Maximize CO2 Flows
Future Potential – Optimized Network to Maximize CO2 Flows 26Denbury Inc. Source: 2021 EPA Greenhouse Gas Reporting Program data Denbury CO2 pipelines Potential future Denbury CO2 pipeline Natural CO2 source Potential future CO2 source Denbury – EOR production Potential future Denbury sequestration
Slide 27: EOR Provides Large-scale CO2 Associated Storage Today
EOR Provides Large-scale CO2 Associated Storage Today • More than 20 active EOR floods connected to DEN pipeline infrastructure – Cedar Creek Anticline EOR began injection in 1H22 (remains on schedule for production response in 2H23) • DEN Class II injection for 2021 totaled approximately 70 Mmtpa (
Slide 28: The Most Environmentally Friendly Oil on the Planet
The Most Environmentally Friendly Oil on the Planet 28Denbury Inc. • Petroleum-based fuels remain a significant contributor to the global economy in all IEA scenarios • Blue oil (negative CI score) and Electrofuels (net zero target) are direct drop-in fuels without modifications to infrastructure Ca
Slide 29: Alliance with Infinium to Deliver Low-Carbon Electrofuels
Alliance with Infinium to Deliver Low-Carbon Electrofuels Denbury Inc. 29 Renewable power and water produce green hydrogen Green hydrogen & CO2 converted to premium transportation fuels using Infinium proprietary technology Result is net-zero carbon jet and diesel fuel for use in existing modes of t
Slide 30: DEN Competitive Advantage – CO2 Storage
DEN Competitive Advantage – CO2 Storage 30Denbury Inc. • 20+ years of CO2 injection and monitoring through EOR provides technical leadership – Multiple large-scale EOR developments and CO2 pipeline projects – Extensive subsurface modeling and monitoring skillsets used in EOR is highly adaptable to C
Slide 31: Advancing ~2 B Metric Tons of CO2 Sequestration Projects
(1) GCMP (2) (3) Aries, Gemini (4) Pegasus (5) Orion (6) Draco (7) Leo Potential storage capacity (million metric tons) 400 300 500 300 250 275 Anticipated injection capacity (Mmtpa) 5-10 10-20 10-20+ 10-20 5-10 5-10 Distance to DEN pipeline (miles) 25 5,10 95 90 25 0 Acreage 850 29,000 84,000 75,00
Slide 32: Progressing Safe and Secure CO2 Storage
Progressing Safe and Secure CO2 Storage 32Denbury Inc. • Seismic data interpretation – identify key horizons, reservoir characteristics and initial trapping mechanisms • Evaluation of existing wellbores – determine if well intervention is necessary prior to CO2 injection • Geologic model constructio
Slide 33: Well Positioned to Deliver on Class VI Development
Well Positioned to Deliver on Class VI Development 33Denbury Inc. DEN Clear Leader in Class II CO2 Injection >750 CO2 injection wells operating in the U.S. Direct pressure monitoring gauge Top of cement required above USDW Class II Well Class VI Well Highly similar construction Class II vs. Class VI
Slide 34: Extensive Depth of Experience in Managing CO2
Extensive Depth of Experience in Managing CO2 • Surface and Groundwater – LIDAR – Strain gauges and inclinometers – Aerial and visual ground surveillance – Seismicity monitoring – Groundwater and above confining zone geochemical analysis • Wellbore Surveillance – Evaluate well conditions with in-hou
Slide 35: Example DEN CO2 Sequestration Site
O&G/EOR Example unit area Example DEN CO2 Sequestration Site • 20-year injection life @ 5 – 10 Mmtpa • 5 – 10 injection wells – avg. rate 0.5 – 1.5 Mmtpa per well • Estimated capex $2 – 4 per tonne – acquisition cost, seismic, wells (injection / monitoring), lateral pipeline, distribution network, a
Slide 36: Commercial Development – Forward Focus
2023 • Continue to capture emissions market and add sequestration sites to the portfolio • Drill stratigraphic test wells and submit additional Class VI storage permits • Purchase long-lead items for network buildout • Carbon capture technology investments / partnerships 2026 and beyond • Significan
Slide 37: Outlook / Summary
37 Outlook / Summary Chris Kendall Director, President and Chief Executive Officer
Slide 38: Projecting Substantial Growth in CCUS Volumes and EBITDA
0 200 400 600 800 1000 Projecting Substantial Growth in CCUS Volumes and EBITDA 38Denbury Inc. • Initial volumes anticipated in 2025; 50 – 70 Mmtpa projected 2030 avg. (~50/50 brownfield/greenfield split) • Cumulative capital investments estimated $1.6 – $2 B from 2023 to 2030; – Avg. $200 – 250 MM
Slide 39: Key Takeaways from Today
Key Takeaways from Today 39Denbury Inc. • DEN U.S. Gulf Coast CO2 pipeline network expandable to transport ~150 Mmtpa for long- term storage • 2 new sequestration sites in MS and LA expand portfolio to ~ 2 B tonnes; First Class VI permit submitted in November 2022 • DEN outlook for 2030E Volumes 50
Slide 40: Q&A Session
40 Q&A Session Chris Kendall Director, President and Chief Executive Officer Mark Allen Executive Vice President, Chief Financial Officer, Treasurer and Assistant Secretary Jim Matthews Executive Vice President, Chief Administrative Officer, General Counsel and Secretary David Sheppard Executive Vic