Steel Authority Of India Limited · NSE:SAIL

Steel Authority Of India — Q3 FY2018-19 Earnings Presentation

39 slides from Steel Authority Of India's earnings presentation, February 2019

  1. Slide 1: Performance Highlights 9M & Q3 FY 2018-19

    STEEL AUTHORITY OF INDIA LIMITED Performance Highlights 9M & Q3 FY 2018-19

  2. Slide 2: Performance Highlights: 9M FY2018-19

    PERFORMANCE HIGHLIGHTS : 9M FY2018-19  Net Sales : Rs 47944 Crore FINANCIAL  EBITDA : Rs 7806 Crore PERFORMANCE  PBT : Rs 2626 Crore  PAT : Rs 1710 Crore  Hot Metal Production : 12.842 MT  Crude Steel Production : 11.928 MT PRODUCTION & SALES  Saleable Steel Production : 10.946 MT PERFORMANCE

  3. Slide 3: Performance Highlights: Q3 FY2018-19

    PERFORMANCE HIGHLIGHTS : Q3 FY2018-19  Net Sales : Rs 15660 Crore FINANCIAL  EBITDA : Rs 2653 Crore PERFORMANCE  PBT : Rs 950 Crore  PAT : Rs 616 Crore  Hot Metal Production : 4.601 MT  Crude Steel Production : 4.281 MT PRODUCTION & SALES  Saleable Steel Production : 3.795 MT PERFORMANCE  Se

  4. Slide 4: Financial Performance: Annual Profit Trend

    FINANCIAL PERFORMANCE Annual Profit Trend 5909 5590 EBITDA 5184 4333 Cash Profit 3866 3225 PBT 2616 2583 2345 2079 PAT 672 -153 -482 -759 -1619 -2203 -2833 -4021 -4851 -7007 FY 14 FY 15 FY 16 FY 17 FY 18 All figures in Rs crore

  5. Slide 5: Financial Performance: Quarterly and Nine Monthly

    FINANCIAL PERFORMANCE 2653 2479 Quarterly 1804 1674 1560 Performance 950 848 Q3 FY 19 vs 616 554 803 Q2 FY 19 vs 82 43 Q3 FY 18 Q3 FY 19 Q2 FY 19 Q3 FY 18 All figures in Rs crore 7806 EBITDA Cash Profit 5120 Nine PBT Monthly PAT 2626 2528 1710 Performance 919 9M FY 19 vs 9M FY 18 -1297 -1945 9M FY19

  6. Slide 6: Financial Performance: Net Worth, Borrowings, Interest Cost

    FINANCIAL PERFORMANCE Annual Net Worth Annual Borrowings & Interest cost 45409 45000 41396 3500 42666 43523 40000 35141 39196 35000 31837 36009 35714 30000 25281 2823 2500 Annual 25000 2528 20000 2300 Borrowings 15000 10000 1500 Interest 1454 Cost 5000 0 968 500 FY 14 FY 15 FY 16 FY 17 FY 18 FY 14 F

  7. Slide 7: Financial Performance

    FINANCIAL PERFORMANCE Rs. Crore 9MFY19 9MFY18 Q3 FY 19 Q2 FY 19 Q3 FY 18 (INDAS Compliant figures) Sales 47944 41486 15660 16541 15190 EBITDA 7806 2528 2653 2479 1560 Depreciation 2494 2216 855 826 760 Finance Cost 2352 1906 825 771 675 PBT Before Exceptional Items 2960 -1594 973 882 126 Exceptional

  8. Slide 8: Production Performance

    PRODUCTION PERFORMANCE All figures In Million Tonne 13.9 14.1 12.9 12.8 12.4 10.46 10.95 SALEABLE STEEL PRODUCTION (incl. SSPs) FY 14 FY 15 FY 16 FY 17 FY 18 9M FY18 9M FY19 Annual 9 Monthly 13.4 13.8 10.23 10.66 12.4 12.4 11.9 SALEABLE STEEL PRODUCION (5 ISPs) 9M FY18 9M FY19 FY 14 FY 15 FY 16 FY 1

  9. Slide 9: Production Performance: 9M FY19

    PRODUCTION PERFORMANCE : 9M FY19 12.0% 1.3% CRUDE STEEL BOF 15.7% Ingot PRODUCTION EAF Route BY PROCESS THF CC 84.3% Route 86.7% SALEABLE STEEL 43.6% Commodity PRODUCTION BY PROCESS 56.4% Value Added

  10. Slide 10: Production Performance: 9M FY19 Product Mix

    PRODUCTION PERFORMANCE : 9M FY 19 SAIL 20.5% PRODUCT MIX : 52.4% 5 ISPs 27.1% 26.8% 60.5% 12.7% BSP 31.9% 68.1% DSP Flats RSP 89.8% 10.2% Longs Semis 99.5% 0.5% BSL 61.2% 38.8% ISP

  11. Slide 11: Production Performance

    PRODUCTION PERFORMANCE Parameter 9M FY H1 FY MAJOR 18-19 18-19 TECHNO-ECONOMIC Coke Rate (kg/thm) 457 460 PARAMETERS Fuel Rate (kg/thm) 562 564 Specific Energy Consumption 6.55 6.58 (GCal/TCS) BF Productivity (T/m3/day) 1.60 1.55 3 LABOUR PRODUCTIVITY (tcs/man/year) MANPOWER & 362 407 377 344 LABOUR

  12. Slide 12: Sales Performance

    SALES PERFORMANCE All figures In Million Tonne 14.1 13.1 12.1 11.7 12.1 10.34 9.98 TOTAL SALES (incl. SSPs) FY 14 FY 15 FY 16 FY 17 FY 18 9M FY 18 9M FY 19 Annual 9 Monthly 13.8 12.7 11.6 11.2 11.7 10.11 9.73 SALES OF 5 ISPs 9M FY 18 9M FY 19 FY 14 FY 15 FY 16 FY 17 FY 17

  13. Slide 13: Power Consumption – 9M FY19

    POWER CONSUMPTION – 9M FY 19 9.53% Own CPP Drawl from Grid 49.83% Purchase from Power 38.47% Exchange JV CPP 2.17%

  14. Slide 14: SAIL Stock Price Movement

    SAIL STOCK PRICE MOVEMENT SAIL's Share Price (Rs.) Sensex Points 38645 36917 35160 36068 35423 34442 32515 33149 34184 31284 37607 36194 29918 35965 36227 36257 28743 29621 34057 35322 33213 32969 31146 30922 31730 92 89 77 83 78 83 80 78 70 76 78 63 60 57 58 61 64 56 54 68 47 49 61 61 55 Closing Sh

  15. Slide 15: SAIL's Modernisation & Expansion Plan

    SAIL’s MODERNISATION & EXPANSION PLAN Actual Production Capacity After Million Tonne 2017-18 On-going Expansion Crude Steel 15.021 21.4 Saleable Steel 14.071 20.2 Technological Shift Before After Technology Expansion Expansion BOF Steel Making 79% 100% CC Route 71% 94% Pelletisation Plant No Yes Cok

  16. Slide 16: Modernisation & Expansion Plan

    MODERNISATION & EXPANSION PLAN  Production through twin-hearth furnace (THF) route to be replaced by BOF-LD converter route.  Production through Ingot – teeming route to be replaced with continuous cast production route. EXPECTED  Enhancement of Production volume by addition of 2 new 4060 m3 Blas

  17. Slide 17: Ongoing Projects (Capex)

    ONGOING PROJECTS (CAPEX) (Rs. Crore) 12191 61870 1 Expansion of existing capacity 3509 2 Value-addition / Product-mix improvement 7039 22739 3 Technological up gradation / Modernization Sustenance including de-bottlenecking, AMR & 4 Environment 39131 39131 5 Total Estimated Cost In addition, a Capex

  18. Slide 18: Capacity After Expansion

    CAPACITY AFTER EXPANSION Saleable Steel Hot Metal (MTPA) Crude Steel (MTPA) (MTPA) Plant After After After 2017-18 2017-18 2017-18 Expansion Expansion Expansion BSP 4.28 7.5 4.07 7.0 3.69 6.6 DSP 2.28 2.5 2.04 2.2 1.95 2.1 RSP 3.32 4.5 3.22 4.2 2.94 4.0 BSL 4.05 5.8 3.69 4.6 3.50 4.2 ISP 2.06 2.9 1.

  19. Slide 19: Product Mix Post Expansion – Saleable Steel

    PRODUCT MIX POST EXPANSION – SALEABLE STEEL Galvanized Products CR Coils/Sheets 7% 2% PET Products 1% Semis 9M FY 19 8% Structurals 8% HR Plates/Coils/Sh eets/skelp Bars & Rods 30% 18% Galvanized Rly Products PET 9% Products CR Products 3% PM Plates Coils/Sheets 1% 17% 11% Semis 12% Structurals HR 1

  20. Slide 20: Modernisation & Expansion Plan - Salem Steel Plant

    MODERNISATION & EXPANSION PLAN - SALEM STEEL PLANT Facilities added: •Steel melting Shop – Electric Arc Furnace (55 T); AOD Converter (60 T); Ladle Furnace (60 T); Single Strand Slab Caster. • Roll Grinder for Hot Rolling Mill • Cold Rolling Mill Complex Production (MTPA) : Item 2017-18 (Actual) Aft

  21. Slide 21: Modernisation & Expansion Plan - IISCO Steel Plant

    MODERNISATION & EXPANSION PLAN - IISCO STEEL PLANT Facilities Completed: • Raw Material Handling System • New Coke Oven Battery (0.88 Mtpa, 7 m tall) • Coke Dry Cooling Plant • Sinter Machines (3.88 Mtpa gross sinter production, 2x204 m²) • Blast Furnace 4160 m3 volume (2.7Mtpa) • 3 nos. of 150 T BO

  22. Slide 22: Modernisation & Expansion Plan - IISCO Steel Plant

    MODERNISATION & EXPANSION PLAN - IISCO STEEL PLANT New stream to produce 2.7 Mtpa of Hot Metal & 2.5 Mtpa of Crude Steel Production (MTPA) : Item 2017 -18 (Actual) After Expansion Crude Steel 1.80 2.50 Saleable Steel 1.69 2.39 The expanded capacity of IISCO Steel Plant has been dedicated to the Nat

  23. Slide 23: Current Progress of Expansion at IISCO Steel Plant

    Current Progress of Expansion at IISCO Steel Plant BURNPUR Coke Oven Battery Sinter Plant Blast Furnace BOF Converters Billet Casters Wire Rod Mill

  24. Slide 24: Modernisation & Expansion Plan – Bokaro Steel Plant

    MODERNISATION & EXPANSION PLAN– BOKARO STEEL PLANT Facilities Completed: • Re-building of Coke Oven Battery #1 & #2. • Up-gradation of Blast Furnace #2 and Stoves Up-gradation of #5 • Auxiliary Fuel Injection (CDI) in Blast Furnaces #2 & #3. • Turbo-Blower-8. • New CRM Complex (1.2 Mtpa) • Up-gradat

  25. Slide 25: Current Progress of Expansion at Bokaro Steel Plant

    Current Progress of Expansion at Bokaro Steel Plant Coke Oven Blast battery-2 Furnace-2 PLTCM Coil Packaging Line Skin Pass Mill Bell Annealing Furnace

  26. Slide 26: Modernisation & Expansion Plan – Bhilai Steel Plant

    MODERNISATION & EXPANSION PLAN– BHILAI STEEL PLANT Facilities Already Completed: • Ore Handling Plant part-A • Second Sinter Machine in Sinter Plant-3 (3.7 MTPA) • New Coke Oven Battery No. 11 (7 m tall, Capacity 0.881 mtpa) • Oxygen Plant (BOO basis) • Universal Rail Mill (1.2 MTPA) and Rail Weldin

  27. Slide 27: Current Progress of Expansion at Bhilai Steel Plant

    Current Progress of Expansion at Bhilai Steel Plant Sinter Machine Coke Oven Battery - 11 Blast Furnace - 8 Continuous Caster - 1 Bar & Rod Mill Universal Rail Mill

  28. Slide 28: Modernisation & Expansion Plan – Rourkela Steel Plant

    MODERNISATION & EXPANSION PLAN– ROURKELA STEEL PLANT Facilities Completed: • New Coke Oven Battery -6 (7 m tall, 1 x 67 ovens) • New Sinter Plant -3 (1 x 360m²) • New Blast Furnace -5, useful volume - 4060 m3 • New 3rd Single Strand Slab Caster (1.5 MTPA) • New Oxygen Plant 2x700 tpd on BOO basis •

  29. Slide 29: Current Progress of Expansion at Rourkela Steel Plant

    Current Progress of Expansion at Rourkela Steel- 3Plant SINTER PLANT Coke Oven Battery - 6 Sinter Plant - 3 1 3rd BOF Converter 3rd Slab Caster BOF Converter Blast Furnace - 5 Tapping

  30. Slide 30: Modernisation & Expansion Plan – Durgapur Steel Plant

    MODERNISATION & EXPANSION PLAN– DURGAPUR STEEL PLANT Facilities Completed: • Rebuilding of Coke Oven Battery no-2 • New Ladle Furnace (125T) • Coke Sorting & Coal Handling Plant • New Dolomite Plant (300tpd) • Bloom-cum-Round Caster 1X4 (0.75 Mtpa) • New Medium Structural Mill (1.0 Mtpa) Production

  31. Slide 31: Current Progress of Expansion at Durgapur Steel Plant

    Current Progress of Expansion at Durgapur Steel Plant Coke Oven Battery-2 Ladle Furnace-3 Bloom cum Round Caster Medium Structural Mill

  32. Slide 32: Raw Materials

    RAW MATERIALS Iron Ore Hot Metal Year Consumption Linkages of Iron Ore (mtpa) (mtpa) 2017-18 15.983 25.87 Existing Mines The capacity of existing mines at Kiriburu, Meghahatuburu, Bolani & Gua are being ramped up to meet the requirement of Iron Ore for post ongoing phase of expansion New Pellet Plan

  33. Slide 33: Raw Materials – Iron Ore

    RAW MATERIALS – Iron Ore Existing Capacity* after Mine Capacity* ongoing Remarks (mtpa) expansion (mtpa) Kiriburu 5.50 5.50 • Expansion at Kiriburu has already been completed whereas Meghathaburu is being ramped up to meet the requirement Meghathaburu 5.00 6.50 of the ongoing expansion plan. Bolani

  34. Slide 34: Raw Materials – Coal

    RAW MATERIALS – Coal Hot Metal Coking Coal Year Linkages of Coking Coal (mtpa) Requirement (mtpa) • Import Component – 86% • Over 70% of imported coal is sourced from Australia. • Indigenous: 13% 2017-18 15.983 15.392 • Domestic coal is largely sourced from Coal India Ltd. • SAIL has existing captiv

  35. Slide 35: Major Joint Ventures

    MAJOR JOINT VENTURES FOCUS AREA ALLIANCE PARTNER REMARKS  A Special Purpose Vehicle, namely, ‘Chhattisgarh Mega Steel Limited’ has been formed for setting-up STEEL an Ultra Mega Steel Plant (UMSP) in Bastar area of Chhattisgarh.  SAIL Bansal Service Center Limited – A JV with Bansal Metal Works Lt

  36. Slide 36: Major Joint Ventures

    MAJOR JOINT VENTURES FOCUS AREA ALLIANCE PARTNER REMARKS  SAIL Kobe Iron India Pvt. Ltd. – A Joint Venture Company has been formulated for setting up a 0.5 TECHNOLOGY mtpa capacity Plant for producing iron nuggets based on ITmk3 technology.  International Coal Ventures Pvt. Ltd., a SPV of 5 leadin

  37. Slide 37: Major Joint Ventures

    MAJOR JOINT VENTURES FOCUS AREA ALLIANCE PARTNER OBJECTIVE  SAIL RITES Bengal Wagon Industry Pvt. Ltd. – A WAGON Joint Venture Company has been formed with M/s MANUFACTURE RITES for setting up Wagon Manufacturing Factory at Kulti, West Bengal.  JV with Tata Steel to promote e-commerce E-PORTAL act

  38. Slide 38: Abbreviations used

    Abbreviations used • BF Blast Furnace • FOB Freight On Board • SMS Steel Melting Shop • JPC Joint Plant Committee • BOF Basic Oxygen Furnace • Kg/thm Kilo Gram Per Tonne of • THF Twin Hearth Furnace Hot Metal • EAF Electric Arc Furnace • Tpd Tonnes Per Day • BSP Bhilai Steel Plant • MT Million Tonne

  39. Slide 39: Disclaimer

    Disclaimer Statements / Data which do not relate to SAIL and are used / made in this presentation are from sources which are considered reliable and Company cannot be held for its authenticity. Further, statements describing the Company’s projections, estimates, expectations are “forward looking sta