AGL Energy Limited · ASX:AGL
AGL Energy — Corporate Update (September 2015)
25 slides from AGL Energy's corporate update, Sep 9, 2015
Slide 1: Broken Hill Solar Plant Community Information Session
Broken Hill Solar 1 Plant Community Information Session 9 September 2015
Slide 2: Agenda
2 Agenda Welcome September CIS 1 Overview of project status – AGL / First Solar 2 3 Employment 4 Project planning 5 Next meeting > AGL Broken Hill Solar Plant > 9 September 2015
Slide 3: Review actions from previous meeting
3 2. Review actions from previous meeting Action item CIS Status Who meeting 1 > AGL Broken Hill Solar Plant > 9 September 2015
Slide 4: Overview of project status
4 Overview of project status • Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 5: AGL overview of project status: Solar Plant
5 2. AGL overview of project status Solar Plant › The changing face of the Broken Hill Solar Plant » Top: January 2015 (civil work) » Middle: April 2015 (module install) » Bottom: August 2015 (module install / termination) › Installation of First Solar PV modules commenced at the start of April › Co
Slide 6: AGL overview: Connection Works
6 2. AGL overview of project status Connection Works (CPP) › 2 x 22kV transmission lines were practically complete at end of February 2015, including crossing of the ARTC rail lines. › Operating protocol with TransGrid (Network Services Provider) has been finalised and implemented. › Feeder No.2 was
Slide 7: Project Milestone – Final Module Installation
7 2. AGL overview of project status Project Milestone – Final Module Installation › We will be marking the final module installation with our key stakeholders › Broken Hill City Council, Wincen Cuy › State and Federal Government › Australian Renewable Energy Agency (ARENA) executive › AGL executives
Slide 8: Nyngan Solar Plant
8 2. AGL overview of project status Nyngan Solar Plant › Full generation (102 MW) was achieved on Saturday, 6 June 2015. > Broken Hill Solar Plant > AGL Energy > 9 September 2015
Slide 9: Nyngan Solar Plant cumulative generation
9 2. AGL overview of project status Nyngan Solar Plant › Generation @ the point of connection (commenced Saturday, 21 March 2015) › Cumulative generation at 23:30hrs on Friday, 4 Sept 2015 was 63,042.82** MWh » ** Gaps in June due to AEMO/EE SCADA – Nyngan was generation factored in cumulative total
Slide 10: Nyngan Solar Plant generation and pricing
10 2. AGL overview of project status Nyngan Solar Plant › Generation on 4-6 September 2015 (Fri-Sun) last week – pricing spike in the PM peak. › Generation from yesterday, 8 September 2015 with actual pricing and forecast pricing based on expected generation. > Broken Hill Solar Plant > AGL Energy >
Slide 11: Broken Hill Solar Plant commissioning approval
11 2. AGL overview of project status Broken Hill Solar Plant › Seeking approval from TransGrid and AEMO before commencing commissioning that will generate “commissioning energy” > Broken Hill Solar Plant > 9 September 2015
Slide 12: First Solar Project Status
12 3. First Solar Project Status > AGL Broken Hill Solar Plant > 9 September 2015
Slide 13: First Solar project status: subcontracts and procurement
13 3. First Solar project status Sub contracts: Three packages of work – civil, structural and electrical › Structural work completed in May 2015 (CTE) › Electrical work completed Sept 2015 (RCR | ODG) › Testing and commissioning activities commenced (STE, First Solar) Procurement and deliveries: De
Slide 14: First Solar project status: construction
14 3. First Solar project status Construction: › Structural work completed in May 2015 › Electrical work completed in Sept 2015 - Solar PV modules nearly complete - Above ground and underground cabling installed - Outstanding work being completed Testing & commissioning is now focus of work, in pr
Slide 15: Quality inspection photos
15 3. First Solar project status Quality inspection – solar panels Quality inspection - above ground cable installation > Broken Hill Solar Plant > 9 September 2015
Slide 16: Module installation complete, re-vegetation
16 3. First Solar project status Module installation complete Re-vegetation of land > AGL Broken Hill Solar Plant > 9 September 2015
Slide 17: Employment
17 Employment (First Solar) > Presentation title > Author > Date (Verdana 10pt)
Slide 18: Project employment
18 4. Project employment › RCR | ODG – electrical subcontractor for First Solar is now reducing headcount and preparing to demobilise by end of September. › Workers on site in the coming 1-2 months will mostly be First Solar employees and testing/commissioning specialists from STE, Motherwell, SMA I
Slide 19: Project Planning
19 Project Planning • Helena Orel (AGL) • Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 20: Project planning: community engagement
20 5. Project planning Engaging with residents, businesses and interested organisations is at the heart of what we do. › Aruma Lodge residents recently visited the site › AGL participated in the recent Chamber of Commerce Business After 5 evening on businesses and solar energy with the Office of Env
Slide 21: AGL energy deals for Broken Hill
21 5. Project planning AGL energy deals for Broken Hill businesses and residents › AGL Energy retail team has prepared energy deals specific for the Broken Hill community: › Businesses – 24% of electricity and solar, available now, $100 off first bill when signing up business and residential propert
Slide 22: Construction Community Fund
22 Construction Community Fund • Helena Orel (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 23: Construction Community Fund
23 6. Construction Community Fund › Advertisements for next round of funding will be advertised: › 12 and 26 September 2015, BDT, website, council office, post offices › Ads will run for four weeks › All applications need to be in by COB Friday 9 October › Expect to complete process (assessment / fu
Slide 24: Next meeting
24 Next meeting > Presentation title > Author > Date (Verdana 10pt)
Slide 25: Next meeting
25 7. Next meeting › Any questions? › Next meeting date › Agenda items > AGL Broken Hill Solar Plant > 9 September 2015