Harte Gold Corp

Harte Gold — Investor Presentation (May 2018)

30 slides from Harte Gold's investor presentation, May 3, 2018

  1. Slide 1: Analyst Presentation

    Analyst Presentation GOLD CORP May 3, 2018

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS This presentation contains forward-looking information under Canadian securities legislation. Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Harte Gold’s development potential and timetable of its opera

  3. Slide 3: Summary

    Summary STRICTLY CONFIDENTIAL

  4. Slide 4: Milestones for 2018

    MILESTONES FOR 2018 HARTE GOLD HAS DELIVERED ON ALL TARGETS TO-DATE  Resource update: tripled resource  Comprehensive debt financing package for up to US$70 million  PEA: $425 million pre-tax NPV5% at US$1,350/oz, 60% pre-tax IRR1  IBA signed with Pic Mobert First Nation (PMFN)  Full permitting

  5. Slide 5: Fully Funded to Production

    FULLY FUNDED TO PRODUCTION COMPREHENSIVE FINANCING PACKAGE FOR UP TO US$70 MILLION Sprott Facility  Up to US$50 million under a senior secured credit facility Appian Subordinated Loan  US$20 million loan, subordinated to Sprott facility Benefits Flexible principal and interest schedule supports r

  6. Slide 6: Phased Mine Plan Increasing to 1,400 tpd

    PHASED MINE PLAN INCREASING TO 1,400 TPD PROVIDES EARLY CASH FLOW AND LONGER TERM GROWTH Today Phase 1: 540 tpd  Low risk ramp-up to commercial production (2018 - 2019) H2 2018 H2 2019 Phase 2:  Existing surface and underground mining infrastructure is sufficient 800 tpd (2020) to support increase

  7. Slide 7: Simple Mine Design

    SIMPLE MINE DESIGN CONTINUOUS AND TABULAR ORE BODY SUPPORTS SIMPLE MINE DESIGN AND EXTRACTION Lower Zone Ore Face Sugar Zone Stope Design  Length: 50 m 8 Meter Width  15 m level interval (floor to floor)  Planned dilution: 11.6%  Unplanned dilution factored into the model: 26% Steeply dipping or

  8. Slide 8: Production Profile to +100,000 Oz/Year

    PRODUCTION PROFILE TO +100,000 Oz/Year SCALABLE MINE PLAN DESIGNED TO MATCH UNDERGROUND DEVELOPMENT Throughput and Grade 600 10.0 Throughput (ktpa) Grade (g/t Au) 450 7.5 300 5.0 150 2.5 0.0 2018 2020 2022 2024 2026 2028 Phase 1 & 2 (800 tpd) Phase 3 (1,400 tpd) Diluted Head Grade Production Forecas

  9. Slide 9: First Quartile Cash Cost Producer

    FIRST QUARTILE CASH COST PRODUCER AISC CASH COST OF US$708/OZ OVER LIFE OF MINE AISC Curve Illustrating Sugar Zone Vs. Other Selected High Grade Canadian Underground Mines Eagle River, Wesdome Sugar Zone, Harte Gold* Macassa, Kirkland Lake $3,000 Island Gold, Alamos Hope Bay, TMAC Hemlo, Barrick $2,

  10. Slide 10: Opportunities to Enhance Project Value

    OPPORTUNITIES TO ENHANCE PROJECT VALUE SEVERAL OPPORTUNTIIES NOT CAPTURED IN THE PEA $750  mining  mineable dilution, lower resource by mining costs +500,000 ? Pre-Tax NPV5% ($ Millions) $600 ounces ?  head grade: 7.0 – 8.0 g/t ? $450 $425 ? ? $344 $300 $150 US$1,250/oz US$1,350/oz Improve Head U

  11. Slide 11: Adding Additional Resource to Mine Plan

    ADDING ADDITIONAL RESOURCE TO MINE PLAN 534,000 OUNCES OF MINERAL RESOURCE NOT INCLUDED IN PEA MINE PLAN 0m 250 m 500 m 750 m 1,000 m 11 TSX: HRT

  12. Slide 12: Mine Design – Grade Distribution

    MINE DESIGN – GRADE DISTRIBUTION MINE DESIGN ILLUSTRATED BY GRADE Sugar Zone South Ramp Sugar Zone North Ramp Middle Zone Ramp Infill Drilling Underway 12 TSX: HRT

  13. Slide 13: Resource and Mine Plan

    Resource and Mine Plan STRICTLY CONFIDENTIAL

  14. Slide 14: Resource Estimate (February 2018)

    RESOURCE ESTIMATE (FEBRUARY 2018) 1.5 Moz Au INDICATED AND INFERRED RESOURCE Mineral Resource Estimate at 3.0 g/t Au Cut-Off Resource Modelling Category Grade Contained Zone Tonnes (g/t Au) Au (ounces)  Includes drilling up to December 6, 2017 Sugar Zone 2,148,000 8.6 594,700 Indicated Middle Zone

  15. Slide 15: PEA Mineable Resource Estimate

    PEA MINEABLE RESOURCE ESTIMATE 934,000 OUNCES OF POTENTIALLY MINEABLE RESOURCE FACTORED INTO PEA MINE PLAN Potentially Mineable Mineralization for Mine Planning  Potentially mineable resource: 941,000 Diluted ounces at a diluted grade of 6.5 g/t Category Contained Zone Tonnes Grade Au (ounces) (g/t

  16. Slide 16: Mine Design

    MINE DESIGN LONGHOLE STOPING PROVIDES A SAFE AND COST EFFICIENT METHOD Mine Design Parameters Longhole Stoping Mining Method Sugar Zone Middle Zone Level interval 15 m 20 m Stope strike length 50 m 30 m Limiting HR (hanging-wall) 7 7 Minimum mining width* 1.3 m true width 1.5 m true width Total 0.50

  17. Slide 17: Mine Design – Schedule

    MINE DESIGN – SCHEDULE MINE DESIGN ILLUSTRATED BY YEAR Sugar Zone South Ramp Sugar Zone North Ramp Middle Zone 17 TSX: HRT

  18. Slide 18: Process Flowsheet

    PROCESS FLOWSHEET SIMPLE FLOWSHEET WITH LOW CAPITAL AND OPERATING COSTS Flowsheet Design Process Flowsheet  Primary jaw crusher followed by secondary cone crusher  Grinding: 800 tpd ball mill  Gravity: Two Falcon concentrators  Flotation: Six TC10 Outotec flotation cells  Filtration  Tailings

  19. Slide 19: Expansion to 1,400 tpd

    EXPANSION TO 1,400 TPD  Estimate of $23 million to be spent in 2020 on expanding throughput capacity: ► Additional cone crusher ► Second ball mill in parallel ► Storage modifications and additional conveyors for the ball mill ► Three additional flotation cells ► Concentrate regrind and leaching equ

  20. Slide 20: Summary Economics

    Summary Economics STRICTLY CONFIDENTIAL

  21. Slide 21: PEA Summary

    PEA SUMMARY Input Unit Value Gold Price US$/oz $1,250 Exchange Rate CAD:USD 0.80 Total Tonnes Processed Tonnes 4,539,800 Average Annual Throughput (2019+) tpa 402,617 Diluted Head Grade g/t 6.5 Macro and Gold Recovery % 95.4% Physical Parameters Mine Life Years 12 Total Ounces Recovered Ounces 904,0

  22. Slide 22: Operating Costs

    OPERATING COSTS OPERATING COSTS AND CONDITIONS WELL DEFINED THROUGH 70KT BULK SAMPLE PROCESS Underground Contract Mining Operating Cost Profile (US$/oz Au) Mining  Detailed bottom-up cost analysis, considering 1,200 Processing 953 the following: 1,000 G&A 79 US$/oz Au ► Technica contract rates (bul

  23. Slide 23: Capital Costs

    CAPITAL COSTS EXISTING MINE DEVELOPMENT REDUCES CAPITAL COSTS, ACCELERATES TIMELINE TO PRODUCTION Costs Remaining for 2018 Capital Cost Profile – as at March 31st  Minimal underground development 80 Underground Development Process Plant Construction Infrastructure Tailings Expansion ► Six months of

  24. Slide 24: Debt Financing Package

    DEBT FINANCING PACKAGE Sprott Facility  Up to US$50 million senior secured credit facility ► Tranche I: US$20 million ► Subsequent US$10 million tranches, as required  5 year term  Interest rate LIBOR + 7.5% Appian Subordinated Loan  US$20 million subordinated loan  6 month term, option to exte

  25. Slide 25: NPV and IRR Summary

    NPV AND IRR SUMMARY Gold Price Sensitivities Unit US$1,150/oz PEA Pricing US$1,350/oz Macro Parameters Gold Price US$/oz $1,150 $1,250 $1,350 Exchange Rate CAD:USD 0.80 0.80 0.80 Pre-Tax NPV and IRR NPV @ 5% M C$ $263 $344 $425 IRR % 40% 50% 60% Post-Tax NPV and IRR NPV @ 5% M C$ $189 $244 $299 IRR

  26. Slide 26: Environmental and Permitting

    Environmental and Permitting STRICTLY CONFIDENTIAL

  27. Slide 27: IBA Signed with Pic Mobert First Nation

    IBA SIGNED WITH PIC MOBERT FIRST NATION  Impact Benefits Agreement (“IBA”) signed with Pic Mobert First Nation (“PMFN”)  Applies to other future mines that may be developed on the 80,000 hectare Sugar Zone property  Proves a framework within which Harte Gold and PMFN will continue to work togethe

  28. Slide 28: Summary

    Summary STRICTLY CONFIDENTIAL

  29. Slide 29: Key Takeaways

    KEY TAKEAWAYS  Fully funded to production  Scalable mine plan: 1,400 tpd, +100,000 ounces of annual production  Simple mine design, well understood orebody. 100,000 tonnes mined to-date  AISC US$708/oz – first quartile cash cost producer  $425 million pre-tax NPV5%  Several opportunities to co

  30. Slide 30: Analyst Presentation

    Analyst Presentation May 3, 2018 GOLD CORP 30 TSX: HRT

Harte Gold — Investor Presentation (May 2018) on 6ix