Azure Power Global Limited · OTC:AZREF
Azure Power Global — Q2 FY2020 Earnings Presentation
33 slides from Azure Power Global's earnings presentation, Nov 15, 2019
Slide 1: Fiscal Second Quarter 2020 Earnings Presentation
3 GW+ Pan India portfolio of solar assets in 24 States India’s first private grid connected MW solar plant India’s first distributed rooftop solar project over one megawatt Issued India’s first solar Green Bond Fiscal Second Quarter 2020 Ended September 30, 2019 Earnings Presentation November 15, 20
Slide 2: Disclaimer
Disclaimer Forward-Looking Statements This information contains forward-looking statements within the meaning of Section 21E of the Securities Exchange Act of 1934 and the Private Securities Litigation Reform Act of 1995, including statements regarding our future financial and operating guidance, op
Slide 3: Agenda
Agenda Company Update Updates on Management Initiatives To Create Shareholder Value Industry Update Fiscal Second Quarter 2020 Financial Results Financial Forecasts and Liquidity Update Reiterating FY 2020 Revenue and Refining MW Operating Guidance 3|Copyright © 2019 Azure Power |www.azurepower.com
Slide 4: 3,370 MW Committed Portfolio With 83% in High Radiation Zone
3,370(1) MW Committed Portfolio With 83% of Portfolio in High Radiation Zone ~83% (2) in High Radiation Zone ~14%(2) in Mid Radiation Zone Focus on Strong Counterparty Credit Punjab (214 MW) 214 MW Rajasthan (1,745 MW) 475 MW Uttar Pradesh (100 MW) 100 MW 1,270 MW BBB- & above Gujarat (270 MW) Bihar
Slide 5: Management Commitment to Capital Discipline
Management Commitment to Capital Discipline Capital discipline is the foundation to our success 1 Delivery of projects on time and on budget 2 Enhance returns on invested capital with efficiency gains and cost optimisation 3 Optimize capital structure to lower risk and cost of capital 4 Risk mitigat
Slide 6: Delivery of Current Pipeline On Time and On Budget
Delivery of Current Pipeline On Time and On Budget 1 189 MW(1) Commissioned in Q2 FY20 Rajasthan 5 Maharashtra 3 Azure Roof Power Projects 50 MWs 130 MWs 9 MWs PPA Duration: 25 Years PPA Duration: 25 Years PPA Duration: 25 Years Tariff: 2.48 INR/kWh (~US 3.6¢/kWh)(2) Tariff:2.72 INR/kWh (~US 3.9¢/kW
Slide 7: Delivery of Current Pipeline On Time and On Budget
Delivery of Current Pipeline On Time and On Budget 1 117 MWs Projects Under-Construction Fencing work Rooftop project under construction Assam 1|90 MW Azure Roof Power Projects |27 MW Tariff: 3.34 INR/kWh (US 4.7¢ / kWh) Tariff: 4.50 - 6.19 INR/kWh (US 6.5 – 9.0¢ / kWh) Expected COD : Q1 FY21 Expect
Slide 8: Enhance Returns on Invested Capital with Efficiency Gains and Cost Optimisation
Enhance Returns on Invested Capital with Efficiency Gains and Cost Optimisation 2 Ongoing review of efficiency and costs. Have found meaningful opportunities Identified meaningful future capital cost savings Opportunities to reduce cost of capital Wider deployment of more efficient cleaning technolo
Slide 9: Optimize Capital Structure to Lower Risk and Cost of Capital
Optimize Capital Structure to Lower Risk and Cost of Capital 3 $75 million Private Placement of Equity, $350 million Green Bond Issuance Ready Access to Capital Diversified Capital Base and Investor Group Equity Raise Highlights Green Bond Highlights US$75 million of equity, or ~6.49 million shares,
Slide 10: Risk mitigated approach to new projects that must meet threshold returns
Risk mitigated approach to new projects that must meet threshold returns 4 Exited 350 MWs of Contracts That Did Not Meet Minimum Thresholds Focused on value creation; all project must be value enhancing Exited 350 MWs through allowable clauses in PPAs to ensure no reputational and relationship risk
Slide 11: If Returns on Future Growth do not Meet Thresholds, Will Explore Giving Back Capital
If Returns on Future Growth do not Meet Thresholds, Will Explore Giving Back Capital 5 Current Market Dynamics Support Returns Above Thresholds Significant Demand for Solar (1) Solar is the Lowest Cost Source of Electricity (3) Gov’t 100GW Solar Target 100 CAGR: 37% US Cents / kWh 3.7 3.9 33 4 Oppor
Slide 12: Industry and Regulatory Update
Industry and Regulatory Update Industry Update Basic Custom Duty (BCD) on Solar Rising tariff caps - Ceiling tariff increased by SECI for recent ISTS tender from INR 2.65/ kWh to INR 2.78/ kWh MNRE has proposed a basic custom duty (BCD) ranging from 10% in first year up to 30% in the third year on i
Slide 13: Financial Forecasts and Review
Financial Forecasts and Review 13|Copyright © 2019 Azure Power |www.azurepower.com
Slide 14: Visible Historical and Future Growth
Visible Historical and Future Growth Growing Portfolio with Strong Contracts in Place Substantial Revenue Growth to Portfolio Run-Rate(1)(2) 3,900 3,370 $358(4) 900 2,815 Revenues (US $ Million) 2,600 Committed 1,798 117 Under Construction MWs 1,300 $161 $144 $112 Operating - $44 $61 Operational Und
Slide 15: 1H FY20 Key Performance Metrics
1H’ FY20 Key Performance Metrics 1,798 MW Operating 2,815 MW Operating US$ 0.46 Mn Project US$88.3m Revenue & Contracted Cost/MW (DC) 34% increase(1) 77% increase(1) 45% increase(1) 25% reduction(1)(2) • 189 MWs Commissioned • vs DC cost per MW US$ 0.61 mn prior • INR 6,235.9 million revenue for • 3
Slide 16: Azure Power Delivered 28% Revenue Growth in Q2 FY20
Azure Power Delivered 28 % Revenue Growth in Q2 FY’20 % Change Quarter Ended September 30, Q2FY’20 vs Commentary (in million) Q2FY’19 2018 2019 2019 INR INR US$ MWs Operating increased 77% 28% Average tariff (INR/kWh) lower by 40% Revenue 2,226 2,847 40.3 PLF of 16.8%, up from 16.4% Extended monsoon
Slide 17: Balance Sheet Highlights
Balance Sheet Highlights As at March 31, 2019 As at September 30, 2019 (in million) (in million) INR INR US$ Cash, Cash Equivalents and Current Investments* 10,545 7,463 105.6 Property, Plant & Equipment, Net 83,445 94,246 1,334.2 Net Debt# 59,007 72,703** 1,029.4** *Does not include Restricted cash
Slide 18: Strong EBITDA, FFO and NAV Growth
Strong EBITDA, FFO and NAV Growth EBITDA, FFO(1), and Net Debt Forecasts NAV/Share of Contracted 2,815 MW Portfolio (no value added for future growth, cost reductions or platform) $ million $ / Share EBITDA: $350 $300 - $330 $35 EBITDA: $300 $260 - $285 $30 $250 EBITDA: $25 $190 - $205 NAV/Share $20
Slide 19: Contracted 2,815 MW Portfolio: Operational, Capex, Cost per Watt Outlook
Contracted 2,815 MW Portfolio: Operational, Capex, Cost per Watt Outlook 3,000 2,815 MWs Operational 2,500 1,800 - 1,825 MWs 2,000 Operational FY'20 FY'21 (US$ millions) Cap Ex $350 - $400 $450 - $500 1,500 $/watt 1,000 Cost per Watt Operating FY’20 – FY’22 DC before SGD/BCD $0.40 - $0.45 AC before
Slide 20: Contracted 2,815 MW Portfolio: Liquidity and Funding
Contracted 2,815 MW Portfolio: Liquidity and Funding US$ million 700 Current Cash Cash Available for Under Construction 600 and Committed Projects Equity Raised (1) US$ million 500 As of Sept 30, 2019 Cash and Current Investments $ 106 900 MWs Short Term Restricted Cash 311 400 Contracted Total Cash
Slide 21: FY20 Guidance
FY’20 Guidance 1,800 – 1,825 MWs Operating INR 12,770 – 13,350 million(1) by March 31, 2020 of Revenue for FY’20 _________________________ 1) US$ 181-189 Mn (at September 30, 2019 exchange rate- INR70.64 to US$1) 21|Copyright © 2019 Azure Power |www.azurepower.com
Slide 22: Appendix
Appendix 22|Copyright © 2019 Azure Power |www.azurepower.com
Slide 23: Historical Plant Load Factor (PLF)
Historical Plant Load Factor (PLF) 22.0% 21.5% 21.0% 20.5% 20.0% 19.4% 19.0% 18.0% 17.9% 16.8% 17.0% 16.4% 16.0% 15.0% 1Q 2Q 3Q 4Q FY'19 FY'20 23|Copyright © 2019 Azure Power |www.azurepower.com
Slide 24: DSO by Counterparty
DSO by Counterparty Amounts in US$ million Total Due Customer Name Project Name Capacity (MWs) Due 91-365 Due greater than 365 DSO outstanding 0-90 SECI , NTPC, NVVN 689 11.2 11.2 0.0 - 60 Southern Power Distribution Com of AP AP-1 50 8.6 2.9 5.8 0.0 422 Ltd Hubli Electricity Supply Company Ltd K-3
Slide 25: Use of Non-GAAP Financial Measures
Use of Non-GAAP Financial Measures Adjusted EBITDA is a non-GAAP financial measure. The Company presents Adjusted EBITDA as a supplemental measure of its performance. This measurement is not recognized in accordance with USGAAP GAAP and should not be viewed as an alternative to USGAAP GAAP measures
Slide 26: Reconciliation of Non-GAAP Measures to Comparable GAAP measures
Reconciliation of Non-GAAP Measures to Comparable GAAP measures Quarter Ended September 30, Six month Ended September 30, (in million) (in million) 2018 2019 2019 2018 2019 2019 INR INR US$ INR INR US$ Net loss (298) (756) (10.7) (268) (586) (8.3) Income tax expense 14 27 0.4 109 171 2.4 Interest ex
Slide 27: Projects Commissioned - Utility
Projects Commissioned - Utility As on September 30, 2019 Commercial Duration PPA Capacity DC Capacity Tariff Project Names Operation Off taker of PPA in Credit Rating(6) (MW) (MW) (INR/kWh) Date(1) Years Operational – Utility Punjab 1 (3) Q4 2009 2 2 17.91 NTPC Vidyut Vyapar Nigam Limited 25 AAA Pun
Slide 28: Projects Commissioned – Utility and C&I
Projects Commissioned– Utility and C&I As on September 30, 2019 Commercial Duration PPA Capacity DC Capacity Tariff Project Names Operation Off taker of PPA in Credit Ratings5) (MW) (MW) (INR/kWh) Date(1) Years Operational – Utility North & South Bihar Power Distribution Bihar1 (4) Q3 2016 10 11 8.3
Slide 29: Under Construction Projects – Utility and C&I
Under Construction Projects –Utility and C&I As on September 30, 2019 Expected Duration PPA Capacity Tariff Credit Ratings(3) Project Names Commercial Off taker of PPA in (MW) (INR/kWh) Operation Date(1) Years Under Construction Assam 1 Q2 2020 90 3.34 Assam Power Distribution Company 25 B+ Total Un
Slide 30: Project Debt Schedule
Project Debt Schedule As of September 30, 2019 Outstanding Principal Amount (In thousands) Type of Interest Currency Maturity Date(1) Name of Project INR US$ (2) Gujarat 2 4,674,908 66,179 Floating US$ 2019 Andhra Pradesh 1 2,508,312 35,508 Fixed INR 2022 Bihar 1 438,767 6,211 Fixed INR 2022 Gujarat
Slide 31: Project Debt Schedule
Project Debt Schedule As of September 30, 2019 Outstanding Principal Amount (In thousands) Type of Interest Currency Maturity Date(2) Name of Project INR US$ (5) Uttar Pradesh 3 1,453,322 20,574 Floating INR 2033 Andhra Pradesh 3 2,087,313 29,549 Floating INR 2034 Punjab 3.1 and 3.2 1,398,416 19,796
Slide 32: Glossary of Select Terms
Glossary of Select Terms Accelerated Depreciation – Accelerated depreciation can be elected at the project level, such that projects that reach COD in the first half of the year can expense 100% of eligible project costs in year 1, and otherwise can expense 50% of project costs in year 1 and the rem
Slide 33: Affordable Solar Power for Generations
Affordable Solar Power for Generations Excellence | Honesty | Social Responsibility | Entrepreneurship 33|Copyright © 2019 Azure Power |www.azurepower.com