Slide 1: Bulyanhulu Mine Tour – Africa Mine Tour October 2005
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Africa Mine Tour – October 2005 FORWARD LOOKING STATEMENT Certain information contained or incorporated by reference herein, including any information as to our future financial or operating performance, constitutes "forward-looking statemen
Slide 2: Bulyanhulu Mine – Agenda
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Agenda Overview Safety and Health Mining Operations Processing Operations Environmental Stewardship Community Relations Vision for Bulyanhulu BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 BARRICK BULYANHULU MINE
Slide 3: Bulyanhulu Mine – Location
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 UGANDA KENYA Bulyanhulu Mine – Location LAKE VICTORIA Mwanza TANZANIA Tulawaka Bulyanhulu Shinyanga Kahama Mombasa Tabora INDIAN OCEAN Zanzibar BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 0 km 100 200 300 400 500 Dar es Salaam LAKE VICTORIA
Slide 4: Bulyanhulu Mine – History
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – History Acquired Sutton Resources in March 1999 – $280 million – Included both Bulyanhulu and Kabanga – 3.6 million ounces of gold reserves First production in April 2001 1.26 million ounces produced through 2004 Ex
Slide 5: Bulyanhulu Mine – Overview
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Overview Gold reserves: 10.6 Moz (2) Gold resources: 2.3 Moz (Measured & Indicated) 2.5 Moz (Inferred) 2005E production: 320-325,000 ounces 2005E cash cost: $340-350 per ounce (1) BARRICK BULYANHULU MINE TOUR – OCTO
Slide 6: Safety and Health
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Agenda Overview Safety and Health Mining Operations Processing Operations Environmental Stewardship Community Relations Vision for Bulyanhulu BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Safety and Health Cli
Slide 7: Lost Time Injury Frequency Rate
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Lost Time Injury Frequency Rate 4 0.7 30 September 2005 3.5 0.59 achieved 818,532 LTI free hours 0.6 3 0.5 0.44 0.42 0.43 2.5 0.35 0.4 2 0.27 TARGET: = <0.3 0.29 0.3 1.5 0.25 0.24 0.2 1 0.5 0.1 0 0 2003 2004 Jan-05 Feb Mar Apr May Jun Jul Au
Slide 8: Safety and Health
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Agenda Overview Safety and Health Mining Operations Processing Operations Environmental Stewardship Community Relations Vision for Bulyanhulu BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 BARRICK BULYANHULU MINE
Slide 9: Mining Operations
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Mining Operations Underground trackless mining operation Accessed by surface shaft and internal ramp Operated 7 days a week – two 10-hr. shifts Mining methods – mechanized sub-level longhole retreat – conventional cut-and-fill – mech
Slide 10: Mining Operations – Equipment
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Mining Operations – Equipment Trucks Loaders – EJC 417 – 2 – Toro T151D – 14 – EJC 420 – 2 – Toro T301D – 7 – EJC 430 – 12 – Toro T400D – 4 – Toro T1400D – 4 Jumbos – Toro 006 – 2 – Two Boom (Waste Dev.) Minimatic – 4 Longhole Drills
Slide 11: Comparison by Mining Method
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Comparison by Mining Method 2004 & Q2 '05 YTD Tonnes by Mining Method 2004 Q2 '05 YTD 45% 40% 35% 30% % Tonnes 25% 20% 15% 10% 5% 0% Development Longhole Sill Pillar Rec. Cut & Fill Conventional Cntrctr/Test Stope Method BARRICK BULYANHULU M
Slide 12: Process Flowsheet
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Process Flowsheet Cyclones (8) Gravity Concentrator SAG Mill Shaking Table Furnace Ball Mill Dore Rougher Flotation Cleaner Flotation Cyclones Thickeners Regrind Mill Concentrate Thicker Copper Con
Slide 13: Processing
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Processing Crushing and grinding circuit Gold/silver gravity circuit Copper/gold/silver flotation circuit Tailings thickening/filtration circuit Paste backfill facility Tailings storage facility Operated 24 hours per day Capa
Slide 14: Environmental Stewardship
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Agenda Overview Safety and Health Mining Operations Processing Operations Environmental Stewardship Community Relations Vision for Bulyanhulu BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Environmental Stewardsh
Slide 15: Community Development
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Agenda Overview Safety and Health Mining Operations Processing Operations Environmental Stewardship Community Relations Vision for Bulyanhulu BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Community Development
Slide 16: Community Development
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Community Development Constructed 441 houses at Bugarama and Illogi for employees and their families On-going project Further 60 houses under construction BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Community Development New High Schoo
Slide 17: Vision for Bulyanhulu
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Bulyanhulu Mine – Agenda Overview Safety and Health Mining Operations Processing Operations Environmental Stewardship Community Relations Vision for Bulyanhulu BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Vision for Bulyanhulu T
Slide 18: Continuous Improvement Summary
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Continuous Improvement Summary 196 CI ideas & initiatives evaluated to date 14 implementations in progress; 3 fully implemented Est Annual Initiative Department Savings Rationalize air travel Aviation US$1,300,000 Self Insurance HR 800,0
Slide 19: Project Phoenix
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Project Phoenix Objective Present the new ‘Bulyanhulu Vision’ Scope Select ‘greenfield’ section of orebody to apply the Vision Develop and evaluate all viable mining options Select and validate preferred operating strategy Map out
Slide 20: Reef 2 Initiative Summary
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Reef 2 Initiative Summary Reserve and resource geometry – Location: 500m in the hanging wall of Zone 1 – Dimensions: mineralization over 2.5 Km of strike and 800 to 1200m of depth – 1.3M tonnes (
Slide 21: Scavenger Cleaner Tails Project
BARRICK GOLD CORPORATION Bulyanhulu Mine Tour October 2005 Scavenger Cleaner Tails Project Part of tailings product that has already been concentrated has leaching capabilities in excess of 70% (500tpd @ about 4.5+g/t material) Propose leaching with cyanide Results in estimated incremental ann
Slide 22: Africa Mine Tour – Forward Looking Statement
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Africa Mine Tour – October 2005 FORWARD LOOKING STATEMENT Certain information contained or incorporated by reference herein, including any information as to our future financial or operating performance, constitutes "forward-looking statements
Slide 23: Tulawaka – Agenda
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Tulawaka – Agenda Overview Safety Succession plan Mining operations Processing operations Environment BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Overview BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 2
Slide 24: Tulawaka – Location
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 UGANDA KENYA Tulawaka – Location LAKE VICTORIA Mwanza TANZANIA Tulawaka Bulyanhulu Shinyanga Kahama Mombasa Tabora INDIAN OCEAN Zanzibar BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 0 km 100 200 300 400 500 Dar es Salaam LAKE VICTORIA Mwanza Tula
Slide 25: Tulawaka – History
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Geographical Area 624 Hectares 10 km Perimeter Dense vegetation BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Tulawaka – History 70/30 joint venture between Pangea Goldfields and Northern Mining Explorations Barrick acquired Pangea Goldf
Slide 26: Tulawaka – Development
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Tulawaka – Development 14 months from greenfields site to production Poured first gold on March 15, 2005 3.4 million hours no lost time injuries (LTI’s) $39 million capital costs (70%) BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Tulawaka
Slide 27: Vision and Goals
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Vision and Goals “Safe Gold Production” Optimise performance of personnel and mineral resources/reserves Effective development and retention of quality personnel for Tulawaka and other Barrick operations Creating a longer future for Tu
Slide 28: Safety – Zero Tolerance
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Safety – Zero Tolerance What have we learned? – Safety comes first, and production is invariably directly linked with safety – Fatigue Management Programme – Operator training Methods / Records / Fraud Never assume if there are NO incident
Slide 29: Succession Plan
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Succession Plan BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Succession Plan Part of the preparation for the future of Tulawaka and Barrick in Tanzania Provides a continuing sequence of qualified people to move up and take over when the curre
Slide 30: Succession Plan
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Succession Plan Develop a program to provide training, ongoing support and mentoring for professionals and new supervisors Ongoing monitoring of progress to ensure compliance is a fundamental requirement BARRICK TULAWAKA MINE TOUR – OCTOBE
Slide 31: Mining – Systems Developed
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Mining Operations BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Mining – Systems Developed Surface Mining Procedures and Safety Systems Succession Planning Grade Control & Production Databases Grade Control MP3 replacing Polygonal estimati
Slide 32: Tulawaka East Open Pit
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Tulawaka East Open Pit Tulawaka East Open Pit – History Mining commenced June 2004 Borrow pit inside final pit limits supplied suitable construction materials to dams Borrow pit used to experiment with final pit wall profile New block
Slide 33: Tulawaka East Open Pit
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Tulawaka East Open Pit Mining Department – Integration of all areas Mining, Geology, Development and Exploration activities in same location 100% Tanzanian Mining Contractor – Caspian Ltd. – Mining contract signed November 2004 BARRICK TUL
Slide 34: Tulawaka East Open Pit
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Tulawaka East Open Pit 3 Stage pit schedule West Stage (red) accelerated development for access to potential underground operation Stage 1 (blue) advancing ore zone BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Mining – Strategic Development
Slide 35: Exploration & Development
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Exploration & Development Tulawaka South T7 West Zone East Pit Underground feasibility BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Underground Feasibility Drilling 2005 In-pit resource drilling 26 Holes 5743m Diamond drilling C
Slide 36: Tulawaka East Zone - Underground
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Tulawaka East Zone - Underground Diamond drilling program completed August 2005 Feasibility study scheduled to be complete in Q4 2005 BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 Processing BARRICK TULAWAKA MINE TOUR – OCTOBER 2005 15
Slide 37: Processing
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Processing Gravity separation technology (50% of gold recovered) Conventional carbon-in-leach technology (total gold recovery is +95%) Tulawaka is the only mine in Tanzania to conduct cyanide destruction and meet the Cyanide Code BARRICK
Slide 38: Processing – Overview
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Processing – Overview Mill availability has been above budget since start up (>95% vs 90%) Reagent consumption rates to date have been 40% below budget for cyanide and 60% below budget for metabisulphite Milling costs have been in line w
Slide 39: Processing – Safety & Training
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Processing – Safety & Training A detailed Process Plant Induction was developed and implemented prior to startup – Only those who have been inducted and passed the test are permitted to enter the plant without an escort Safe Work Procedure
Slide 40: Environment
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Environment Environment Department started activities at Tulawaka Project in 2001 as a regional project of KMCL Environment Department During 2002 – 2003 collected environmental baseline information for the Tulawaka Project BARRICK TULAWAK
Slide 41: Environment – Department Functions
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 Environment – Department Functions Waste management (hazardous and non- hazardous materials management) Land management (topsoil, flora, re-vegetation) Provide advice to all departments on environmental issues Environmental compliance
Slide 42: Tulawaka Mine Tour October 2005 – Footnotes
BARRICK GOLD CORPORATION Tulawaka Mine Tour October 2005 FOOTNOTES 1. Based on reserves calculated as at December 31, 2004 using an assumed price of $375 per ounce for gold. Calculations have been performed by employees of Barrick under the supervision of Rene L. Marion, P. Eng., Vice President, Tec
Slide 43: Exploration
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 EXPLORATION Africa Mine Tour – October 2005 FORWARD LOOKING STATEMENT Certain information contained or incorporated by reference herein, including any information as to our future financial or operating performance, constitutes "forward-looking
Slide 44: Lake Victoria District - Tanzania
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Lake Victoria District - Tanzania Lake Victoria Mwanza Kabanga Nyanzaga Tulawaka Bulyanhulu Jomu Golden Ridge Lake Victoria Greenstone Belt Shinyanga Kahama Buzwagi BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 Buzwagi BARRICK LAKE V
Slide 45: Buzwagi – Plan Map
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Buzwagi – Plan Map Deposit hosted in granodiorite Strikes north-south N 70° dip to east Domain 1 BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 Buzwagi – Long Section Zone 1 (looking west) S N 100 m BARRICK LAKE VICTORIA DISTRIC
Slide 46: Buzwagi – Cross Section #73300
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Buzwagi – Cross Section #73300 BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 Buzwagi – Plan View Soil Anomalies Current pit plan BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 4
Slide 47: Lake Victoria District – Exploration
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Lake Victoria District – Exploration(1) Nyanzaga Advanced drill testing 2005 Golden Ridge Metallurgical testing in 2006 Other Field work ongoing on other properties BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 (1) Refer to fin
Slide 48: Nyanzaga – Tusker Prospect
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Nyanzaga – Tusker Prospect BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 Nyanzaga – Kilimanjaro Prospect BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 6
Slide 49: Kabanga (Nickel) – Lake Victoria District
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Kabanga (Nickel) – Lake Victoria District Acquired in Sutton Resources transaction Located 400km west of Bulyanhulu Increased known resource at Kabanga Main and discovered adjacent MNB deposit Inferred resource of 26 million tonnes @ 2.6
Slide 50: Lake Victoria District - Tanzania
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Lake Victoria District - Tanzania Lake Victoria Mwanza Kabanga Nyanzaga Tulawaka Bulyanhulu Jomu Golden Ridge Lake Victoria Greenstone Belt Shinyanga Kahama Buzwagi BARRICK LAKE VICTORIA DISTRICT EXPLORATION – OCTOBER 2005 FOOTNOTES 1. Barrick’s
Slide 51: Mining in Africa
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Mining in Africa Africa Mine Tour – October 2005 FORWARD LOOKING STATEMENT Certain information contained or incorporated by reference herein, including any information as to our future financial or operating performance, constitutes "forward-loo
Slide 52: Mining in Tanzania
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Mining in Tanzania Gold Mining & Development Agreement Right to enter loans and use mine as security Right to export and sell production Right to open bank accounts outside of Tanzania Right to retain abroad the proceeds of sale of miner
Slide 53: Mining in Tanzania – Fiscal Regime
BARRICK GOLD CORPORATION Africa Mine Tour October 2005 Mining in Tanzania Fiscal Regime 3% royalty 30% corporate income tax Depreciation allowance Withholding taxes Low import duty VAT relief No export tax duty BARRICK BULYANHULU MINE TOUR – OCTOBER 2005 Mining in Tanzania Government A