  1. Slide 1: Diavik Diamond Mine

    25 June 2014 Diavik Diamond Mine Jean-Marc Lieberherr, Managing director, Rio Tinto Diamonds Marc Cameron, President, Diavik Diamond Mines

  2. Slide 2: Cautionary statement

    2 Cautionary statement This presentation has been prepared by Rio Tinto plc and Rio Tinto Limited (“Rio Tinto”) and consisting of the slides for a presentation concerning Rio Tinto. By reviewing/attending this presentation you agree to be bound by the following conditions. Forward-looking statements

  3. Slide 3: The Diavik Joint Venture

    3 The Diavik Joint Venture 60% 40% owner and operator owner Rio Tinto Dominion Diamond Corp ©2014, Rio Tinto, All Rights Reserved

  4. Slide 4: Health and safety

    4 Health and safety • Our most important value • Strong safety performance • Certified to ISO international standards • Mine rescue team comprised of employees ©2014, Rio Tinto, All Rights Reserved

  5. Slide 5: Island-based Diavik Diamond Mine

    5 Island-based Diavik Diamond Mine Processed kimberlite containment Diavik plant site Wind farm Waste rock pile A418 dike & pit Airstrip A154 dike & pit Future fish habitat Lac de Gras ©2014, Rio Tinto, All Rights Reserved

  6. Slide 6: Diavik at a glance

    6 Diavik at a glance • Located on an island in the tundra − 210 km south of Arctic Circle − 300 km northeast of Yellowknife • Temperature range +20°C to -45°C • 4 kimberlite pipes – 3 in operation • Strong free-cash flow generation • The current mine plan has production ending in 2023 • 2000-02 cons

  7. Slide 7: Operations – underground mining

    7 Operations – underground mining • 2013 – first full year as all underground mine • 2013 – 2.1mt ore producing 7.2m carats • 2014 on target to exceed plan of 1.9mt and 6.9m carats • Forecast to produce 5.5m to 6m carats annually 2015-2017 ©2014, Rio Tinto, All Rights Reserved

  8. Slide 8: Operations – underground mining

    8 Operations – underground mining • Technologically advanced mine using the best equipment − Remote scoop operations − Computerized drill patterns • Mining methods: − Sublevel retreat A154 South and A418 − Blasthole stoping A154 North ©2014, Rio Tinto, All Rights Reserved

  9. Slide 9: Operations – processing

    9 Operations – processing • Record processing performance in Q1 2014 • Capable of recovering all economic diamonds • Product sorting facility in Yellowknife cleans and sorts goods ©2014, Rio Tinto, All Rights Reserved

  10. Slide 10: Community relations

    10 Community relations • Modern formal agreements with 5 Aboriginal communities • Formal agreement with local government • 2013 – Aboriginal & Northern employment increased 2% • 2013 – Northern business spend increased 5% ©2014, Rio Tinto, All Rights Reserved

  11. Slide 11: Award winning wind farm – proven technology

    11 Award winning wind farm – proven technology • Benchmark for cold climate • Rio Tinto’s first wind farm • Four 2.3 megawatt turbines • 2013 – 8.4% power and 3.8m litres diesel offset • 2014 Q1 – 11.1% power and 1.4m litres diesel offset • $31m capex, eight year payback ©2014, Rio Tinto, All Rights

  12. Slide 12: Diavik kimberlite pipes

    12 Diavik kimberlite pipes ©2014, Rio Tinto, All Rights Reserved

  13. Slide 13: Diavik reserves and resources (31 December 2013)

    13 Diavik reserves and resources (31 December 2013) • A154 South pipe − 2.2 mt reserves/grade 3.6cpt • A154 North pipe − 7.5 mt reserves/grade 2.1 cpt • A418 pipe − 6.5 mt reserves/grade of 3.4 cpt • A21 (resource only) − 3.6 mt measured resources/ grade 2.8cpt − 0.4 mt indicated resources/ grade 2.

  14. Slide 14: Diavik current mine plan

    14 Diavik current mine plan Reserves (Tonnes Millions) 2.5 2.0 1.5 1.0 0.5 0.0 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 A154S A154N A418 ©2014, Rio Tinto, All Rights Reserved

  15. Slide 15: Diavik current mine plan

    15 Diavik current mine plan Reserves (Carats Millions) 7 6 5 4 3 2 1 0 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 A154S A154N A418 ©2014, Rio Tinto, All Rights Reserved

  16. Slide 16: Current mine plan

    16 Current mine plan Capital and operating costs C$M (2014 real terms) 500 450 400 350 300 250 200 150 100 50 0 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Operating Cost Capital Cost ©2014, Rio Tinto, All Rights Reserved

  17. Slide 17: A21 kimberlite update

    17 A21 kimberlite update • Design and approach to dike construction completed with initial technical review of cutter soil mixing technique for construction being approved • Key scope of work packages completed • Costing estimates being finalized • Project roles defined and potential candidates iden

  18. Slide 18: Tibbitt to Contwoyto Winter Road Joint Venture

    18 Tibbitt to Contwoyto Winter Road Joint Venture • Joint Venture between Rio Tinto, Dominion Diamond Corp & DeBeers • 353 km to Diavik • ~$20m annual cost to build/operate • Operates for two months • 87% of road built on frozen lakes ©2014, Rio Tinto, All Rights Reserved

  19. Slide 19: Diavik – a world class diamond mine

    19 Diavik – a world class diamond mine • Safety will always be our first priority • A proven underground mine • Sustainable cost base • Growth opportunities – A-21 • Strong community partnerships in place for life of mine ©2014, Rio Tinto, All Rights Reserved

  20. Slide 20: Thank you

    20 Thank you ©2014, Rio Tinto, All Rights Reserved