  1. Slide 1: Elizabeth Hill Silver Project

    For personal use only Elizabeth Hill Silver Project Advancing Australia’s Highest-Grade ASX-Listed Silver Project1 ASX: WCE | NOVEMBER 2026 Cover Image is for illustrative purposes only. Silver bars/bullion shown are generic and are not sourced from, or representative of, product from the Elizabeth

  2. Slide 2: Disclaimer

    Disclaimer For personal use only Forward-Looking Statements Statements in this presentation which are not statements of historical fact, including but not limited to those relating to exploration results, mineral resource estimates, development timelines, production potential and future plans, are f

  3. Slide 3: West Coast Silver's Vision and Current Focus

    West Coast Silver’s Vision Current Q4 2026 / Q1 2027 Focus For personal use only Expanding the silver resource: Chasing silver extensions: “Grow and transition November 2026 MRE update – Advance drill definition of NW Elizabeth Hill’s high- 3.36 Moz Ag at 446 g/t Ag, with Extension and Elizabeth Hil

  4. Slide 4: Strategic Asset: Historical Mine on Granted Mining Lease

    Strategic Asset Historical Mine on Granted For personal use only Mining Lease Elizabeth Hill Silver Mine 1999 - 2000 • Elizabeth Hill Project – (M47/342) WCE 70%, Strategic Alien Metals Ltd 30%1. Pilbara Location • Elizabeth Hill West P47/2033: WCE 70%, GreenTech 30%. Granted • Granted Mining Lease

  5. Slide 5: Updated MRE: Resource grows 20% to 3.36 Moz Ag

    Updated MRE Resource grows 20% to 3.36 Moz Ag For personal use only Incorporating approximately 4,726m of additional RC and diamond drilling Elizabeth Hill Long Section: N S Contained silver by JORC category (Moz) 4.0 3.5 3.363 Moz 3.0 2.795 Moz 0.776 2.5 2.0 Moz 1.5 2.426 2.587 1.0 0.5 0.369 0.0 Ap

  6. Slide 6: Updated MRE: 77% of contained silver is Indicated

    Updated MRE 77% of contained silver is Indicated resource For personal use only Increase from 13% Indicated Resource in April 2026 Metric April 2026 November 2026 Change • Successful 2026 drilling increased Tonnes (kt) 141.0 234.7 +66.5% contained silver in the Mineral Grade (g/t Ag) 617 446 -27.7%

  7. Slide 7: Updated MRE: High-grade core and cut-off sensitivity

    Updated MRE High-grade core and cut-off sensitivity For personal use only At 60 g/t Ag COG, resource contains 95.2% of the reported ounces in 31.8% of the reported tonnes Cut-off (g/t Ag) Tonnes (kt) Grade (g/t Ag) Contained Ag (koz) 20 · reported 234.7 446 3,363 30 140.9 726 3,287 40 104.3 968 3,24

  8. Slide 8: Updated MRE: Resource growth and follow-up drilling

    Updated MRE Resource growth and follow-up drilling For personal use only The November model incorporates 46 additional drill holes and a revised geological interpretation Elizabeth Hill Resource Model - 3D Oblique View: North-west extension Classified as Inferred in November MRE. Follow-up drilling

  9. Slide 9: Pure Silver Play: Highest reported silver grade in peer group

    Pure Silver Play HIGHEST REPORTED SILVER GRADE IN West Coast Silver Peers SELECTED PEER GROUP For personal use only Elizabeth Hill has the highest reported silver grade within the selected project peer group. Ultra-High Grade West Coast Silver 446 Highest in Elizabeth Hill g/t Ag peer group >400 g/t

  10. Slide 10: Peer Drilling Benchmark

    Peer Drilling Benchmark 2026 Silver Drilling : WCE Ranks #2 and #3 in Selected ASX Peers For personal use only All silver intercepts from ASX-listed issuers appearing in the supplied 2026 MinerDeck charts. RANK COMPANY ASX PROJECT Ag (g/t) WIDTH (m) FROM (m) Ag g/t·m RELATIVE GRADE × WIDTH 1 Polymet

  11. Slide 11: Strategy: Development & Resource Growth

    Strategy Development & Resource Growth For personal use only Advancing resource confidence, near-mine drilling and district-scale exploration. DEVELOPMENT GROWTH • November 2026 JORC MRE • West: broad granite-hosted mineralisation. • 3.36 Moz Ag @ 446 g/t Ag • (77% Indicated, 100% basis). • Deeps: i

  12. Slide 12: Processing: Pilbara processing plants

    Processing Pilbara processing plants For personal use only Radio Hill (Artemis Resources) is the first toll-treatment option under assessment for Elizabeth Hill. Plant Owner / operator Circuit / feed Mtpa Road km (est.) Reported status / relevance Radio Hill1 Artemis Resources Ni–Cu concentrator 0.4

  13. Slide 13: Next Phase: Three Growth Fronts at Elizabeth Hill

    Next Phase Three Growth Fronts at Elizabeth Hill 1 For personal use only North Growth April 2026 MRE 2026 Drilling Outcomes shell 1. Drilling extended known Mineralisation extended mineralisation west, north, south and ~70 m north 'OPEN' @ depth 2.8Moz Ag near surface. @ 617g/t Ag 2. November MRE: 3

  14. Slide 14: Drill Campaign: H2 2026 Diamond Drilling

    Drill Campaign H2 2026 Diamond Drilling For personal use only Up to 18 holes / approximately 1,800m to support resource and study milestones Allocated drilling 6 holes / 510m MRE infill / confidence 8 holes / 640m Western extension 2 holes / 360m Elizabeth Hill Deeps 2 holes / 290m Below historic mi

  15. Slide 15: Exploration: Geophysical Surveys to Define New Silver Drill Targets

    Exploration Geophysical Surveys to Define New For personal use only Silver Drill Targets IP and CSAMT geophysical surveying underway along approximately 4km of the Munni Munni Fault Zone Key program features • Approximately 4 km of Munni Munni fault corridor is being surveyed. • Mine-site IP test re

  16. Slide 16: New Tenement: Elizabeth Hill West Granted

    New Tenement Elizabeth Hill West - Granted For personal use only P47/2033 is immediately adjacent to the Elizabeth Hill mine lease (M47/342) What has changed • Granted P47/2033: 70% WCE / 30% GreenTech. • Targets within 1 km of the historical mine. • Historical Trenching: 5m @ 5.2g/t Ag; 19,000ppm C

  17. Slide 17: Elizabeth Hill West – Surface Outcrop

    Elizabeth Hill West Elizabeth Hill West – Surface Outcrop For personal use only P47/2033 | Surface observations from 14 November 2026 Investors are cautioned that visual estimates of mineral quantities or grade should never be considered a proxy or substitute for laboratory analyses. Laboratory assa

  18. Slide 18: Funded Workstreams & Near-Term Catalysts

    Catalysts Funded Workstreams & Near-Term Catalysts For personal use only From high-grade drill results to resource updates and Scoping Study evaluation 1 Resource Definition 2 H2 Diamond Program • November 2026 MRE delivered: 3.36 Moz Ag at 446 g/t Ag, • Up to 18 diamond holes / ~1,800m 77% Indicate

  19. Slide 19: 2026 / 2027 Program Timeline

    Program 2026 / 2027 Program Timeline For personal use only November MRE delivered, with the next update targeted for March 2027 WORKSTREAMS PROGRAM WINDOW 2026 2027 OCT 26 NOV DEC JAN 27 FEB MAR APR H2 diamond drilling In Progress IP / CSAMT & modelling Resource update November MRE delivered H2 resu

  20. Slide 20: Board and Elizabeth Hill Project Delivery Team

    Corporate Board and Elizabeth Hill Project Delivery Team For personal use only Experienced Board, corporate and technical team to advance Elizabeth Hill Board of Directors Vince Fayad Sergei Smolonogov Thomas Reddicliffe Non-Executive Chairman Executive Director & CEO Non-Executive Director • 40 yea

  21. Slide 21: Corporate Overview – Capital Structure and Share Performance

    Corporate Corporate Overview – ASX: WCE For personal use only Capital Structure Share Performance Shares on Issue 435,742,147 0.30 10 Share Price A$0.047 Market Capitalisation A$20.5M Share Price ($/sh) Cash A$5.6m 0.20 Volume (m) Implied Enterprise Value A$14.9m 5 Average Daily Turnover ($) 6 month

  22. Slide 22: Appendix 1: Selected Silver Project Peer Comparison

    Appendix 1: Selected Silver Project Peer Comparison For personal use only As reported Measured Indicated Inferred Total Reported Mkt Cap. g/t g/t g/t g/t g/t Ag Moz Ag Source: Company Ticker Project Status Commodities Mt Moz Mt Moz Mt Moz Mt Moz % silver Link (A$m) Ag Ag Ag Ag Eq. Eq. ASX Joaquin /

  23. Slide 23: Elizabeth Hill Contact

    For personal use only Elizabeth Hill Advancing Australia’s Highest-Grade ASX-Listed Silver Project ASX | WCE westcoastsilver.com.au Contact Sergei Smolonogov Chief Executive Officer info@westcoastsilver.com.au +61 8 9322 3383 Investor & Media Relations Dannika Warburton - Investability westcoastsilv

  24. Slide 24: Drill Results: New Silver Discovery & Near-Surface Extensions

    Drill Results New Silver Discovery & Near-Surface Extensions For personal use only Released July-August 2026 • New west-to-east drilling confirmed Mineralisation western extensions now in the Extended West November MRE 70m • The system remains open Mineralisation • Western mineralisation extends nea

  25. Slide 25: Drill Results: Bonanza Silver and Extensions

    Drill Results Bonanza Silver and Extensions 1 For personal use only • New west-to-east drilling intersected high-grade silver and extended mineralisation near surface and westward into granite. The November MRE incorporates these results. • Exceptional diamond drilling results: EXCEPTIONAL o 38.3m @

  26. Slide 26: Core Photos: Visible Native Silver

    Core Photos Visible Native Silver – 26WCDD037 1 For personal use only That’s 3.1% Ag Native Silver in Quartz-Carbonate Veining – 26WCDD037: 51.95m–52.30m downhole – 0.35m @ 31,154g/t Ag Hotter the Colours the Higher the Silver Grade Oxidised Native Silver – 26WCDD037: 22.20m–32.95m downhole, Visible

  27. Slide 27: Growth: High-Grade Silver at Deeps

    Growth High-Grade Silver at Deeps For personal use only Silver Trend Beneath Historical Workings Key Highlights • Three intersections currently define a new mineralised trend - ➢ 26WCDD029: 3m @ 524g/t Ag from 183m downhole, incl.1.5m @ 1,039g/t Ag from 184.5m downhole. ➢ UGD084: 7m @ 607g/t Ag from