Magnetite Mines Ltd. · ASX:MGT

Magnetite Mines — Investor Presentation (June 2024)

23 slides from Magnetite Mines's investor presentation, Jun 20, 2024

  1. Slide 1: Premium Iron Ore ... for steel sector decarbonisation

    For personal use only Premium Iron Ore ... for steel sector decarbonisation June 2024

  2. Slide 2: Disclaimer

    Disclaimer For personal use only IMPORTANT NOTICE ADDITIONAL INFORMATION The purpose of this presentation is to provide general information about This presentation should be read in conjunction with MGT’s Annual Report at 30 Magnetite Mines Limited ("MGT"). It is not recommended that any person make

  3. Slide 3: Developing Razorback: Expansive, premium-grade iron ore project in a tier 1 location

    Magnetite Mines (ASX:MGT) Developing Razorback: Expansive, premium-grade iron ore project in a tier 1 location For personal use only The Company The Opportunity Focused on 100% Rare, premium-grade Steelmakers are Supportive SA and Substantial owned Razorback Magnetite iron ore looking now Federal go

  4. Slide 4: Corporate overview

    Corporate overview (ASX:MGT) Recent corporate transformation in readiness to develop project For personal use only Board Management Market Cap Jim McKerlie Chair of the Board Tim Dobson Chief Executive Officer BA Economics (Hons), Dip Fin Mg t, FCA, FAICD BAp pSc (E xt.Me tallu rgy), GA ICD, FAusIMM

  5. Slide 5: Increasing global steel demand is a certainty

    Increasing global steel demand is a certainty Steel is also critical to tackling climate change For personal use only Steel is used in all aspects of the built environment Production has doubled every 20 years since 1950 … Source: World Steel Association … and more steel is necessary for energy tran

  6. Slide 6: Challenging steel decarbonisation targets have been set

    Challenging steel decarbonisation targets have been set Steel industry now committed and making transition investment decisions For personal use only Steel industry produces 8% of global carbon emissions Major steel producer carbon reduction targets Source: Company filings 1. by 2030 compared to 201

  7. Slide 7: The transition away from coal has commenced

    The transition away from coal has commenced Razorback to supply high-grade, low-impurity iron ore for replacement technologies For personal use only Coal-using blast furnaces replacement to EAFs has commenced and forecast to accelerate Iron ore grade required Feed Iron Reduction Melting Carbon emiss

  8. Slide 8: EAFs are increasingly set to replace blast furnaces

    EAFs are increasingly set to replace blast furnaces High-quality scrap and DRI is needed to feed them For personal use only Steel production by process route 70%+ of steelmaking Source: Wood Mackenzie Note: the AET-1.5 scenario is Wood Mackenzie's view of the pat hway to limiting warming to 1.5 degr

  9. Slide 9: New premium-grade iron ore supply critical to transition

    New premium-grade iron ore supply critical to transition Razorback Project positioned to meet urgent new demand For personal use only Razorback >68% Fe concentrates positioned in DR-grade range* High-grade iron ore demand-supply gap to increase Exported Iron Ore – Fe Grade Comparison Australian Hema

  10. Slide 10: Australia is now recognising the green iron opportunity

    Australia is now recognising the green iron opportunity Realising the economic advantage of Australia’s world-leading renewables For personal use only The Malinauskas Labor Government will officially The Australian Government has identified green metals begin its search for partners to kickstart Sou

  11. Slide 11: The South Australia advantage

    The South Australia advantage SA is leading the way to a future green iron economy For personal use only Attracting international investment Value adding Australia’s opportunity can be realised through collaboration and investment in green iron hubs Magnetite + Renewable Energy + Green Hydrogen ✓Tie

  12. Slide 12: Razorback: Expansive, soft, outcropping iron ore

    Razorback: Expansive, soft, outcropping iron ore South Australia’s Braemar Iron Formation – a globally significant magnetite province For personal use only The Braemar advantage ▪ Outcropping ore: very low strip ratio Iron Peak ▪ Siltstone-hosted iron ore, not BIF * ▪ Soft relative to WA magnetite o

  13. Slide 13: Outstanding project location in the undeveloped Braemar

    Outstanding project location in the undeveloped Braemar Close to potential future green iron hubs at Whyalla & Port Pirie For personal use only Adelaide 240km Open-access rail ~50km Whyalla Port 315km Port Pirie 180km Grid Power 100% renewable by 2027 1313 ~125km

  14. Slide 14: Low risk conventional project configuration

    Low risk conventional project configuration Well-proven mining practices and processing technologies For personal use only CAMP ROADS LOW PROFILE TAILING STORAGE FACILITY Open cut mining RAZORBA CK WASTE RO CK DUMP PROCESSING PLANT RAZORBA CK PIT Magnetic separation IRO N PEAK PIT IRO N PEAK WASTE R

  15. Slide 15: Positive Razorback Project Optimisation Study economics

    Positive Razorback Project Optimisation Study economics Results leading to larger scale production and staged expansion strategy For personal use only Staged development pathway manages risk Key project metrics 8 Expa nsion Phy sica l Metrics Unit Base Ca se Option dry Concentra te production ra te

  16. Slide 16: Razorback Project economics globally-competitive

    Razorback Project economics globally-competitive Highly-competitive cost base on a standardised basis For personal use only Wood Mackenzie 2027 VIU-adjusted (62% Fe eq.) cost curve (US$/t)a,b 1st quartile 2nd quartile 300 250 US$/t (real 2023$) 200 150 10Mtpa 5Mtpa 100 50 - 5% 0% 100% 10% 15% 40% 45

  17. Slide 17: Razorback Project financing approach

    Razorback Project financing approach Joint venture with motivated offtakers For personal use only UNINCORPORATED JOINT VENTURE (JV) JV PARTNER 1 Joint Ventures (JV) Potential partners $ ▪ Well-proven model for big Australian iron ore projects over ▪ World-class asset has attracted RAZORBACK JV many

  18. Slide 18: MGT's bespoke sustainability platform

    MGT’s bespoke sustainability platform Elevating future ESG outcomes through early action and commitment For personal use only Environmental sustainability Social & community inclusion ▪ Enabling future low-carbon ▪ Partnering agreement signed with Partnering Agreement with Ngadjuri Nation steel prod

  19. Slide 19: Magnetite Mines is well positioned for success

    Magnetite Mines is well positioned for success Aligned with timing and acceleration of downstream demand For personal use only KEY MILESTONES NEXT STEPS Confirmed Economics infrastructure updated MOU signed Azure Capital access for rail including Iron with CIMIC’s appointed as Peak and 2Bt Pacific F

  20. Slide 20: Magnetite Mines

    Magnetite Mines For personal use only Decarbonisation Outstanding Project Progressing to Substantial re-rating Tailwind Credentials Development potential ▪ Premium-grade iron ore ▪ Tier 1 location ▪ Partnering in progress ▪ Project set for long life needed now to enable ▪ Close to port & rail ▪ Expe

  21. Slide 21: References

    For personal use only References 1. ASX Announcement – 09/02/23 – Iron Peak Mineral Resource Significantly Improved 2. ASX Announcement – 03/11/22 - Muster Dam Mineral Resource Estimate 3. ASX Announcement – 09/06/23 - Iron Peak Deposit Maiden Ore Reserve 4. World Steel Association – 18/05/2023 – Wo

  22. Slide 22: Contact

    For personal use only Contact gemma.brosnan@magnetitemines.com +61 8 8427 0516 www.magnetitemines.com 22

  23. Slide 23: Appendix: Mineral Resources and Reserves

    Appendix 1 Mineral Resources and Reserves1,3 For personal use only Razorback Iron Ore Project (Razorback & Iron Peak deposits combined) a Classification Tonnes (Mt) Mass Rec % Fe % SiO2 % Al2O3 % P% LOI % Magnetite % Indicated 1,675 15.95 18.36 48.02 8.06 0.18 5.46 15 Inferred 1,570 16.09 17.74 48.6

Magnetite Mines — Investor Presentation (June 2024) on 6ix