  1. Slide 1: 4Q FY2014 Results

    2QFY14 Results Presentation 4Q FY2014 Results 1

  2. Slide 2: Key highlights

    Key highlights 4QFY14: 3,577 million units Net Generation FY14: 17,061 million units 4QFY14: ₹ 2,058 Crore Total Income FY14: ₹ 8,705 Crore 4QFY14: ₹ 746 Crore EBITDA FY14: ₹ 3,454 Crore 4QFY14: ₹ 175 Crore Profit after Tax FY14: ₹ 755 Crore Dividend A pay-out of ₹2 per share for FY 2014, subject to

  3. Slide 3: Agenda

    Agenda Sector Update Operational Financial Projects Update Performance Performance 3

  4. Slide 4: Capacity profile and PLF's

    Capacity profile and PLF’s Sector-wise Installed Capacity – 243 GW Mode-wise Installed Capacity (as on Mar 31, 2014) (as on Mar 31, 2014) +1,128 MW* +1,351 MW* RES +8,461 MW* 12% Central; 28% State; +638 MW* 38% Hydro 17% Private; Thermal Nuclear 34% 69% 2% +6,620 MW*  73% and 70% of the entire cap

  5. Slide 5: Demand-supply scenario

    Demand-supply scenario Power Demand Supply Position 4QFY14 (BU) Peak Demand and Peak Met FY14 (GW) 7.6% 6.9% 5.5% 5.4% 136 130 248 2.6% 239 2.4% 4.5% 1.6% 1.3% 46 43 41 40 39 74 73 73 36 71 1.8% 69 67 18 18 30 29 ER &NE SR WR NR All India ER &NE SR WR NR All India Requirement Availability Deficit Re

  6. Slide 6: Indian economy and thermal coal prices

    Indian economy and thermal coal prices Thermal coal prices have come down while  Industrial activities continues to be subdued the Rupee has been flattish during 4QFY14  However generation capacity growth has been API 4 Coal (monthly avg.) 150 good in recent months resulting overall USD/INR (month

  7. Slide 7: Agenda

    Agenda Sector Update Operational Financial Projects Update Performance Performance 7

  8. Slide 8: Power generation

    Power generation 4Q Plant-wise Net Generation Full year Plant-wise Net Generation 8,448 1,924 1,737 1,734 7,022 6,770 6,593 1,398 1,025 3,697 3,310 446 Ratnagiri Vijaynagar Barmer Ratnagiri Vijaynagar Barmer 4QFY13 4QFY14 FY13 FY14 Plant load factor (%) Ratnagiri Vijayanagar Barmer 4QFY14 60% 101% 3

  9. Slide 9: Power sales

    Power sales 4Q power sales break-up Full year power sales break-up 9,885 2,570 53% 8,382 53% 51% 2,292 62% 8,804* 8,098* 2,271* 47% 49% 47% 1,378* 38% 4QFY13 4QFY14 FY13 FY14 Long term Short term Long term Short term 4QFY13 4QFY14 FY13 FY14 Average Realization (`/kwh)^ 4.15 4.85 4.15 4.62 All figure

  10. Slide 10: Agenda

    Agenda Sector Update Operational Financial Projects Update Performance Performance 10

  11. Slide 11: Consolidated financial results

    Consolidated financial results ` Crore Particulars 4QFY13 4QFY14 FY13 FY14 Turnover 2,363 2,113 9,148 8,908 EBITDA 858 746 3,007 3,454 EBITDA (%) 36% 35% 33% 39% Interest 256 302 963 1,206 Depreciation 174 199 662 810 Exceptional gain(-) / loss(+) -4 5 197 378 Profit Before Tax 407 240 1,186 1,060 P

  12. Slide 12: Consolidated financial highlights

    Consolidated financial highlights Particulars Mar 31, 2013 Mar 31, 2014 Net Worth (₹ Crore) 6,204 6,571 Debt (₹ Crore) 10,377 10,106 Net Fixed Assets (₹ Crore) * 15,489 14,750 Debt Equity Ratio (x) 1.67 1.54 Weighted average cost of debt 11.19% 11.04% *Including CWIP and Capital Advances 12

  13. Slide 13: Consolidated financial highlights (contd…)

    Consolidated financial highlights (contd…) 4QFY14 %YoY Particulars Remarks (₹ Crore) change Revenue from operations - Sale of Power 1,799 -7% Due to lower generation - Transmission 26 -13% Transmission Revenue as per ARR - Power traded 193 -35% Total income 2,018 -11% Other operating income 40 Total

  14. Slide 14: Agenda

    Agenda Sector Update Operational Financial Projects Update Performance Performance 14

  15. Slide 15: Domestic mining projects

    Domestic mining projects Status Update  Mining lease transferred in the name of BLMCL  Approval received from MoEF for 25% enhancement to 3.75MTPA BLMCL- Kapurdi mine  Terms of Reference issued for mining capacity expansion to 7MTPA  Public hearing expected to be held in the 1st week of Jun’14 

  16. Slide 16: Kutehr hydro project

    Kutehr hydro project Project Details Status Update Gross capacity 240 MW (3 x 80)  Techno-economic clearance from CEA received  MOEF accorded Forest stage-I & II clearance & environment clearance Technology Run-of-the-river Hydropower  Pre-qualification of vendors for electro- mechanical & hydro-

  17. Slide 17: Forward looking and cautionary statement

    Forward looking and cautionary statement Certain statements in this report concerning our future growth prospects are forward looking statements, which involve a number of risks, and uncertainties that could cause actual results to differ materially from those in such forward looking statements. The