Portland General Electric Co · NYSE:POR
Portland General Electric — Investor Presentation (September 2012)
43 slides from Portland General Electric's investor presentation, September 2012
Slide 1: Investor Presentation
Investor Presentation September 2012 1
Slide 2: Cautionary Statement
Cautionary Statement Information Current as of August 7, 2012 Except as expressly noted, the information in this presentation is current as of August 7, 2012 — the date on which PGE filed its Quarterly Report on Form 10-Q for the quarterly period ended June 30, 2012 — and should not be relied upon a
Slide 3: PGE Value Drivers
PGE Value Drivers • Clear focus, 100% regulated utility • Growth in service territory • Multiple opportunities for rate base growth • Progressive environmental and renewable position • Strong financial position 3
Slide 4: Strong Platform. Positioned for Sustained Growth.
PGE INVESTMENT THESIS Strong Platform. Positioned for Sustained Growth. The Company The Strengths The Growth 4
Slide 5: PGE At A Glance
PGE At A Glance Vertically integrated – generation, Beaver transmission and distribution Port Westward OREGON WASHINGTON Montana Market cap >$2B 26 Colstrip 3 & 4 Columbia River Service area in 84 northwest Oregon Portland Sandy Eastern Oregon River T.W. Sullivan Coyote Springs – includes Port
Slide 6: Attractive, Growing Service Territory
Attractive, Growing Service Territory Demographic Growth Retail Load Growth (2) (Million MWhs) Continued in-migration 18.8 • Population growth of 1-1.2% annually 18.6 through 2020(1) 18.5 Industrial Growth Economy continues to improve • Growth in high-tech & manufacturing – Intel’s D1X facility – Da
Slide 7: History of Successful Execution of Capital Projects
History of Successful Execution of Capital Projects Recent Capital Projects Average Rate Base ($M) Biglow Canyon Wind Farm (2007-2010) ‒ Three phase build-out; $960 million $3,152 $2,863 Smart Meters (2008-2010) $2,381 $2,425 ‒ 825,000 meters installed; $145 million $1,939 Selective Water With
Slide 8: Ready for the Next Growth Phase
PGE TODAY Ready for the Next Growth Phase 2006 – 2010 2011 – 2012 2013+ Grew business and built Transition – preparing for Opportunities for strong, solid platform next growth phase sustainable growth 8
Slide 9: Strong Platform. Positioned for Sustained Growth.
PGE INVESTMENT THESIS Strong Platform. Positioned for Sustained Growth. The Company The Strengths The Growth 9
Slide 10: Key Strengths
Key Strengths Diversified customer base and 1 generation portfolio 2 High quality utility operations 3 High customer satisfaction rate 4 Solid financial performance Strong balance sheet and 5 financial resources 10
Slide 11: Diversified Customer Base and Generation Portfolio
1. Diversified Customer Base and Generation Portfolio Retail Revenues Power Sources as a by Customer Percent of Retail Load (2011) Per the 2012 AUT (1) Total = $1.7B Total = 2,217 MWa Industrial Purchased Hydro 13% PowerHydro & Wind 22% Coal 26% 29% 19% Residential Wind & Solar Gas Commercial Natura
Slide 12: High Quality Utility Operations
2. High Quality Utility Operations Highly dependable generation portfolio with 93% availability in 2011 Strong power supply operations to stabilize and optimize power costs Progressive approach to reduce coal Effective generation – Boardman 2020 Plan Utility Operations Ongoing T&D investment
Slide 13: High Customer Satisfaction
3. High Customer Satisfaction Top No. 1 No. 2 Decile Investor-owned In the West for Nationally among utility in the nation general business large key customers for residential satisfaction for satisfaction customer satisfaction JD Power & JD Power & TQS Research, Associates Associates Inc. All custo
Slide 14: Solid Earnings
4. Solid Earnings Net Income EPS ROE ($M) (Diluted) 8.2- $1.85- $140- 9.0% 9.0%(1) 2.00(1) 151(1) $1.95 $147 $1.66 8.0% $125 2010 2011 2012E 2010 2011 2012E 2010 2011 2012E Reduced gap between actual ROE and allowed ROE of 10% 1) Based on guidance range, as most recently reaffirmed on August 7, 2012
Slide 15: Dividend Growth
4. Dividend Growth 3.1% CAGR $1.07 $1.05 $1.03 $1.00 $0.96 $0.92 2007 2008 2009 2010 2011 2012 Target Payout Ratio of 50 to 70% Note: Represents annual dividends paid 15
Slide 16: Strong Balance Sheet and Financial Resources
5. Strong Balance Sheet and Financial Resources Revolving Credit Facilities (1) Financial Resources (in millions) Investment grade ratings of BBB and Baa2 Manageable debt maturities Total – weighted average Available Credit Credit 15.5 years Facilities + Cash $660 $619 Target capital structure
Slide 17: Strong Platform. Positioned for Sustained Growth.
PGE INVESTMENT THESIS Strong Platform. Positioned for Sustained Growth. The Company The Strengths The Growth 17
Slide 18: Future Generation Need
Future Generation Need Load-Resource Forecast(1) - Energy Demand Exceeds Generation Resources MWa 3000 Retail load 2500 2015 shortfall Opportunity 2000 632 MWa to grow rate base Long-Term Contracts 1500 1000 PGE Generation 500 0 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 1) Load-Resource Fore
Slide 19: Potential Opportunities for Rate Base Growth
Potential Opportunities for Rate Base Growth Potential to add $2B to 5 rate base (1) 4 3 Cascade 2 New Crossing $3.1B 1 New renewable base load energy New peaking energy capacity Average 2016-2017 Rate Base 2011 1) Rate base growth dependent on outcome of RFP processes 19
Slide 20: New Peaking Capacity Resource
1. New Peaking Capacity Resource Requirement 200 MW year-round flexible resource 200 MW bi-seasonal (winter and summer) peaker 150 MW winter-only peaker Acceptable Bid Types(1) Build-own-transfer project on a greenfield site Asset purchase agreement of an existing facility PGE’s benchmar
Slide 21: New Base Load Energy Resource
2. New Base Load Energy Resource Requirement 300-500 MW base load energy resource Acceptable Bid Types(1) Build-own-transfer project on a greenfield site Asset purchase agreement of an existing facility PGE’s benchmark bid – Carty 1 Construction bid on PGE’s benchmark site (project will be
Slide 22: New Renewable Energy Resource
3. New Renewable Energy Resource Requirement 100 MWa resource(1) Specifications To meet Oregon’s Renewable Energy Standard of 15% by 2015 – wind, solar, biomass or other Bidders can submit a PPA, build own transfer or asset purchase agreement of an existing facility PGE plans to submit a ben
Slide 23: Cascade Crossing Transmission Project
4. Cascade Crossing Transmission Project Requirement 500 kV line, approximately 215 miles Specifications Path from Eastern Oregon to Salem, south of Portland Connect Boardman, Coyote Springs, and potential new projects to service territory Provide transmission access for potential new wind r
Slide 24: Potential Capital Projects Timeline
Potential Capital Projects Timeline (in millions) 2012 2013 2014 2015 2016 2017 Capacity Resource $250-$350 Energy Resource $550-$700 Renewable Resource $700-$850 Cascade Crossing $800-$1,000 Base Capital Spending(1) $325 $300 $275 $275 $350 $375 • Capacity, energy and renewable forecast assumes sel
Slide 25: Portland General Electric Value Proposition
Portland General Electric Value Proposition Strong balance sheet Solid growth in customer demand Strong Platform positioned for Sustained Potential rate base growth of $2B Growth Constructive regulatory environment 25
Slide 26: PGE Investor Relations Team
PGE Investor Relations Team Director, Investor Relations William J. (503) 464-7395 Valach William.Valach@pgn.com Analyst, Investor Relations Lucia M. (503) 464-8586 Dempsey Lucia.Dempsey@pgn.com Portland www.PortlandGeneral.com 121 S.W. Salmon Street General Suite 1WTC05 Electric Portland, OR 97204
Slide 27: Appendices
Portland General Electric Appendices 27
Slide 28: Appendices
Appendices 1. Financials 2. Resource planning 3. Regulatory environment 4. Business initiatives – details 28
Slide 29: YTD 2012 Financial Results
YTD 2012 Financial Results Net Income Earnings per Share (in millions) 2011 2012 2011 2012 Q1 $69 $49 $0.92 $0.65 Q2 $22 $26 $0.29 $0.34 YTD $91 $75 $1.21 $0.99 YTD Q2 Retail Revenues Weather Adjusted Load Growth (in millions) (excluding two large paper manufacturers) $853 $856 Q2 2012 0.5% $390 Q2
Slide 30: Resource Mix
Resource Mix Resource Capacity (at 12/31/11)(1) Power Sources as a Capacity % of Total Percent of Retail Load Capacity Per the 2012 AUT Hydro Deschutes River Projects 298 MW 7.1% Clackamas/Willamette River Projects 191 4.6 Total = 2,217 MWa Hydro Contracts 485 11.6 974 23.3 Natural Gas/Oil Purchased
Slide 31: Business Growth: Integrated Resource Plan
Business Growth: Integrated Resource Plan Integrated Resource Planning Process Under OPUC guidelines, PGE is required to file an Integrated Resource Plan within two years of acknowledgment of the previous plan The IRP requires that the primary goal must be the selection of a portfolio of resourc
Slide 32: Energy Load-Resource Balance
Energy Load-Resource Balance Load-Resource Balance (2012-2021) Energy 3500 3000 Retail load before EE (excl. 5-year opt-outs) 2500 Annual Average Availability (MWa) Retail load including EE (excl. 5-year opt-outs) 632 MWa (513 MWa after EE) 2000 Long-term Contracts Wind – Biglow, Klondike II, Vansyc
Slide 33: Energy Action Plan
Energy Action Plan Annual Annual Energy Action Plan for 2015 MWa PGE Load With EE Savings 2,620 Remove 5-year Opt-Outs -128 Existing PGE & Contract Resources -1,860 PGE Resource Target 632 Resource Actions Thermal: CCCT 406 Combined Heat & Power 2 Renewable: ETO Energy Savings 119 Existing Contract
Slide 34: Capacity Load-Resource Balance
Capacity Load-Resource Balance Load-Resource Balance (2012-2021) Winter Capacity 6000 Peak Hour before EE + Reserves (excl. 5- 5000 year opt-outs) Peak Hour Load 4000 after EE + Reserves 2015 Shortfall Available Capacity (MW) (excl. 5-year opt-outs) 1,409 before EE Wind - Biglow 1-3, 1,233 after EE
Slide 35: Capacity Action Plan
Capacity Action Plan Capacity Action Plan for 2015 MW PGE Load with EE Savings 4,150 Remove 5-year Opt-Outs -144 Operating Reserves(1) 183 Contingency Reserves(2) 232 Existing PGE & Contract Resources -3,012 PGE Resource Target 1,409 Resource Actions Thermal: CCCT 441 Combined Heat & Power 2 Renewab
Slide 36: Regulatory Environment
Regulatory Environment Oregon Public Utility Commission – Governor-appointed Commission with staggered four-year terms (John Savage 3/2013, Stephen Bloom 12/2015, Susan Ackerman (chair) 3/2016) Return on Equity & Capital Structure – 10.0% allowed return on equity – 50% debt and 50% equity capita
Slide 37: Recovery of Power Costs / Return on Equity
Recovery of Power Costs Annual Power Cost Update Tariff • Annual reset of rates based on forecast of net variable power costs (NVPC) for the coming year • Subject to OPUC prudency review and approval, new prices go into effect on or around January 1 of the following year Power Cost Adjustment Mechan
Slide 38: Renewable Energy Standard
Renewable Energy Standard Additional Renewable Resources Integrated Resource Plan addresses procurement of wind or other renewable resources to meet requirements of Oregon’s Renewable Energy Standard by 2015. Such need is now approximately 100 MWa (or 300 MW wind nameplate capacity) Year Renewable T
Slide 39: Decoupling Mechanism
Decoupling Mechanism The decoupling mechanism is intended to allow recovery of margin lost due to a reduction in sales of electricity resulting from customers’ energy efficiency and conservation efforts Includes a Sales Normalization Adjustment mechanism (SNA) for residential and small non- resident
Slide 40: Cost Efficiency Initiatives
Cost Efficiency Initiatives Company-wide benchmarking to identify best practices Investments to leverage technology – Financial system and supply chain replacement project – Timekeeping System – Enterprise Asset Management Process Improvements & Work Redesign Savings will offset cost inflati
Slide 41: Smart Meter Project
Smart Meter Project Smart Meters Provide two-way communications with residential and commercial customers Vendor: Sensus Technology: FlexNet radio frequency technology Completed installation of 825,000 meters as of December 31, 2010 Capital costs: $145 million OPUC approved limited term
Slide 42: Boardman 2020 Emissions Controls
Boardman 2020 Emissions Controls Emissions Controls at the Boardman Plant In December 2010, the Oregon Environmental Quality Commission (OEQC) approved revised Best Available Retrofit Technology (BART) rules June 2011, EPA approved revised rules, which were published in the Federal Register in J
Slide 43: Biglow Canyon Wind Farm
Biglow Canyon Wind Farm Columbia Gorge, eastern Oregon 450 MW total nameplate capacity Total cost approximately $1B Phase I Phase II Phase III Nameplate Capacity 125 MW, 76 turbines 150 MW, 65 turbines 175 MW, 76 turbines MW per unit 1.65 Megawatts 2.3 Megawatts 2.3 Megawatts Cost (w/AFDC) $25
Portland General Electric — Investor Presentation (September 2012) on 6ix