Akzo Nobel N.V. · EURONEXT:AKZA
Akzo Nobel — Corporate Update (February 2022)
16 slides from Akzo Nobel's corporate update, Feb 16, 2022
Slide 1: Community Forum
Community Forum Feb 16th, 2022
Slide 2: Agenda
Agenda Odour Update Air Monitoring Results Noise Update Reporting of Complaints Questions & Discussion Community Forum #5 February 2022 2
Slide 3: Odour Updates
Odour Updates Community Forum #5 February 2022 3
Slide 4: RTO
RTO • Commissioned & Operational from December 2021 • Initial Golder monitoring results conducted 13th Dec • Further balancing and finetuning of RTO setup Jan 2021 • Follow – Up Golder Monitoring planned Wk 3 Feb • Carbon bed filter remains in place as standby for RTO Community Forum #5 February 202
Slide 5: Paint Plant Update
Paint Plant Update Golder conducting weekly boundary Odour sampling Completed a review of Paint Plant Odour & Emission sources and final report submitted to EPA in January Recommendations from Golder report are being investigated and scoped to remove VoC & Odour sources from Paint Plant Community Fo
Slide 6: Air Monitoring Updates
Air Monitoring Updates Community Forum #5 February 2022 6
Slide 7: Fence line air quality monitoring for VOCs
Fence line air quality monitoring for VOCs ❑ Monitoring undertaken by Golder Associates’ NATA- accredited air quality team ❑ 8 fence line monitoring locations ❑ Monitoring ongoing from March – December ❑ Monitoring continues to show levels of VoC’s significantly below threshold values Community Foru
Slide 8: Noise Review
Noise Review Community Forum #5 February 2022 8
Slide 9: Acoustic Wall
Acoustic Wall Acoustic Wall – Awaiting Council planning approval (submissions for objections closed 28th Jan) – Engineering, scoping & working drawings underway – Building permit and tendering process – Installation will take approx. 12 – 16 weeks – We welcome neighborhood feedback on wall design an
Slide 10: Noise Review
Noise Review Powder Plant continues to cease operations at night. Powder Mill fan upgrade has improved overall noise levels Replacement gearbox of DT 5 completed Noise reduction plan completed and being implemented Focus on engineering controls to eliminate noise sources Seek community feedback to e
Slide 11: Reporting of Complaints
Reporting of Complaints Community Forum #5 February 2022 11
Slide 12: Reporting of Complaints
Reporting of Complaints First Contact site personnel have received training in dealing with reported complaints Response to some complaints not as expected and further training completed Complaints received have been responded to We continue to encourage community members to report issues directly t
Slide 13: Xmas Shutdown Works
Xmas Shutdown Works • Removal & recladding of asbestos sheeting with Colourbond • Roadway Upgrade • Routine Shutdown Maintenance • Thank you to Neighbours along Barwon Avenue for putting up with additional traffic over a number of days Community Forum #5 February 2022 13
Slide 14: Powder Building wall on Barwon Ave
Powder Building wall on Barwon Ave Community Forum #5 February 2022 14
Slide 15: Questions & Discussion
Questions & Discussion Community Forum #5 February 2022 15
Slide 16: Thank you
Thank you