  3. Slide 3: Corporate Snapshot & Select Guidance

    Slide 3: Corporate Snapshot & Select Guidance

    CORPORATE OVERVIEW Corporate Snapshot & Select Guidance(1) Q3 2021 average production 84,924 boe/d Light oil (% of production) 2,878 bbls/d (3%) Condensate (% of production) 5,990 bbls/d (8%) NGLs (% of production) 6,889 bbls/d (8%) Natural gas (% of production) 415 MMcf/d (81%) Q3 2021 adjusted fun

  4. Slide 4: Corporate Snapshot & Select Guidance Continued

    Slide 4: Corporate Snapshot & Select Guidance Continued

    CORPORATE OVERVIEW Corporate Snapshot & Select Guidance Continued Long-term (drawn) debt as at September 30, 2021 $648.3 million Total debt as at September 30, 2021(1) $637.9 million Credit facilities borrowing base limit as at September 30, 2021 $850.0 million Common shares (basic) as at September

  5. Slide 5: 2021E Natural Gas Marketing

    Slide 5: 2021E Natural Gas Marketing

    CORPORATE OVERVIEW 2021E NATURAL GAS MARKETING AECO $3.65 $0.05 $0.46 $3.15 7% 43% 12% Dawn Alliance $4.45 $3.86 $0.19 $0.05 $1.30 $0.43 $2.97 38% $3.38 Henry Hub Note: Birchcliff natural gas realizes Dif. a 10% heat premium(1) US$3.86/MMBtu $4.57 Pricing Hub US$1.23/MMBtu $1.46 Forecasted Sales Pri

  6. Slide 6: Keys to Success

    Slide 6: Keys to Success

    CORPORATE OVERVIEW KEYS TO SUCCESS  Executives with a proven track record, continuity since inception and significant ownership. Management  Highly experienced Management Team with excellent technical knowledge and a long history with the company.  453 (449.9 net) Montney/Doig horizontal wells dr

  7. Slide 7: 2021 Capital Program

    Slide 7: 2021 Capital Program

    LOOKING FORWARD 2021 CAPITAL PROGRAM 2021 Capital Program - Wells Drilled and Brought on Production Total w ells drilled in 2021 Total w ells brought on production in 2021(1) Pouce Coupe Montney D1 horizontal natural gas wells 7 7 Montney D2 horizontal natural gas wells 3 3 Montney C horizontal natu

  8. Slide 8: Preliminary Outlook for 2022

    Slide 8: Preliminary Outlook for 2022

    LOOKING FORWARD PRELIMINARY OUTLOOK FOR 2022(1) Annual average production: 78,000 – 80,000 boe/d The continued strengthening of Birchcliff’s balance sheet also provides optionality to increase shareholder returns, including increased dividends and Adjusted funds flow: ~$650 MM(2)(3) common share rep

  9. Slide 9: Production History

    Slide 9: Production History

    TRACK RECORD OF EXECUTION PRODUCTION HISTORY 90,000 79,000 - 80,000 77,977 76,401 80,000 77,096 Compound per-share production growth of 10% per year since 2005. 70,000 (11% since Phase I of the Pouce Coupe 67,963 Average Production (boe/d) Gas Plant was completed in 2010) 60,000 49,236 50,000 38,950

  10. Slide 10: Corporate Reserves

    Slide 10: Corporate Reserves

    TRACK RECORD OF EXECUTION CORPORATE RESERVES(1) 1,200,000 $7,000 PDP - Reserves 1,100,000 TP - Reserves 2P - Reserves $6,000 1,000,000 PDP - NPV10 On a per share basis PDP, TP and 900,000 TP - NPV10 2P reserves have increased at a compound annual growth rate of $5,000 2P - NPV10 800,000 12%, 18% and

  11. Slide 11: Proven Track Record as a Low-Cost Producer

    Slide 11: Proven Track Record as a Low-Cost Producer

    TRACK RECORD OF EXECUTION PROVEN TRACK RECORD AS A LOW-COST PRODUCER 5 Year Profitability Breakdown: 2016 2017 2018 2019 2020 Average Average AECO (CDN$/GJ) $2.05 $2.04 $1.42 $1.67 $2.11 $1.86 Average WTI (US$/bbl) $43.32 $50.95 $64.77 $57.03 $38.91 $51.00 P&NG Revenue ($/Mcfe)(1) $3.12 $3.74 $3.68

  12. Slide 12: Proven Track Record as a Low-Cost Finder

    Slide 12: Proven Track Record as a Low-Cost Finder

    TRACK RECORD OF EXECUTION PROVEN TRACK RECORD AS A LOW-COST FINDER $12 PDP F&D 1P F&D 2P F&D Adjusted funds flow $10 netback recycle ratios(1) 0.6x F&D Cost ($/boe) $8 1.3x 1.4x 1.6x 1.5x 1.3x 1.8x 0.9x $6 1.0x 1.3x 2.0x 1.9x 1.8x 1.7x 2.0x $4 1.8x $2 17.4x 8.8x $0 2016 2017 2018 2019 2020 5 Yr Avg

  13. Slide 13: Peer Emissions Metrics

    Slide 13: Peer Emissions Metrics

    ENVIRONMENTAL, SOCIAL AND GOVERNANCE PEER EMISSIONS METRICS(1)(2)(3)(4) November 10, 2021 13

  14. Slide 14: Commitment to Environmental Stewardship

    Slide 14: Commitment to Environmental Stewardship

    ENVIRONMENTAL, SOCIAL AND GOVERNANCE COMMITMENT TO ENVIRONMENTAL STEWARDSHIP Waste heat recovery units at the Pouce Coupe Gas Plant take the equivalent of >5,000 cars off the road annually. Peer-leading water storage and infrastructure has taken the equivalent of over 50,000 large water handling tru

  15. Slide 15: Investing in Our People and the Community

    Slide 15: Investing in Our People and the Community

    ENVIRONMENTAL, SOCIAL AND GOVERNANCE INVESTING IN OUR PEOPLE AND THE COMMUNITY $4.25 million donated to more than 100 local community groups and organizations in the last 5 years. Continued partnerships with local communities through educational, cultural, and economic development initiatives. Major

  16. Slide 16: Montney/Doig - A World Class Resource Play

    Slide 16: Montney/Doig - A World Class Resource Play

    MONTNEY/DOIG RESOURCE PLAY MONTNEY/DOIG - A WORLD CLASS RESOURCE PLAY 440 gross (437.7 net) Montney/Doig horizontal wells producing as of Dec 31, 2020 Resource density. Stacked resource up to 300 metres thick. Large areal extent. Extends over 50,000 square miles. Exceptional “fracability”. Low clay

  17. Slide 17: Montney/Doig Mineralogy Leads to Excellent Fracability

    Slide 17: Montney/Doig Mineralogy Leads to Excellent Fracability

    MONTNEY/DOIG RESOURCE PLAY MONTNEY/DOIG MINERALOGY LEADS TO EXCELLENT “FRACABILITY” The Montney/Doig Resource Play rock type is composed of a Some other resource plays have a high percentage of clays high percentage of hard minerals, and a low percentage of and soft minerals. When fractured this res

  18. Slide 18: Birchcliff's Montney/Doig Resource Play

    Slide 18: Birchcliff's Montney/Doig Resource Play

    MONTNEY/DOIG RESOURCE PLAY BIRCHCLIFF’S MONTNEY/DOIG RESOURCE PLAY • Large contiguous land base with 415.7 (394.6 net) sections prospective for the Montney/Doig as at December 31, 2020. • Birchcliff has a contiguous land block at Pouce Coupe and Gordondale of approximately 228 net sections. • Stacke

  19. Slide 19: Montney/Doig Multi-Layer Opportunity

    Slide 19: Montney/Doig Multi-Layer Opportunity

    MONTNEY/DOIG RESOURCE PLAY MONTNEY/DOIG MULTI-LAYER OPPORTUNITY November 10, 2021 19

  20. Slide 20: Science & Technology Pad

    Slide 20: Science & Technology Pad

    MONTNEY/DOIG RESOURCE PLAY SCIENCE & TECHNOLOGY PAD November 10, 2021 20

  21. Slide 21: Birchcliff Montney/Doig Inventory 2020YE

    Slide 21: Birchcliff Montney/Doig Inventory 2020YE

    MONTNEY/DOIG RESOURCE PLAY BIRCHCLIFF MONTNEY/DOIG INVENTORY 2020YE Note: Location inventory includes three (3) 100% W.I. existing wells that have proved non-producing reserves. (2 in Pouce Coupe and 1 in Elmworth). November 10, 2021 21

  22. Slide 22: 2020 Liquids Summary

    Slide 22: 2020 Liquids Summary

    MONTNEY/DOIG RESOURCE PLAY 2020 LIQUIDS SUMMARY 2020 Well Rates (IP60) MULTI-INTERVAL CUBE-STYLE DEVELOPMENT Discovery of Extension to the Gordondale Light Oil Pool • In Q3 2020, Birchcliff brought the production on from its 14-well pad (14-19-079-12W6) located in the northeastern area of Pouce Coup

  23. Slide 23: 2021 Capital Program

    Slide 23: 2021 Capital Program

    MONTNEY/DOIG RESOURCE PLAY 2021 CAPITAL PROGRAM 2021 Budget Locations & Well Rates (IP60) MULTI-INTERVAL CUBE-STYLE DEVELOPMENT 2021 Capital Program Major Themes • 2021 Capital Program focused on low-risk drilling opportunities to generate free funds flow. • Majority of capital to be spent on DCCET

  24. Slide 24: Pouce Coupe Overview

    Slide 24: Pouce Coupe Overview

    POUCE COUPE POUCE COUPE OVERVIEW • Proven asset in development phase. • Wells show high initial deliverability, low terminal decline and stable long term production. • Predictable results with improving gas rates and liquids yields. • No land expiry issues. • The 2021 drilling program included 19 (1

  25. Slide 25: 8-Well 14-28 Pad Raw Production

    Slide 25: 8-Well 14-28 Pad Raw Production

    POUCE COUPE 8-WELL 14-28 PAD RAW PRODUCTION (BOE/D) 8-well pad continuing to build on multi- interval cube-style development success 14-28 Pad Initial Results IP 30(1) IP 60(1) Aggregate production rate (boe/d) 9,214 9,154 Aggregate natural gas production rate (Mcf/d) 50,635 51,367 Aggregate condens

  26. Slide 26: Pouce Coupe 2021 Type Curve

    Slide 26: Pouce Coupe 2021 Type Curve

    POUCE COUPE POUCE COUPE 2021 TYPE CURVE *Assumptions: Fx 1.25 (CDN$ to US$1). *All economics are before tax; reference date is January 1, 2021. November 10, 2021 26

  27. Slide 27: Multi-Interval Cube-Style Development

    Slide 27: Multi-Interval Cube-Style Development

    POUCE COUPE MULTI-INTERVAL CUBE-STYLE DEVELOPMENT November 10, 2021 27

  28. Slide 28: Gordondale Overview

    Slide 28: Gordondale Overview

    GORDONDALE GORDONDALE OVERVIEW • High oil & NGLs weighting. • Strategic infrastructure. • Low base production decline. • The 2021 drilling program included 8 (8.0 net) horizontal oil and natural gas wells: 2 Montney D1 natural gas wells, 1 Montney D2 natural gas well, 1 Montney C natural gas well, 2

  29. Slide 29: 4-Well 06-35 Pad Raw Production

    Slide 29: 4-Well 06-35 Pad Raw Production

    GORDONDALE 4-WELL 06-35 PAD RAW PRODUCTION (BOE/D) Continued successful development of the Montney D1 & D2 intervals 06-35 Pad Initial Results (1) (1) IP 30 IP 60 Aggregate production rate (boe/d) 5,421 5,069 Aggregate natural gas production rate (Mcf/d) 27,879 26,640 Aggregate light oil production

  30. Slide 30: Gordondale Base Production History

    Slide 30: Gordondale Base Production History

    GORDONDALE GORDONDALE BASE PRODUCTION HISTORY(1) Birchcliff Last well drilled in 2014 (on-stream 2015) Added Field Acquisition with peak production of ~35,000 boe/d Compression (~22,000 BOE/d) Scheduled AltaGas Plant Turnaround AltaGas deep-cut Plant on- stream October 2012 and Montney oil pool deve

  31. Slide 31: Gordondale 2021 Halo Oil Type Curve

    Slide 31: Gordondale 2021 Halo Oil Type Curve

    GORDONDALE GORDONDALE 2021 HALO OIL TYPE CURVE *Assumptions: Fx 1.25 (CDN$ to US$1). *All economics are before tax; reference date is January 1, 2021. November 10, 2021 31

  32. Slide 32: Pouce Coupe Drilling Performance

    Slide 32: Pouce Coupe Drilling Performance

    D&C CONTINUOUS PERFORMANCE IMPROVEMENT POUCE COUPE DRILLING PERFORMANCE November 10, 2021 32

  33. Slide 33: Pouce Coupe Completion Evolution

    Slide 33: Pouce Coupe Completion Evolution

    D&C CONTINUOUS PERFORMANCE IMPROVEMENT POUCE COUPE COMPLETION EVOLUTION Completion Parameter 2016 2017 2018 2019 2020 2021 Design # of Wells 14 37 15 17 24 25 Completion Fluid Slickwater Slickwater Slickwater Slickwater Slickwater Slickwater Lateral Length (m) 2,074 2,202 2,478 2,298 2,201 2,692 Num

  34. Slide 34: Gordondale Drilling Performance

    Slide 34: Gordondale Drilling Performance

    D&C CONTINUOUS PERFORMANCE IMPROVEMENT GORDONDALE DRILLING PERFORMANCE November 10, 2021 34

  35. Slide 35: Gordondale Completion Evolution

    Slide 35: Gordondale Completion Evolution

    D&C CONTINUOUS PERFORMANCE IMPROVEMENT GORDONDALE COMPLETION EVOLUTION Asset Acquired Asset Acquired Completion Parameter 2016 2017 2018 2019 2020 2021 Design # of Wells 22 13 16 8 8 Completion Fluid Slickwater Slickwater Slickwater Slickwater Slickwater Lateral Length (m) 2,352 1,959 2,058 2,273 2,

  36. Slide 36: Engineered Completions for Montney/Doig Development

    Slide 36: Engineered Completions for Montney/Doig Development

    D&C CONTINUOUS PERFORMANCE IMPROVEMENT ENGINEERED COMPLETIONS FOR MONTNEY/DOIG DEVELOPMENT Industry Range Birchcliff Best Practices Oil Birchcliff Best Practices Gas Liner type Openhole or Cemented Cemented Cemented Fluid CO2, N2, Hybrid, Slickwater Slickwater Slickwater 100 – 400 m 200 – 250 m 300

  37. Slide 37: Pouce Coupe Gas Plant

    Slide 37: Pouce Coupe Gas Plant

    POUCE COUPE GAS PLANT Production Processed through the Pouce 2018 2019 2020 9mo/21 Coupe Gas Plant 31% Average production: Natural gas (Mcf/d) 250,011 263,108 239,419 255,870 69% Condensate & NGLs (bbl/d) 2,609 4,735 5,440 5,808 Total (boe/d) 44,278 48,587 45,343 48,453 9mo/21 Natural Gas Volumes Pr

  38. Slide 38: Key Strategic Advantages

    Slide 38: Key Strategic Advantages

    POUCE COUPE GAS PLANT KEY STRATEGIC Corporate Operating Costs vs. % of Natural Gas Sales Volumes Processed at the Pouce Coupe Gas Plant $8.00 100% Corporate Operating Cost ($/boe) ADVANTAGES $6.00 80% 60% $4.00 • 100% owned and operated. 40% • Generates operating cost savings of $2.00 20% approximat

  39. Slide 39: Building on Our Past

    Slide 39: Building on Our Past

    BUILDING ON OUR PAST Forecasted annual average production of Birchcliff’s average daily production was 76,401 boe/d in 79,000-80,000 boe/d in 2020 compared to 2,793 boe/d in 2005, a compounded 2021 annual growth rate of 25% per year over that span. 1 2 3 4 5 6 7 8 9 10 11 12 2004 2021 July 2016: Com

  40. Slide 40: Building on Our Past: Production Growth and Cost Reduction

    Slide 40: Building on Our Past: Production Growth and Cost Reduction

    BUILDING ON OUR PAST Birchcliff has increased production at a compound annual growth rate of 25% since 2005. Operating & Total Cash Costs(1) $20 Operating and Total Cash Costs $18 $16 have decreased by 72% and 41% $14 $12 since 2008 largely due to horizontal drilling success and benefits $/boe $10 $

  41. Slide 41: Building on Our Past: Reserves Growth

    Slide 41: Building on Our Past: Reserves Growth

    BUILDING ON OUR PAST Reserves Growth 1,200 4,800 Birchcliff has added significant 1,000 4,000 low cost reserves since 800 3,200 commencing operations in boe/1,000shares MMboe 600 2,400 2005. On a per common share 400 1,600 basis, PDP, TP and 2P reserves 200 800 grew 12% per year, 18% per 0 0 year an

  42. Slide 42: Canada's LNG Advantage

    Slide 42: Canada's LNG Advantage

    APPENDIX CANADA’S LNG ADVANTAGE Cleaning Our World’s Environment, a 2.0 Bcf/d LNG Facility Could: • Displace 50 million tonnes of carbon emissions from coal-fired power generation. • Replace approximately 10 large-scale coal fired power plants in China. Benefits • Reduce Alberta’s 2016 annual GHGs o

  43. Slide 43: Proximal to Infrastructure with Long Term Exposure to LNG Export

    Slide 43: Proximal to Infrastructure with Long Term Exposure to LNG Export

    APPENDIX PROXIMAL TO INFRASTRUCTURE WITH LONG TERM EXPOSURE TO LNG EXPORT Montney/Doig Birchcliff Montney/Doig Production Resource Play Owned Infrastructure Pouce Coupe Gas Plant Nova Pipeline System North American Market LNG Export Source: RBC Energy Insights: The Montney – Tracking an Elephant Aug

  44. Slide 44: Montney/Doig Well Locations

    Slide 44: Montney/Doig Well Locations

    APPENDIX MONTNEY/DOIG WELL LOCATIONS Existing and Potential Future Drilling Locations by Interval at December 31, 2020 Average Proved Plus Probable Reserves plus Cumulative Gross Number of 2P Net Number of 2P Production Horizontal Well Locations Horizontal Well Locations (Bcfe) Potential Potential P

  45. Slide 45: Series A Perpetual Preferred Shares

    Slide 45: Series A Perpetual Preferred Shares

    APPENDIX SERIES A PERPETUAL PREFERRED SHARES Preferred Share Details Series A Number of Shares 2,000,000 Issue Date August 8, 2012 TSX Trading Symbol BIR.PR.A Issue / Par Price $25.00 per share Quarterly Dividend $0.523375 per share Yield on Par Price 8.374% Redeemable by Holder No • September 30, 2

  46. Slide 46: Series C Preferred Shares

    Slide 46: Series C Preferred Shares

    APPENDIX SERIES C PREFERRED SHARES Preferred Share Details Series C Number of Shares 1,533,108 Issue Date June 14, 2013 TSX Trading Symbol BIR.PR.C Issue / Par Price $25.00 per share Quarterly Dividend $0.4375 per share Yield at Issue 7.0% Redeemable by Birchcliff or the June 30, 2020 and each Holde

  47. Slide 47: Corporate Information

    Slide 47: Corporate Information

    CORPORATE INFORMATION OFFICERS AUDITORS A. Jeffery Tonken KPMG LLP, President, CEO and Chairman of the Board Chartered Professional Accountants Calgary, Alberta Myles R. Bosman Vice-President, Exploration and Chief Operating Officer RESERVES EVALUATORS Bruno P. Geremia Deloitte LLP Vice-President an

  48. Slide 48: Advisories: Definitions and Abbreviations

    Slide 48: Advisories: Definitions and Abbreviations

    ADVISORIES DEFINITIONS Deloitte Deloitte LLP, independent qualified reserves evaluator McDaniel McDaniel & Associates Consultants Ltd., independent reserves evaluator Pouce Coupe Gas Plant Birchcliff’s 100% owned and operated natural gas plant located in the Pouce Coupe area of Alberta ABBREVIATIONS

  49. Slide 49: Advisories

    Slide 49: Advisories

    ADVISORIES “Adjusted funds flow” denotes cash flow from operating activities before the effects of decommissioning expenditures and changes in non-cash operating working capital. Birchcliff eliminates settlements of decommissioning expenditures from cash flow from operating activities as the amounts

  50. Slide 50: Advisories: BOE and MCFE Conversions

    Slide 50: Advisories: BOE and MCFE Conversions

    ADVISORIES BOE AND MCFE CONVERSIONS Boe amounts have been calculated by using the conversion ratio of 6 Mcf of natural gas to 1 bbl of oil and Mcfe amounts have been calculated by using the conversion ratio of 1 bbl of oil to 6 Mcf of natural gas. Boe and Mcfe amounts may be misleading, particularly

  51. Slide 51: Advisories: Forward-Looking Information

    Slide 51: Advisories: Forward-Looking Information

    ADVISORIES FORWARD-LOOKING INFORMATION Certain statements contained in this presentation constitute forward-looking statements and forward-looking information (collectively referred to as “forward-looking statements”) within the meaning of applicable Canadian securities laws. The forward-looking sta

  52. Slide 52: Thank You Team Birchcliff

    Slide 52: Thank You Team Birchcliff

    THANK YOU TEAM BIRCHCLIFF Jeffrey Akeroyd, Bradley Alexander, Karen Allen, Diana Almeida, Tracy Anderson, Camille Ashton, Gaetano Aurigemma, Angela Belbeck, Tyrus Bender, Riley Berge, Lindsey Berlinger, Daniel Blattler, Calvin Bohdan, Angela Boire, Darryl Bolch, Deborah Borthwick, Myles Bosman, Jeff

Source: Internet Archive copy of birchcliffenergy.com

More decks from Birchcliff Energy Ltd.

All 36 Birchcliff Energy decks