Slide 1: Barberton Gold Mines: Operations at SA's Oldest Gold Mine
BARBERTON GOLD MINES OPERATIONS AT SA’S OLDEST GOLD MINE
Slide 2: Disclaimer
DISCLAIMER This presentation is provided on a confidential basis. The name 'Presenter' refers to Pan African Resources PLC and its advisors, subsidiaries or affiliated companies. This presentation has not been filed, lodged, registered or approved in any jurisdiction and recipients of this document
Slide 3: Overview of Presentation
OVERVIEW OF PRESENTATION • Overview and history of Barberton Mines • Current mining methods • Further exploration potential 3
Slide 4: Overview of Barberton Gold Mines
OVERVIEW OF BARBERTON GOLD MINES
Slide 5: Overview of Barberton Mines ('BML')
OVERVIEW OF BARBERTON MINES (‘BML’) • Mining started in 1886 at Sheba Mines – oldest operating mine • Currently BML have three operations i.e. Sheba, New Consort and Fairview • BML treat about 24 000 ore tons per month at about 11g/t • BML also have a Tailings Retreatment Plant (90,000t/m) • Combine
Slide 6: Locality of Barberton Mines
LOCALITY OF BARBERTON MINES 6
Slide 7: Start of the Golden Quarry - Sheba
START OF THE GOLDEN QUARRY - SHEBA This is where it all started. After this discovery a company was floated and the first shares were sold at £1 and it increased to £120 7
Slide 8: Edwin Bray Adit at Sheba Mine
EDWIN BRAY ADIT AT SHEBA MINE Edwin Bray Adit when it started – Oldest photo of this adit available 8
Slide 9: Edwin Bray Adit in Progress
EDWIN BRAY ADIT IN PROGRESS 1 ee za 5 + TOT lf
Slide 10: Edwin Bray Adit in Production
EDWIN BRAY ADIT IN PRODUCTION 10
Slide 11: Edwin Bray Adit Still in Use
EDWIN BRAY ADIT STILL IN USE 11
Slide 12: Edwin Bray Adit Still in Use
EDWIN BRAY ADIT STILL IN USE Edwin Bray Adit still in use – 127 years later 12
Slide 13: Sheba Mine - ZK Vertical Shaft
SHEBA MINE - ZK VERTICAL SHAFT Sheba Mine – SK vertical shaft – Today (110 years old) 13
Slide 14: Fairview Mine Stamp Mill
FAIRVIEW MINE STAMP MILL Very early days of Fairview, on top of the mountain 14
Slide 15: Fairview – Main Adit
FAIRVIEW – MAIN ADIT Fairview Main Adit being used today 15
Slide 16: New Consort – 1 Level
NEW CONSORT – 1 LEVEL Early days at New Consort No1 level entrance 16
Slide 17: New Consort - Main Adit
NEW CONSORT - MAIN ADIT New Consort Main Adit today ± 60 years old 17
Slide 18: BIOX Plant
Ba he La BlOXe PLANT BIOXe Plant
Slide 19: Barberton Tailings Retreatment Plant – 'BTRP'
BARBERTON TAILINGS RETREATMENT PLANT – ‘BTRP’ BTRP 19
Slide 20: Current Mining Methods
CURRENT MINING METHODS
Slide 21: Current Mining Methods
CURRENT MINING METHODS • Mechanised Mining – Cut and fill (90%) Breast & Updip • Open Stoping – Conventional Mining (10%) • Shrinkage Mining (0%) 21
Slide 22: Current Mining Method
CURRENT MINING METHOD • Mechanised Mining – Cut and fill (90%) Waste from your infrastructure development is hauled back into stope for fill (Ramp system and Access cross cut which is then fan lifted) 55% of reef tons removed equates to waste tonnage requirement for waste fill (Development meter
Slide 23: Current Mining Method
CURRENT MINING METHOD Simplified section view of stoping/mining layout 23
Slide 24: Current Mining Method
2 CURRENT MINING METHOD Simplified plan view of stoping/mining layout 24
Slide 25: Current Mining Method
2 CURRENT MINING METHOD Close up section of floor support in 1st cut 25
Slide 26: Current Mining Method
2 CURRENT MINING METHOD Close up section of floor support in 1st cut 26
Slide 27: Current Mining Method
2 CURRENT MINING METHOD Close up plan view of floor support in 1st cut 27
Slide 28: Current Mining Method
2 CURRENT MINING METHOD Close up plan view of floor support in 1st cut 28
Slide 29: Current Mining Method
2 CURRENT MINING METHOD Close up plan view of floor support in 1st cut 29
Slide 30: Current Mining Method: Stoping Cycles
2 CURRENT MINING METHOD Stoping cycles 30
Slide 31: Current Mining Method: Stoping Cycles
2 CURRENT MINING METHOD Stoping cycles 31
Slide 32: Current Mining Method
2 CURRENT MINING METHOD Section along strike of stope showing Breast mining & Updip mining 32
Slide 33: Fall of Ground Measures
FALL OF GROUND MEASURES • Mechanised Mining – Cut and fill (90%) Because the back areas are filled with waste the overall stability of the stopes are good At Fairview we are mining at about 1800m below surface and have not seen any seismic related activities Only the current stope face area is
Slide 34: MRC Ore Body and Exploration Potential
MRC ORE BODY AND EXPLORATION POTENTIAL
Slide 35: Barberton Mines - Fairview
BARBERTON MINES - FAIRVIEW • The MRC is the second richest orebody in the world • Current life of orebody is 26 years, which greatly exceeds the BML life of mine • There is a realistic potential for MRC to continue at depth 35
Slide 36: The Top Highest Grade Underground Gold Operations
BARBERTON MINES - FAIRVIEW The top 10 highest grade underground gold operations Data retrieved from the IntelligenceMine database - Published in MINING.COM on 16 July 2015 36
Slide 37: The Top Highest Grade Underground Gold Operations
BARBERTON MINES - FAIRVIEW The top 10 highest grade underground gold operations (What the table should look like in reality) 37
Slide 38: MRC Orebody
2 BARBERTON MINES - FAIRVIEW MRC Orebody 38
Slide 39: MRC Orebody
2 BARBERTON MINES - FAIRVIEW MRC Orebody 39
Slide 40: Exploration Potential at BML
BARBERTON MINES Exploration Potential at BML Unique geology Amira Project Study by University of Western Australia Current UJ study 40
Slide 41: Metamorphic Devolatilisation
BARBERTON MINES Metamorphic devolatilisation Transition from greenschist to amphibolite facies triggers process of devolatilisation H2O-CO2-H2S fluids are released from mineral crystal structures and these fluids can transport gold to favourable depositional sites Adequate amounts of gold can
Slide 42: Metamorphic Devolatilisation
BARBERTON MINES Metamorphic devolatilisation At higher pressure (and T) gold solubility is higher When pressure is released, H2S (the ligand that makes gold soluble) is driven off, resulting in gold precipitation Pressure shadows, which can form during faulting and folding, create spaces effec
Slide 43: Calculated Volume of Source Rock Required for a Deposit
BARBERTON MINES Calculated volume of source rock required to form a deposit containing a given amount of gold Barberton Greenstone Belt contains 1600 cubic km source rock 43
Slide 44: Geological Map
BARBERTON MINES Geological map 44
Slide 45: Amira Project – 3D Model
BARBERTON MINES Amira Project – 3D model 45
Slide 46: Amira Project – Including Geological Features
BARBERTON MINES Amira Project – including geological features 46
Slide 47: Amira Project – High Potential Areas
BARBERTON MINES Amira Project – high potential areas N Large deposit Sheba Stress Fairview High Low 3 km 47
Slide 48: Semi-mechanised Stoping
BARBERTON MINES Semi-mechanised Stoping 48
Slide 49: Waste Filling
BARBERTON MINES Waste Filling 49
Slide 50: Up-dip Drilling
BARBERTON MINES Up-dip drilling 50
Slide 51: Up-dip Drilling
BARBERTON MINES Up-dip drilling 51
Slide 52: Breast Mining – Waste Fill
BARBERTON MINES Breast Mining – Waste Fill 52
Slide 53: Breast – Face Drilling
BARBERTON MINES Breast – Face Drilling 53
Slide 54: Compacting – Prior to Cement Cap
BARBERTON MINES Compacting – prior to cement cap 54
Slide 55: Sweeping – Between Reef and Waste Pile
BARBERTON MINES Sweeping – Between Reef and Waste Pile 55
Slide 56: Thank You