  1. Slide 1: Wimmera Project Noise and Vibration Impact Assessment

    Wimmera Project Noise and Vibration Impact Assessment Community Information Session 24 March 2021

  2. Slide 2: Noise and Vibration Impact Assessment

    Noise and Vibration Impact Assessment Noise and Vibration Assessment Objectives Measurement of Existing Conditions Criteria Impact Assessment Mitigation

  3. Slide 3: Noise and Vibration – EES Draft Evaluation Objective

    Noise and Vibration – EES Draft Evaluation Objective • To protect the health and wellbeing of the community, and minimise effects on air quality, noise and social amenity. • Assess the likely noise increases, and vibration impacts at sensitive receptors in the vicinity of the project and along the p

  4. Slide 4: Noise and Vibration – Key legislation and guidance

    Noise and Vibration – Key legislation and guidance Construction Operation State State • Civil construction, building and demolition • Environmental Protection Act 1970 (Vic) guide (EPA Vic Publication No. 1834) • Environmental Protection Amendment Act Vibration (No applicable AS/NZ standards) 2017 (

  5. Slide 5: Mine layout and closest receptors

    Mine layout and closest receptors • Sensitive receptors in all directions surrounding the mine site. • Noise levels modelled for all sensitive receptors within 5km of the mine site including, Noradjuha, Toolondo and Clear Lake. • Six receptors within mine layout development envelope will require an

  6. Slide 6: Baseline noise monitoring

    Baseline noise monitoring Period Average LA90 dB Day 27 to 34 Evening 26 to 32 Night 21 to 25 • Noise monitoring in February 2019 for one month at six locations. • Further monitoring in March 2020 at three locations. • Typical noise levels for rural environment. Red Gum Swamp

  7. Slide 7: Baseline vibration monitoring

    Baseline vibration monitoring Site 2 • Site 1 - Natimuk-Hamilton Road • Site 2 - Nurrabiel Church Road Measured existing vibration levels are low, and below human comfort vibration criteria for a residential building. Site 1

  8. Slide 8: Construction noise and vibration assessment

    Construction noise and vibration assessment Stage Activity Duration Description • Construction works will occur predominantly C1 Bulk/earthworks/civils 2 months Clearing and preparing site, excavations during normal (daytime) working hours, for a period of up to two years. C2 Concrete works 4 months

  9. Slide 9: Construction noise assessment

    Construction noise assessment

  10. Slide 10: Operational noise assessment

    Operational noise assessment Noise from Industry in Regional Victoria (NIRV) Publication 1411 Recommended Maximum Noise Levels (RMNLs) Day Evening Night 46 dB(A) 41 dB(A) 36 dB(A)

  11. Slide 11: Operational noise modelling

    Operational noise modelling • Noise model includes mining fleet, processing plant, and other ancillary equipment including truck movements • Fixed location of mineral unit plant (MUP) • Noise levels modelled by Years 1, 7, 13, 16, 17 and 19 • Noise modelling is an iterative process to assess mitigat

  12. Slide 12: Operation - Initial mitigation measures

    Operation - Initial mitigation measures • Dredge mining method • Fixed location of mineral unit plant (MUP) • Stockpiles • AMC cell activity day period only Dredge • Reduced night time ancillary and mining activities Amphiroller in the Accelerated Mechanical Consolidation (AMC) cell

  13. Slide 13: Operational noise assessment Year 1

    Operational noise assessment Year 1 Dredge

  14. Slide 14: Operational noise assessment Year 16

    Operational noise assessment Year 16 Dredge Red Gum Swamp

  15. Slide 15: Key findings - Operation

    Key findings - Operation 5km Night-time mining Operational noise is predicted to exceed the NIRV 2km Recommended Maximum Noise Level (36 dB(A)) 1km • Red – exceedance > 7 dB • Yellow – exceedance < 7 dB • Blue – exceedance <2 dB Exceedances in the north primarily due to the processing plant, elsewhe

  16. Slide 16: Noise and vibration assessment - Transport Route

    Noise and vibration assessment - Transport Route Horsham • Four transport route options under consideration. • 60 truck movements per 24-hour period, (2 to 3 movements per hour). • Assessment to consider the noise impacts and potential for sleep disturbance at receptors within Noradjua 100 metres fr

  17. Slide 17: Next steps - development of mitigation measures

    Next steps - development of mitigation measures • Consultation with the local community to discuss the noise and vibration impact assessment. • Discussions with the EPA, council and stakeholders. • Refinement of proposed operations and mitigation measures to satisfy the evaluation objectives set out