Agl Energy Limited · ASX:AGL

Agl Energy — Corporate Update (July 2015)

23 slides from Agl Energy's corporate update, Jul 1, 2015

  1. Slide 1: Broken Hill Solar Plant Community Information Session

    Broken Hill Solar 1 Plant Community Information Session 1 July 2015

  2. Slide 2: Agenda

    2 Agenda Welcome May CIS 1 Overview of project status – AGL / First Solar 2 3 Employment 4 Project planning 5 Construction community fund 6 Next meeting > AGL Broken Hill Solar Plant > 1 July 2015

  3. Slide 3: Review actions from previous meeting

    3 2. Review actions from previous meeting Action item CIS Status Who meeting 1 Coordinate community group visit to the site when February Closed HO panels installation underway 2015 > AGL Broken Hill Solar Plant > 1 July 2015

  4. Slide 4: Overview of project status

    4 Overview of project status • Adam Mackett (AGL) • Samantha Coras (First Solar) > Presentation title > Author > Date (Verdana 10pt)

  5. Slide 5: AGL overview of project status

    5 2. AGL overview of project status Solar Plant › The changing face of the Broken Hill Solar Plant » Top: January 2015 (civil work) » Middle: April 2015 (module install) » Bottom: May 2015 (module install / termination) › Installation of First Solar PV modules commenced at the start of April › Half

  6. Slide 6: Connection Works (CPP)

    6 2. AGL overview of project status Connection Works (CPP) › 2 x 22kV transmission line was practically complete at the end of February 2015, including crossing of the ARTC rail. › Operating protocol with TransGrid (Network Services Provider) finalised and executed. › Feeder No.2 of the 2 x 22kV tra

  7. Slide 7: Recent stakeholder site visit

    7 2. AGL overview of project status Recent stakeholder site visit › Broken Hill City Council Site Visit (6 May 2015) » Site visit included local media → very positive feedback › AGL Chief Engineer Site Visit (6 May 2015) › Broken Hill Community Site Visit (28 May 2015) – Photo » Feedback > Broken Hi

  8. Slide 8: Nyngan Solar Plant

    8 2. AGL overview of project status Nyngan Solar Plant › Full generation (102 MW) was achieved on Saturday, 6 June 2015. > Broken Hill Solar Plant > AGL Energy > 1 July 2015

  9. Slide 9: Nyngan Solar Plant

    9 2. AGL overview of project status Nyngan Solar Plant › Low irradiance levels on Friday before full generation on Saturday > Broken Hill Solar Plant > AGL Energy > 1 July 2015

  10. Slide 10: Nyngan Solar Plant

    10 2. AGL overview of project status Nyngan Solar Plant › Generation at point of connection (commenced Saturday, 21 March 2015) › Cumulative generation at 23:30hrs on Friday, 26 June 2015 was 32,314.40** MWh » ** Gaps in June due to AEMO/EE SCADA – Nyngan was generation factored in cumulative total

  11. Slide 11: First Solar

    11 3. First Solar overview of project status > AGL Broken Hill Solar Plant > 1 July 2015

  12. Slide 12: First Solar overview of project status

    12 3. First Solar overview of project status Sub contracts: Three packages of work – civil, structural and electrical › Structural work completed in May 2015 (CTE) › Electrical work in full progress (RCR | ODG) › Testing and commissioning activities commenced (STE, First Solar) Procurement and deliv

  13. Slide 13: First Solar overview: construction

    13 3. First Solar overview of project status Construction: › Structural work completed in May 2015 › Electrical work in full progress - Trenching for underground cables - 350,000 solar PV modules installed - Installing above ground and underground cabling - Switchgear on site required for grid conne

  14. Slide 14: Table structure and cable installation

    14 3. First Solar overview of project status Table structure installation Above ground cable installation > Broken Hill Solar Plant > 1 July 2015

  15. Slide 15: Switchgear lifting and block looking south

    15 3. First Solar overview of project status Lifting switchgear into position Block 2 looking south > AGL Broken Hill Solar Plant > 1 July 2015

  16. Slide 16: Employment

    16 Employment • Samantha Coras (First Solar) > Presentation title > Author > Date (Verdana 10pt)

  17. Slide 17: Project employment

    17 4. Project employment RCR Infrastructure electrical contractor – main subcontractor for First Solar › 130 people inducted › 150 working on site, approximately half are locals, the number fluctuates depending on the work stage › Note: Hays are no longer recruiting for First Solar and RCR Infrastru

  18. Slide 18: Project Planning

    18 Project Planning • Helena Orel (AGL) • Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)

  19. Slide 19: Project planning

    19 5. Project planning Recent stakeholder site visits › May 28 – Broken Hill community group › Feedback? > AGL Broken Hill Solar Plant > 1 July 2015

  20. Slide 20: Construction Community Fund

    20 Construction Community Fund • Helena Orel (AGL) > Presentation title > Author > Date (Verdana 10pt)

  21. Slide 21: Construction Community Fund

    21 6. Construction Community Fund › Next round of funding will be advertised in September 2015 › Ads will run for four weeks › Expect to complete process (assessment / cheque handover) November > AGL Broken Hill Solar Plant > 1 July 2015

  22. Slide 22: Next meeting

    22 Next meeting > Presentation title > Author > Date (Verdana 10pt)

  23. Slide 23: Next meeting

    23 7. Next meeting › Any questions? › Next meeting date (proposed for Wednesday 9 September 2015) › Agenda items > AGL Broken Hill Solar Plant > 1 July 2015