    ASX and MEDIA RELEASE 21 July 2022 For personal use only Noosa Mining Conference Presentation Alkane Resources Limited’s Managing Director, Mr Nic Earner, will be presenting at the Noosa Mining Conference today at 11:30am (AEST), (9:30am (AWST)). A copy of Mr Earner’s presentation is attached. This

  2. Slide 2: Noosa Mining Conference Presentation

    For personal use only NOOSA MINING CONFERENCE PRESENTATION Nic Earner, Managing Director 21 July 2022 © 2022 Alkane Resources

  3. Slide 3: Disclaimer

    Disclaimer This presentation contains certain forward-looking statements and forecasts, including possible or assumed reserves and resources, production levels and rates, costs, prices, future performance or potential growth of Alkane Resources Ltd, industry growth or other trend projections. Such s

  4. Slide 4: FY22 Highlights

    FY22 Highlights For personal use only Exceeded production guidance at Tomingley Initial Boda Resource is over 10 million equivalent ounces Roswell Resource increased 37% and with San Antonio now stands at 1.31 million ounces Tomingley Life of Mine Plan extends beyond 2030 Competitive AISC below A$1,

  5. Slide 5: Strategy: Growth and Investment

    Strategy, Alkane is growing shareholder value through: Growth and • Reliable and increasing gold For personal use only production at Tomingley Investment • Proven exploration and development success • Cornerstone investments CONSISTENT MINING TRACK RECORD OF STRATEGIC DEALS TO FINANCIAL STRENGTH AND

  6. Slide 6: Tomingley Corridor: Central West NSW

    Tomingley Corridor: Central West NSW For personal use only ~10km mineralised corridor adjacent to established processing infrastructure at Tomingley Gold Operations (TGO) ALKANE RESOURCES | ASX:ALK 5

  7. Slide 7: Tomingley Operation

    Tomingley Operation For personal use only • 1Mtpa processing plant operating since 2014 (permitted for 1.5Mtpa) • Exceeded FY22 production guidance with 66,804 oz at AISC <A$1,500/oz • Open cut and underground operations • Growing resource base Resource (Roswell): 14.1Mt @2.00g/t Au (904,000 oz)# •

  8. Slide 8: Operational Excellence & Resource Growth

    Operational Excellence & Resource Growth For personal use only • Tomingley has consistently met or exceeded production guidance • Since mining commenced in 2013, mineral resources have grown ahead of production • Over 900koz of resources has been added, net of mine depletion as at the end of FY21 (n

  9. Slide 9: Tomingley Extension Project

    Tomingley Extension Project For personal use only • Life Of Mine (LOM) plan shows operation to at least 2031#. • Planned production of approximately 745,000 oz for the period, with processing ramping to 1.5 mtpa. • The planned production profile (averaged for each period) is: • 50,000 – 60,000 ozpa

  10. Slide 10: Boda Prospect

    Boda Prospect For personal use only • Initial Boda Resource released* *ASX Release 30 May 2022 ALKANE RESOURCES | ASX:ALK 9

  11. Slide 11: North Molong Porphyry Project Drilling Program

    North Molong Porphyry Project Drilling Program For personal use only • Kaiser surface RC program, view to create resource • At depth in Boda Two and Three, shaped by interpretation • At depth in Korridor • Early stage work at Konigin and Murga ALKANE RESOURCES | ASX:ALK 10

  12. Slide 12: Converting opportunities into shareholder value

    Converting opportunities For personal use only into shareholder value Alkane owns ~9.7% of Calidus Resources, which is • Board and management experience across the has completed commissioning and ramping to be a full mining life-cycle allows prudent assessment 100,000oz+ p.a. producer in Western Aus

  13. Slide 13: Corporate Profile

    Corporate Profile Ian Gandel (Non-Executive Chairman) For personal use only Capital Structure Mr Gandel is a successful Melbourne based businessman with extensive experience in retail management and retail property. Through his private investment vehicles Mr Gandel has Ordinary Shares 596 million be

  14. Slide 14: Key Priorities for FY23

    Key Priorities for FY23 For personal use only Test high grade extensions, near surface resources and repeat structures at Boda and nearby porphyry targets Early stage exploration across greater Boda region (North Molong Porphyry Project) Initial Kaiser Resource Tomingley Corridor Exploration Drive (

  15. Slide 15: For personal use only

    For personal use only www.alkane.com.au @alkaneresources alkane-resources-ltd

  16. Slide 16: Mineral Resources

    Mineral Resources For personal use only TOMINGLEY GOLD PROJECT SAR MINERAL RESOURCES (as at 4 May 2022) MEASURED INDICATED INFERRED TOTAL Total Gold DEPOSIT Tonnage Grade Tonnage Grade Tonnage Grade Tonnage Grade (Kt) (g/t Au) (Kt) (g/t Au) (Kt) (g/t Au) (Kt) (g/t Au) (Koz) Total Resources (cut off

  17. Slide 17: Ore Reserves

    Ore Reserves TOMINGLEY GOLD OPERATION ORE RESERVES(as at 30 June 2021) For personal use only PROVED PROBABLE TOTAL Total Gold DEPOSIT Tonnage Grade Tonnage Grade Tonnage Grade (Kt) (g/t Au) (Kt) (g/t Au) (Kt) (g/t Au) (Koz) Open Pittable Reserves (cut off 0.40g/t Au) Wyoming One 0 0.0 0 0.0 0 0.0 0