Boliden AB · OMXSTO:BOL
Boliden AB — Investor Day (November 2013)
20 slides from Boliden AB's investor day presentation, Nov 21, 2013
Slide 1: Smelters update
Smelters update CMD 21 November 2013 Kerstin Konradsson President Boliden Smelters
Slide 2: Smelters Financial development
Smelters Financial development R4Q, MSEK EBIT ex PIR YTD Q3 530 (892) Quarterly EBIT excl PIR* MSEK MSEK R lli Q EBIT excll PIR*, Rolling PIR* RHS 900 1 800 Major maintenance stops in 2013 Otherwise stable quarterly Maintenance earnings g since 2011 700 1 400 Lower metal prices Positive TC
Slide 3: Gross profit development
Gross profit development 8 000 7 000 9% 9% 11% 7% 8% 4% 6% 9% 6 000 2% 9% 11% 11% 12% 11% 11% 5 000 4 000 MSEK 30% 32% 33% 35% 36% M 3 000 2 000 1 000 49% 44% 36% 36% 39% 0 2009 2010 2011 2012 2013 Q3-4Q TC/RC Free Metal Premium Sulphuric acid Other by‐products Boliden CMD 2013 3 2013-11-21
Slide 4: Strategic priorities
Strategic priorities Improve safety, environmental & CSR performance f Secure optimal raw material supply Broaden customer & product portfolio Increase and diversify metals output Improve operational efficiency & cost position Reduce Capital Employed Boliden CMD 2013 4 2013-11-21
Slide 5: Copper Production – Q3
Copper Production – Q3 Rönnskär – production stability issues Total feed, Copper Cathode kt production production, Harjavalta – ok kt 400 100 Maintenance stops in Q2 350 ‒ Rönnskär at plan; Production problems 80 300 at start-up ‒ Harjavalta 1 week delayed 250 60 200 150 40 100 20 50 0 0 Q3 Q4
Slide 6: Rönnskär - Challenge
Rönnskär - Challenge Copper, pp , lead and secondary y smelter Production instability Background: ‒ Lower grade in concentrates ‒ Quality e-materials ‒ Changed raw material mix Consequences: ‒ Lower recovery ‒ High intermediate stocks ‒ Low free metals ‒ High costs Low EBIT from by-products En
Slide 7: Rönnskär - Actions
Rönnskär - Actions Copper, pp , lead and secondary y smelter Focus areas ‒ Production stability ‒ Reduce intermediate stocks ‒ Reduce costs Actions ‒ Raw material selection ‒ Process control – steering and models ‒ Adapt processes towards more complex material mixes and low-grade concentrates
Slide 8: Harjavalta
Harjavalta Copper pp and nickel smelter Current situation ‒ Costs under control ‒ Copper - intermediate stocks back on target ‒ High free metals ‒ Ni k l - stable Nickel t bl Focus areas ‒ OEE ((Overall Equipment q p Effectiveness)) ‒ Costs Q4 ‒ Cable fire fire, EBIT impact ~4MEUR 4MEUR Bolide
Slide 9: Bergsöe
Bergsöe Current situation ‒ Tight supply of batteries ‒ Significant raw material price increases ‒ Improved productivity ‒ 3-4% volume increase ‒ Stable cost level Focus areas ‒ New sourcing g markets ‒ Continue operational improvements ‒ Environmental permitting process appealed Boliden CMD 201
Slide 10: Zinc Production – Q3
Zinc Production – Q3 Kokkola – stable production Total feed, Zinc Metal production, production Odda - only 3 Direct Leach-reactors kt kt 250 140 Maintenance stops in Q2 120 ‒ On plan 200 100 150 80 60 100 40 50 20 0 0 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2011 2012 2013 Zinc feed, total Zinc
Slide 11: Odda
Odda Current situation ‒ Respacing of tankhouse no 5, closure of tankhouse no 4 ‒ 17% cost reduction/ton zinc since 2010 ‒ Reduced production due to DL-reactor ‒ DL-reactor replaced begin 2014 Boliden CMD 2013 11 2013-11-21
Slide 12: Increased productivity in cell house
Increased productivity in cell house Respacing New transformer Boliden CMD 2013 12 2013-11-21
Slide 13: P100 Odda improvement programme continues
P100 Odda improvement programme continues Focus areas ‒ Cost reductions ‒ De-bottlenecking 2009 2013 3rd 4th Boliden CMD 2013 13 2013-11-21
Slide 14: Kokkola
Kokkola Current situation ‒ Continued stable production ‒ Managing calcine stock ‒ High costs due to oxygen Focus areas ‒ Silver recovery ‒ Quality of sulphuric acid Boliden CMD 2013 14 2013-11-21
Slide 15: Silver recovery
Silver recovery Background ‒ Increasing silver content in zinc concentrates ‒ High silver prices Investment ‒ Investment 27 MEUR ‒ Production Q3 2014 ‒ Production of 25 t silver ‒ Silver concentrate, <10 000 g/ton, with small amounts of gold and lead ‒ Further refinement to silver elsewhere ‒ Hi
Slide 16: Silver recovery November 2013
Silver recovery November 2013 Boliden CMD 2013 16 2013-11-21
Slide 17: Pricing model
Pricing model Income streams - pricing of zinc concentrate t t ‒ Metal value from recovery of silver*, gold and lead from zinc concentrate Deductions - pricing of silver concentrate ‒ Silver (5%), Gold (5%) and lead (3units) ‒ Treatment Charge and Silver & Gold Refining Charges • Minimum deducti
Slide 18: Maintenance 2014
Maintenance 2014 Maintenance stops ‒ Maintenance stops in all units Q2 or Q3 ‒ Ni-line in Harjavalta EBIT effect -220 MSEK ‒ -140 MSEK in Q2 ‒ -80 MSEK in Q3 Boliden CMD 2013 18 2013-11-21
Slide 19: Disclaimer
Disclaimer This presentation has been prepared by Boliden for information purposes only. Nothing in this material shall be construed as an offer or solicitation to buy y or sell any y securityy or p product,, or to engage in or refrain from engaging in any transaction. This presentation has been
Slide 20: Boliden CMD 2013
Boliden CMD 2013 20 2013-11-21