Northland Power Inc. · TSX:NPI

Northland Power — Corporate Update (September 2020)

27 slides from Northland Power's corporate update, Sep 16, 2020

  1. Slide 1: High Bridge Wind Project Virtual Public Information Meeting

    High Bridge Wind Project Virtual Public Information Meeting September 16, 2020 1

  2. Slide 2: Welcome! Technological Housekeeping

    Welcome! Technological Housekeeping • Technical assistance handout available in GoToWebinar access panel. • Presentation will be approximately two hours and will be recorded. • We will break to address questions in the middle of the presentation and at the end of the presentation. • To post a questi

  3. Slide 3: Presentation Agenda

    Presentation Agenda 1. Background 2. Introductions • Northland Development Team • Supporting Partners 3. Overview of Northland Power 4. Initial Questions 5. Article 10 Process • Overview • Application Supplement o Address comments from NYSDPS o Compliance with local laws o Facility design updates •

  4. Slide 4: Background

    Background • High Bridge Wind has held multiple public information sessions to keep the Town of Guilford and local residents updated on the project over the last few years. o July 2019 presentation, just prior to the filing of the Application. o High Bridge Wind also held a public open house at its

  5. Slide 5: Introductions: Northland Development Team

    Introductions Northland Development Team Chris Stanton Michelle Chislett Paul Kaminski Jeffrey Nemeth Project Manager, Managing Director, General Manager, Director, Development, Northland Power, Inc. Northland Power, Inc. Construction, Americas Northland Power, Inc. Northland Power, Inc. Virtual Pub

  6. Slide 6: Introductions: Supporting Partners

    Introductions Supporting Partners James Muscato Laura Darling Erin Szalkowski Partner, Associate, Principal, Young Sommer, LLC Young Sommer, LLC Innovant Public Relations, LLC Greg Liberman Daniel Zvirzdin Erica Tauzer Associate Principal, Senior Environmental Analyst, Project Manager, EDR EDR EDR V

  7. Slide 7: Northland Today

    NORTHLAND TODAY The evolution of Northland Power • Global developer, owner and operator of sustainable infrastructure assets • Market Capitalization of approx. CAD$7.7BB; Enterprise Value of approx. CAD$14BB • Over 30 years of successfully developing, constructing and operating power projects over f

  8. Slide 8: Global Reach

    Global Reach Multiple development opportunities across countries and across technologies NORTH AMERICA Mature markets for renewables and thermal Opportunity for bulk storage EUROPE Significant offshore wind presence with three projects Further potential for additional offshore development opportunit

  9. Slide 9: Diversified Asset Portfolio

    Diversified Asset Portfolio North America Europe Asia South America EBSA - Regulated Early stage Utility development in Japan and S. Korea South Korea Japan Taiwan Hai Long In La Lucha In Advanced Construction Development Technology: Operating Under Construction & Development Offshore Wind 1,184 MW

  10. Slide 10: Initial Questions?

    Initial Questions? Project website: NorthlandPower.com >> What we do >> Development Projects >> Wind >> High Bridge Wind Project email: HighBridgeWind@NorthlandPower.com Project Facebook page: High Bridge Wind Project Office address: 125 Marble Road in Guilford Office phone number: (607) 226-9004 To

  11. Slide 11: Article 10 Process: Application Timeline

    Article 10 Process Application Timeline Milestone Date Public Involvement Program (PIP) Plan April 27, 2018 Preliminary Scoping Statement (PSS) January 24, 2019 Application August 12, 2019 Deficiency Letter from NYS Siting Board October 11, 2019 Application Supplement January 17, 2020 Application de

  12. Slide 12: Article 10 Process: Application and Supplement Materials

    Article 10 Process Application and Supplement Materials • Paper copies – available at local repositories o Guilford Town Hall o Guernsey Memorial Library o Oxford Memorial Library o Gilbertsville Free Library • Electronic copies – available online • Department of Public Services Document and Matter

  13. Slide 13: Article 10 Process: Application Supplement

    Article 10 Process Application Supplement The layout of the Facility, the Application, and supporting Appendices and Figures were updated to: • Address comments from the NYSDPS; • Ensure compliance with Town of Guildford’s Local Law No. 3 of the year 2019, entitled “Renewable Energy Systems Local La

  14. Slide 14: Article 10 Process: Application Supplement

    Article 10 Process Application Supplement 1. Addressed NYSDPS Comments on the Application • Only 17 comments were received. • Comments generally requested that High Bridge Wind provide supplemental data, information, or clarification needed for NYSDPS and other State agencies to complete their analy

  15. Slide 15: Article 10 Process: Application Supplement

    Article 10 Process Application Supplement *See Figure 1 of the Application Supplement for a more detailed layout comparison map. Virtual Public Information Meeting highbridgewind@northlandpower.com September 16, 2020 (607) 226-9004 15

  16. Slide 16: Facility Design Updates: Turbines

    Article 10 Process Application Supplement - Facility Design Updates Turbines – 18 turbines were shifted Turbine Shift (feet) Direction Reason T101 268 West Wetland impact avoidance T104 255 Northwest Compliance with local law T105 34 Northwest Compliance with local law T106 47 West Compliance with l

  17. Slide 17: Facility Design Updates: Turbine Setback Requirements

    Article 10 Process Application Supplement - Facility Design Updates Turbine Setback Requirements – The most conservative setbacks (highlighted) will be followed. Setback Feature Applicant Town of Guilford Manufacturer Drinking Water Well 100 feet 100 feet None Gas Well None None None Natural Gas Pip

  18. Slide 18: Facility Design Updates: Access Roads and Collection Lines

    Article 10 Process Application Supplement - Facility Design Updates Access Roads – Total length increased by 1 mile • Reduced Impacts to wetlands • Limited work on steep slopes • Minimized Grading • Optimized turbine delivery routes Collection Lines – Corridor length reduced by 1 mile • Installation

  19. Slide 19: Updated Design Drawings

    Article 10 Process Application Supplement To Support These Facility Design Updates: Updated Design Drawings • Updated drawings show compliance with the local law and provide other details requested by the agencies and Town. Perpendicular crossing of perennial stream minimizes impacts, while careful

  20. Slide 20: Revised Sound Modelling

    Article 10 Process Application Supplement To Support These Facility Design Updates: Revised Sound Modelling • The Final Facility design will meet all noise standards required by the State and the Town. Throughout the final design process, the layout will be optimized with consideration to these stan

  21. Slide 21: Revised Shadow Flicker Modelling

    Article 10 Process Application Supplement To Support These Facility Design Updates: Revised Shadow Flicker Modelling • Preliminary shadow flicker modeling indicates shadow flicker could potentially exceed the design goal of 30 hours per year at 9 non- participating residences. o This modeling is pre

  22. Slide 22: Updated Wetland and Stream Impact Drawings

    Article 10 Process Application Supplement To Support These Facility Design Updates: Updated Wetland and Stream Impact Drawings • The updated Facility design has reduced wetland impacts by 43% and stream 1 impacts by 35%. Steep Slopes Analysis • To address concerns raised by the agencies and the Town

  23. Slide 23: Updated Visual Impact Analysis

    Article 10 Process Application Supplement To Support These Facility Design Updates: Updated Visual Impact Analysis • Facility design updates are generally minor from a visual standpoint and would not affect the conclusions reached in the Visual Impact Assessment included in the Application. Viewpoin

  24. Slide 24: Revised Exhibit 31 (Local Laws)

    Article 10 Process Application Supplement To Support These Facility Design Updates: Revised Exhibit 31 (Local Laws) • Exhibit 31 was fully updated to provide a comprehensive assessment of the Facility’s compliance with recently adopted local laws. ☑ Wind Turbine and Ancillary Facility (e.g., substat

  25. Slide 25: Current Status (Adjudicatory Phase)

    Article 10 Process Current Status (Adjudicatory Phase) 1. Issues • Parties (i.e., State agencies, the Town of Guilford, and other groups with a stake in the Project) filed Issues Statements on April 24, 2020 • These statements identified the primary issues that the parties were seeking to resolve wi

  26. Slide 26: A10 Process Next Steps

    A10 Process Next Steps 1. Briefing Period 2. Recommended Decision • Issued by the Administrative Law Judges (ALJs) that preside over this case. • Anticipated November 2020. 3. Certificate Order • Issued by the New York State Board on Electric Generation Siting and the Environment (Siting Board) • Wi

  27. Slide 27: Question and Answer Session

    Question and Answer Session Project website: NorthlandPower.com >> What we do >> Development Projects >> Wind >> High Bridge Wind Project email: HighBridgeWind@NorthlandPower.com Project Facebook page: High Bridge Wind Project Office address: 125 Marble Road in Guilford Office phone number: (607) 22

Northland Power — Corporate Update (September 2020) on 6ix