Boral — Corporate Update (November 2017)
25 slides from Boral's corporate update, Nov 15, 2017
Slide 1: Boral Quarries Teven: Community Consultative Committee meeting
Build something great™ BORAL QUARRIES TEVEN > Community Consultative 15 November 2017 Committee meeting Teven Quarry offices, Teven
Slide 2: Agenda
Agenda ˃ Welcome, administration and ‘safety moment’ ˃ Quarry operations update ˃ Environmental management and performance ˃ Planning consent modification – one year on… ˃ Community participation and general business
Slide 3: Welcome, administration and 'safety moment'
Welcome, administration and ‘safety moment’ ˃ Welcome and re-introductions ˃ Previous meetings – 2017 Whole of Community Meeting ˃ 8 June 2017 ˃ Presentations and meeting notes from previous meetings are available from the quarry’s website – www.boral.com.au/tevenquarry ˃ Any matters arising? ˃ Apol
Slide 4: Quarry operations update
Build something great™ BORAL TEVEN QUARRY > Quarry operations update
Slide 5: Current and future projects
Current and future projects ˃ Pacific Highway upgrades ˃ Woolgoolga to Ballina ˃ Construction of the new Harwood Bridge ˃ Construction of Ferngrove residential estate ˃ Local projects ˃ Internal supply to Boral Concrete plants ˃ Internal supply to Boral Asphalt plants ˃ Local civil construction comp
Slide 6: Zero/One/Ten Award
Zero/One/Ten Award AFTER HOURS CONTACT. PH: 0401 894 493 ==
Slide 7: IQA Innovation Awards 2017
IQA Innovation Awards 2017
Slide 8: Slide 8
Slide 9: Environmental management and performance
Build something great™ BORAL TEVEN QUARRY > Environmental management and performance
Slide 10: Boral
BORAL.
Slide 11: Slide 11
Slide 12: Environmental monitoring
Environmental monitoring Averaging Period g/m2/montha Deposited Dustb Annual 4.00 a – Maximum total deposited dust level b – Dust is assessed as insoluble solids as defined by AS3580.10.1-1991 (AM-19) (At the nearest existing or likely future off-site sensitive receptor) Source: Table 7.1 (Page 28)
Slide 13: Environmental monitoring
Environmental monitoring Annual Average Dust Deposition (Insoluble Solids) 0.30 g / m2 / month
Slide 14: Environmental monitoring
Environmental monitoring Annual Average Dust Deposition (Insoluble Solids) 0.53 g / m2 / month
Slide 15: Environmental monitoring
Environmental monitoring Annual Average Dust Deposition (Insoluble Solids) 1.80 g / m2 / month
Slide 16: Environmental monitoring
Environmental monitoring Annual Average Dust Deposition (Insoluble Solids) 0.39 g / m2 / month
Slide 17: Environmental monitoring: PM10 monitoring
BORAL. Environmental monitoring PM10 Monitoring: Teven Quarry 40.00 mmm 24 Hour Sample Sample Annual Average-Progressive ~~ Maximum Concentration Standard 24-hr (50ug/m3) —— Maximum Concentration Standard Annual Average (25yg/m3) is SS os os sy sy 3 py N e 3 @) 9 AY AY AY Ay ve Ay we AY ay > Vv » oy
Slide 18: Water quality limits for Boral Teven Quarry from EPA Licence
Water quality limits for Boral Teven Quarry from EPA Licence No 2261 * On the 14/6/17 - 235mm of rainfall was recorded in previous 5 consecutive days. As per condition L1.3 of EPL2216, discharge of runoff exceeding the quality limits in L2.4 to waters from the premises is permitted when the discharg
Slide 19: Blast overpressure and vibration results
Date Time Overpressure [dB] Peak Vibration [mm/s] Tuesday, 8 September 2015 11:48:58 109.9 2.0 Tuesday, 22 September 2015 13:20:50 114.4 1.5 Thursday, 1 October 2015 13:03:07 106.0 2.1 Friday, 16 October 2015 13:32:00 107.0 2.1 Boral Teven Quarry Blast Limits Friday, 23 October 2015 13:15:24 110.6 0
Slide 20: Planning consent modification – one year on
Build something great™ BORAL TEVEN QUARRY > Planning consent modification – one year on…
Slide 21: Consent modification – one year on
Consent modification – one year on… ˃ Almost 12 months has passed since Council approved the consent modification. ˃ Operating hours for processing have been firmly implemented: ˃ Monday to Friday – 7am to 6pm ˃ Saturday - None ˃ Mobile crushing has been conducted for 31 working days. ˃ Of the addit
Slide 22: Community participation and general business
Build something great™ BORAL TEVEN QUARRY > Community participation and general business
Slide 23: Community participation
Community participation ˃ The Boral Teven Quarry has this year supported or been involved with: ˃ Boral’s corporate environmental partners, Conservation Volunteers Australia, spent three days working at the Southern Cross School, Ballina. ˃ Ballina Lions Club’s World Festival of Magic Children’s Chr
Slide 24: General business and contacts
General business and contacts ˃ Items of general business ˃ Next meeting of the Community Consultative Committee ˃ Next meeting will be arranged for the first half of 2018. ˃ Boral Teven Quarry contacts: ˃ Scott Gillieatt Quarry Manager 6687 8360 / scott.gillieatt@boral.com.au ˃ Paul Jackson Stakeho
Slide 25: Thank you for your attendance
Build something great™ BORAL TEVEN QUARRY > Thank you for your attendance