Metals Exploration Plc · LSE:MTL
Metals Exploration — Shareholder Meeting (June 2015)
14 slides from Metals Exploration's shareholder meeting presentation, Jun 30, 2015
Slide 1: Annual General Meeting – Presentation – 30 June 2015
Annual General Meeting – Presentation – 30 June 2015
Slide 2: Important Notice
IMPORTANT NOTICE This presentation has been prepared by the management of Metals Exploration Plc for the benefit of the investing community including, brokers, fund managers, investors and analysts and not for the benefit of any particular person. It should be read in conjunction with information pr
Slide 3: Philippine Focussed – Near Producer
PHILIPPINE FOCCUSSED – NEAR PRODUCER KEY SHAREHOLDERS - % HOLDING (28 April 2015) MTL Luxembourg 49.15% SHARE CAPITAL (28 June 2015) Runruno Holdings 18.98% Issued ordinary shares 1,374,972,024 Ruffer 13.33% Unlisted options 7,235,000 Baker Steel 9.80% Market Capitalisation (28 April)
Slide 4: Runruno Gold Project – Poised for Production
RUNRUNO GOLD PROJECT – POISED FOR PRODUCTION 100% owned Runruno Gold Project - commissioning underway Staged commissioning of the process plant commenced Strong major shareholder support - MTL (Luxembourg) s.a.r.l, Runruno Holdings, Baker Steel, CF Ruffer, Investec Runruno 100% owned - Finan
Slide 5: Year 2014 Highlights
Year 2014 HIGHLIGHTS Finalised debt facility with HSBC and BNP – Paribas Construction and mine development continued throughout the year Undertook a major restructure of the Group, requirement of the debt facility security package Special tree cutting permit issued – construction of RSI comm
Slide 6: Process Plant – Construction and Commissioning
PROCESS PLANT – CONSTRUCTION and COMMISSIONING Process plant construction at 93% complete Switchyard complete, commissioned and in operations Advanced pre-commissioning Commenced staged commissioning with the crusher, transfer station and conveyor areas, followed by: Flotation, 7 July Mi
Slide 7: Site Video
Runruno Processing Plant, —
Slide 8: Operational Management
OPERATIONAL MANAGEMENT Operational management substantially in place General Manager Runruno Operations – Peter Storey General Manager Maintenance – Kevin Oxenham Technical Services Superintendent – Michael James Mine Production / Training Superintendent – Colin Smith Senior Mine Geologi
Slide 9: Corporate Social Responsibility
CORPORATE SOCIAL RESPONSIBILITY Education & Training Scholarships and assistance Adopt a school programme Out of work youth skills training programmes Teachers salaries Mature age learning programs Health & Nutrition Education Provision of a professionally staffed clinic including doctor and
Slide 10: Corporate Social Responsibility
CORPORATE SOCIAL RESPONSIBILITY Environment Protection and Enhancement Environmental monitoring Slope stabilisation and rehabilitation of disturbed areas Forest regeneration Multiple award winner Communication Information and Education To shape desirable social opinion about the compan
Slide 11: Runruno Gold Project
RUNRUNO GOLD PROJECT Status: - commissioning - 93% complete - Commenced Commissioning - Production ramp-up – Q3/Q4 2015 Initial Mine life: 10.3 years Payable Production: 1,006,000 ozs Annual Production (aver.): 96,700 ozs (101,800 ozs Au years 1-5, 92,700 ozs Au years 6-10.3) • Runruno Cash Cost (Av
Slide 12: Regional Location
REGIONAL LOCATION Airfield – Bagabag airfield 10 kms north of Solano Road – upgraded – largely concrete. Power supply – switch yard in Bayombong will be the origin for the new 69Kv line to site, running along 5 km the new road • Runruno Project 12
Slide 13: Project Description
PROJECT DESCRIPTION Five key components: Mine Open Pit and Run of Mine (ROM) Pad Process Plant facility consisting of conventional crushing, grinding, flotation, along with BIOX® and gravity recovery Tailings Storage Facility (TSF): to ensure materials are properly managed and to reclaim water
Slide 14: Resources and Reserves March 2011 & April 2013
RESOURCES AND RESERVES March 2011 & April 2013 Runruno Main Ore Gold Molybdenum Reserve Category Mt g/t M Oz ppm M lbs Proven 10.2 1.90 0.62 616 13.9 Probable 4.8 1.77 0.27 414 4.4 2P Reserves 15.0 1.85 0.90 603 18.3 Additional Inferred 2.9 1.73 0.16 258 1.7 Resource in-pit Ore Gold Molybdenum Resou