Whitehaven Coal Limited · ASX:WHC

Whitehaven Coal — Shareholder Meeting (October 2014)

34 slides from Whitehaven Coal's shareholder meeting presentation, Oct 28, 2014

  1. Slide 1: ASX cover letter for AGM documents

    28 OCTOBER 2014 The Manager, Listings Australian Securities Exchange Company Announcements Office Dear Sir, Via ASX Online We attach copies of the Chairman’s Address and Managing Director’s Presentation which will be delivered at the Company’s Annual General Meeting being held at 10:00am today. Your

  2. Slide 2: Whitehaven Coal 2014 AGM – Chairman's Address

    28 OCTOBER 2014 WHITEHAVEN COAL 2014 AGM – CHAIRMAN’S ADDRESS It has been a challenging year for Whitehaven – and the coal industry in general. The environment for coal companies has been tough with coal prices for all coal types declining during the year while the Australian dollar remained strong

  3. Slide 3: Chairman's Address continued: social licence to operate

    28 OCTOBER 2014 are responding to the environmental challenge and requiring their industries source higher-energy, higher- quality coal. This plays to the strengths of the Australian industry generally, and Whitehaven in particular. Whitehaven already produces a high-quality thermal product with low

  4. Slide 4: Chairman's Address continued: cost reductions and financial performance

    28 OCTOBER 2014 A particularly pleasing aspect of FY2014 has been the discipline with which management has reduced expenses, driven efficiencies and extracted the benefits of scale. Measures have included renegotiating rail and port charges on more favourable terms, centralising administrative funct

  5. Slide 5: Chairman's Address closing and contacts

    28 OCTOBER 2014 As a 23Mtpa producer, with pre-approvals in place at Vickery to expand to an additional 5Mtpa if required, Whitehaven is ideally placed to participate in this growth. Ladies and gentlemen, we are grateful for the role local communities have played in Whitehaven’s success to date and

  6. Slide 6: Whitehaven Coal Limited AGM 2014

    Whitehaven Coal Limited AGM 2014 A year of delivering on targets Sydney, Australia 28 October 2014

  7. Slide 7: Disclaimer

    Disclaimer Statements contained in this material, particularly those regarding the possible or assumed future performance, costs, dividends, returns, production levels or rates, prices, reserves, potential growth of Whitehaven Coal Limited, industry growth or other trend projections and any estimate

  8. Slide 8: Our goal: Creating Australia's premier ASX listed coal company

    Our goal Creating Australia’s premier ASX listed coal company 3

  9. Slide 9: Coal in today's world

    Coal in today’s world Coal is the power energizing the world Our energy needs in perspective: In just one day... @ wm @ Global lati will increase by 85,000+ 1,100,000 21 0 000 People will move to cities People open ’ in China and India an internet account a Te A million an metric wy 225,000 tons = 9

  10. Slide 10: Coal's growing role in global energy

    Coal’s growing role in global energy Nearly 3.5 billion people in the world have limited or no access to electricity Coal is the lowest cost source of electricity for many countries around the world World Demand for Coal (Mtce) 8000.0 BP expects world coal demand to increase by 1.5Bt from 7000.0 201

  11. Slide 11: The case of India

    The case of India In India more than 700 million people lack access to modern power for lighting, cooking, water pumping and other productive purposes Sources of electricity by 2030 in India • Wind & Solar 8% • Nuclear, Hydro & Biomass 29% • Coal 63% The cost of solar electricity is estimated to be

  12. Slide 12: Improving technology

    Improving technology New technology is reducing carbon emissions from coal fired plants 7

  13. Slide 13: CCS is "commercial"

    CCS is “commercial” SaskPower, a large Canadian power generation company has just brought online the world’s first commercial CCS facility in Canada The plant will capture 100% of SO2 and 90% of CO2 emissions and provide power for 100,000 homes CCS can deliver a future for coal fired power stations

  14. Slide 14: Australian political support

    Australian political support The Hon Tony Abbott, the Prime Minister of Australia “Energy is what sustains prosperity and coal is the world’s principle energy source and it will be for many decades to come” and “Coal is good for humanity, coal is good for prosperity, coal is an essential part of our

  15. Slide 15: Where we operate

    Where we operate Maules Creek (75%) • Reserves to support ~ 30 years • Permitted & Planned : 13 Mtpa ROM • SSCC, PCI and high energy thermal Narrabri North (70%) • Reserves to support ~ 25 years • Permitted : 8 Mtpa ROM • Planned : 6 Mtpa ROM • PCI & low ash thermal coals Tarrawonga (70%) • Reserves

  16. Slide 16: Community contribution

    Community contribution Whitehaven currently employs over 655 people with 74% living in the region around its operating mines Wages paid to employees in the region were over $80 million in FY2014 and will increase in FY2015 First phase recruitment for Maules Creek has been completed with over 1,800 a

  17. Slide 17: Aboriginal engagement

    Aboriginal engagement Whitehaven has developed an Aboriginal Engagement Strategy to build on and enhance relationships with the Aboriginal community in which it operates During FY2014 Whitehaven employed a dedicated Aboriginal Community Relations Officer At the Maules Creek project the company worke

  18. Slide 18: Delivering on targets

    Delivering on targets TARGETS FY2014 OUTCOME Improve safety performance at all operations Lowest group TRIFR rate in 5 years Ensure current operations are performing to Record production at three mines plan Reduce costs Fully absorbed costs declined by 9% for the year Overcome quality issues in Narr

  19. Slide 19: Safety performance

    Safety performance Introduction of Whitehaven’s “Safehaven Rules” during the year is delivering improved safety performance as evidenced by a 30% decline in the TRIFR and a 40% reduction in the LTIFR from the previous year Achieved lowest group wide TRIFR rate for 5 years of 14.06 below the NSW aver

  20. Slide 20: Financial highlights for FY2014

    Financial highlights for FY2014 Headlines FY2014 FY2013 Comment EBITDA before significant 90.4 17.1  Significant improvement from previous year items ($’m)  Increase in line with EBITDA growth and reduced coal Operating cash flow ($’m) 108.6 (32.3) purchases Average unit cost per tonne  Significa

  21. Slide 21: Costs are falling

    Costs are falling H2 H1 FY2014 FY2014 (1) FY2014 FY2013 (1) (2) Average revenue per tonne was flat with coal price reduction offset by weakening in the A$ Coal Sales (equity basis, excl. purchased '000t 3,913 4,302 8,215 5,994 (3) coal) Average revenue (excl. purchased coal & net $A/t 77 81 79 79 (3

  22. Slide 22: Sales destination – premium markets

    Sales destination – premium markets Thermal Coal Sales 2014 Japan and Korea are key markets for Whitehaven coal 8% 8% Thermal coal sales in FY2014 were 8.9Mt (100% basis) Japan including purchased coal with most sold into the premium 47% Korea Asian markets China 37% Other Metallurgical coal sales t

  23. Slide 23: Record saleable coal production

    Record saleable coal production Excellent performance at Narrabri increased Whitehaven’s managed production by 26% to 10.3Mt for the year The open cut mines also performed strongly as Werris Creek and Tarrawonga set new records Whitehaven Managed Coal Production (000's t) 12,000 10,000 8,000 6,000 4

  24. Slide 24: Narrabri performing strongly

    Narrabri performing strongly Tier 1 World Class Mine Narrabri Saleable Coal Production (000's t) 6,000 Record ROM and saleable coal production of 5.7Mt and 5.2Mt respectively for FY2014 5,000 Productivity of about 17,000tpmpy (ROM basis) achieved in FY2014 placing the mine amongst 4,000 the most pro

  25. Slide 25: Narrabri beyond FY2015

    Narrabri beyond FY2015 Top Coal Caving assessment has been completed and is inferior to the introduction of a wider longwall panel face Increased panel lengths will lead to less changeouts in the future, usually only one in each year Wider panel face (400 metres) - Increases annual productivity of m

  26. Slide 26: Maules Creek construction 75% complete

    Maules Creek construction 75% complete All major elements of the Tier 1 world class mine either ahead or on schedule % Complete at 24 Oct 14 Area Contractor Rail Leighton 82% Bulk Earthworks Ditchfield 72% CHPP Design, Supply Sedgman 100% CHPP Erect Downer 48% Water Supply Stripes 100% Power Supply

  27. Slide 27: Project "S" curve

    Project “S” curve Whitehaven expects to have spent about $610 million at the time of the first coal shipments from Maules Creek Revenue will begin for coal sales from January 2015, several months before construction activity is completed Commissioning of the remaining mine infrastructure will contin

  28. Slide 28: Maules Creek mining

    Maules Creek mining Whitehaven will owner operate the Mining mine with first phase of staff and Model operator recruitment completed, mining commenced Low cost funding secured for new ultra class mining equipment via an Funding & operating lease. Mining equipment Equipment sufficient for an operatin

  29. Slide 29: Maules Creek – Mine infrastructure

    Maules Creek – Mine infrastructure 24

  30. Slide 30: Maules Creek – Mine infrastructure

    Maules Creek – Mine infrastructure Train loadout bin and stockyard Sleepers and rail line ready for laying 25

  31. Slide 31: Vickery approval

    Vickery approval Approval granted by NSW Government in September Vickery Project Key Elements Details Location About 25kms north of Gunnedah Resources and Reserves Reserves of 204Mt contained within a Resource of 508Mt Whitehaven 100%. Will consider the formation of a Joint Venture by Ownership sell

  32. Slide 32: Investment proposition – low cost growth

    Investment proposition – low cost growth Saleable Coal Production by Mine (Mt) Production is expected to more than 25.0 double by FY2018 as Maules Creek 125% Growth ramps up to its full capacity 20.0 Saleable production in FY2015 is 15.0 expected to be about 14Mt on a 110% Growth 100% basis (include

  33. Slide 33: Targets for FY2015

    Targets for FY2015 Aiming for ongoing improvement in safety performance at all operations Ensuring construction of Maules Creek remains ahead of schedule and under budget Developing long term markets and sales contracts for all Maules Creek production Recruiting and training the workforce to operate

  34. Slide 34: Thank you

    Thank you www.whitehavencoal.com.au

Whitehaven Coal — Shareholder Meeting (October 2014) on 6ix