Northern Minerals Limited · ASX:NTU

Northern Minerals — RIU Explorers Conference 2018

36 slides from Northern Minerals's conference presentation, Feb 21, 2018

  1. Slide 1: Delivering critical technology metals to the EV evolution

    Delivering critical technology metals to the For personal use only EV evolution On track for mid-year project completion February 2018

  2. Slide 2: Disclaimer

    Disclaimer For personal use only This presentation has been prepared by Northern Minerals Limited (“Northern Minerals” or the “Company”). It should not be considered as an offer or invitation to subscribe for or purchase any securities in the Company or as an inducement to make an offer or invitatio

  3. Slide 3: Four stage approach to full value capture

    For personal use only Four stage approach to full value capture Stage 1 Stage 2 Stage 3 Stage 4 TEST PILOT PLANT REFINE PROJECT BUILD FULL SCALE DOWNSTREAM • 10% of full scale capacity • Reduce mining cost - • 585,000tpa operation • Downstream separation • Production – July 2018 modify mining method

  4. Slide 4: Electric Vehicles – Not just a lithium story!

    Electric Vehicles – Not just a lithium story! For personal use only Li Lithium Al Aluminium Co Cobalt Mg Magnesium Cu Copper C Graphite Ni Nickel Dysprosium Dy Fe Mn Mo V Neodymium Nd

  5. Slide 5: Dysprosium

    Dysprosium For personal use only 66 99% Dy Production from China Lighter & More Efficient 162.5 20m 100g 2,000tpa Forecast EV Dysprosium per EV demand for Government sales by 2025 electric vehicle Dy by 2025 mandated change

  6. Slide 6: Rare earth distribution comparison: Browns Range vs Lynas Mt Weld

    Northern Minerals Lynas Browns Range Mt Weld For personal use only Rare earth distribution 1 Rare earth oxide composition 2 1 Based on Wolverine Mineral Resource 2 Source: Lynas Corporation website

  7. Slide 7: Browns Range - Filling the Dysprosium supply gap

    Browns Range - Filling the Dysprosium supply gap For personal use only Browns Range More than one Browns Range required to fill the supply gap Dysprosium Production forecast Browns Range Dysprosium forecast* Forecast Dysprosium demand Source: Adamus Intelligence, Northern Minerals

  8. Slide 8: HRE – sustainable pricing

    HRE – sustainable pricing Dysprosium Oxide 99%min China US$/kg For personal use only 400 350 Increased demand from new EV sales coupled with crackdown 300 Dy US$/kg 250 200 on illegal mining in China will positively impact prices 150 Terbium Oxide 99.9%min China US$/kg 900 800 700 Tb US$/kg 600 500

  9. Slide 9: Constructing a new industry

    Constructing a new industry For personal use only Pilot Plant Site May 2017 September 2017 June 2017 December 2017

  10. Slide 10: For personal use only

    In 2017, Northern Minerals completed stacking of raw product ready for processing For personal use only In 2018, we will commence a new supply of heavy rare earths to the global market

  11. Slide 11: Enhancement projects underway

    For personal use only Enhancement projects underway Mining Processing Plant Schedule Financing 205,000t ore mined at Wolverine and Gambit West; Sales Agreement Steeper walls employed, resulting in more ore and less Community waste; Funding secured to investigate this and other project Feasibility en

  12. Slide 12: Pilot Plant Flowsheet

    For personal use only Pilot Plant Flowsheet Mining Processing Plant Schedule Financing Sales Agreement Community Components and equipment unloaded in Darwin Feasibility Project Component: Contractor: Modular processing plant Sinosteel MECC Annual Production: Capital Cost: 60,000tpa (based on 10 A$39

  13. Slide 13: Project development schedule

    Project development schedule For personal use only Mining Apr ‘17 Jun ‘17 Sep ‘17 Dec ‘17 Mar ‘18 Jun ‘18 Processing Plant Final Investment Decision Schedule Mining completed, ore stockpiled Financing Fabrication 98% Plant modules complete in China transported to Australia Sales Agreement Commenceme

  14. Slide 14: Financing

    Financing $10 million Sales Agreement For personal use only Prepayment** $24.5 million R&D Financing Facility - Mining Available $11 million Processing Plant Sinosteel Deferred $3 million Lind Financing Payment* Facility*** - available Schedule Financing $11 million Lind Financing $13.5 million Faci

  15. Slide 15: Secure sales agreement

    For personal use only Secure sales agreement Mining 100% of Browns Range Pilot Plant production to be purchased by Lianyugang Zeyu New Materials Direct shipping Processing Plant Sales Co Ltd (JFMAG), a 51% route from Wyndham or owned subsidiary of Guangdong Darwin to Schedule Rare Earths Group. Lian

  16. Slide 16: Training-to-Work Facility

    For personal use only Training-to-Work Facility Mining Processing Plant Schedule Financing Sales Agreement Community Feasibility • Northern Minerals has partnered with The Wunan Foundation for the establishment of an $8.1 million indigenous training-to-work facility at Browns Range. • The Federal Go

  17. Slide 17: Full scale feasibility

    Full scale feasibility • The three-year pilot project has been designed to assess the technical and For personal use only Mining economic feasibility of the proposed full-scale development. • Key aspects of assessment during the Pilot Plant phase: Processing Plant Mining and ore variability; Schedul

  18. Slide 18: Blue Sky potential

    Blue Sky potential The Browns Range dome is a massive For personal use only geological feature covering 1,500km2 and stretching 60km x 30km most of which hasn’t been effectively explored JORC Resource supporting an 11 year full scale operation ICEMAN Exploration target to add additional 9 years of J

  19. Slide 19: Beyond Browns Range

    For personal use only Beyond Browns Range Rock chip samples up to 42% TREO with approximately 95% Heavy REO Rock chip samples from the Boulder Ridge project confirm high-grade Heavy Rare Earths (HRE) Preliminary metallurgical tests indicate excellent recovery rates (>90%) Best results exceed 12% TRE

  20. Slide 20: Key Personnel and Partners

    Key Personnel and Partners For personal use only Key Site Personnel: Eben Van Rooyen – Resident Manager Tony Hadley – General Manager George Bauk Managing Robin Jones Director/CEO Chief Operating Officer Bin Cai Executive Officer Mark Tory Robin Wilson Chief Financial Exploration Officer Manager

  21. Slide 21: Key Highlights

    For personal use only Key Highlights

  22. Slide 22: 2018 – Delivering on potential

    2018 – Delivering on potential For personal use only

  23. Slide 23: Corporate Overview

    Corporate Overview For personal use only Northern Minerals Share Price Performance 0.16 9.00 0.14 8.00 Share Price (A$/share) 0.12 7.00 6.00 Volume (m) 0.10 5.00 0.08 4.00 0.06 3.00 0.04 2.00 0.02 1.00 0.00 0.00

  24. Slide 24: Delivering critical technology metals to the EV evolution

    For personal use only Delivering critical technology metals to the EV evolution

  25. Slide 25: Appendices

    For personal use only Appendices

  26. Slide 26: Heavy rare earths crucial to growth of electric vehicle sector

    Heavy rare earths crucial to growth of electric vehicle sector For personal use only NdDyFeB permanent magnets used by major electric vehicle (EV) manufacturers require Dysprosium and Terbium as key additives for high performance Changing policy settings by European governments and future developmen

  27. Slide 27: Browns Range – An Eight Year Journey

    Browns Range – An Eight Year Journey For personal use only

  28. Slide 28: Global EV growth drivers

    Global EV growth drivers For personal use only Battery technology Regulatory support for eliminating range technology lower emission vehicles Consumer demand EVs approaching price reaches inflection point parity with combustion vehicles

  29. Slide 29: EV acceptance reached inflection point in 2017

    EV acceptance reached inflection point in 2017 For personal use only

  30. Slide 30: Chinese carmakers to dominate EV production

    Chinese carmakers to dominate EV production For personal use only

  31. Slide 31: Mineral Resources

    Mineral Resources For personal use only 1 – Rounding may cause some computational discrepancies (TREO (metal) tonnes estimated from Mt x TREO%) Mineral resources as per NTU announcement 2 March 2015 in relation to increased reserves.

  32. Slide 32: Ore Reserves

    Ore Reserves For personal use only Ore reserves as per NTU announcement 2 March 2015 in relation to increased reserves.

  33. Slide 33: Pilot plant: targeted production

    Pilot plant: targeted production For personal use only Mixed RE carbonate (REC) produced Product specification available for REC REC samples validated by several downstream separators REC suitable for solvent extraction separation Low thorium and uranium levels First shipment planned for September q

  34. Slide 34: NTU Board

    NTU Board Colin McCavana - Non-executive Chairman (appointed 2006) For personal use only Mr McCavana has more than 35 years of management experience worldwide in the earthworks, construction and mining industries. George Bauk - Managing Director / CEO (appointed 2010) George is an experienced execut

  35. Slide 35: Executive Team

    Executive Team For personal use only 5 years 5 years 12 years 1 year 2 months Mark Tory Robin Jones Robin Wilson Eben Van Rooyen Tony Hadley Chief Financial Officer Chief Operating Officer Exploration Manager Resident Manager General Manager Mark is a Chartered Robin has more than 20 Robin has held

  36. Slide 36: The Northern Minerals SPIRIT

    For personal use only The Northern Minerals SPIRIT

Northern Minerals — RIU Explorers Conference 2018 on 6ix