Reward Minerals Ltd · ASX:RWD

Reward Minerals — Shareholder Meeting (May 2017)

15 slides from Reward Minerals's shareholder meeting presentation, May 2017

  1. Slide 1: Reward Minerals Limited AGM Presentation May 2017

    REWARD MINERALS LIMITED AGM Presentation May 2017 ASX | RWD www.rewardminerals.com

  2. Slide 2: Forward Looking Statements & Disclaimer

    FORWARD LOOKING STATEMENTS & DISCLAIMER This document includes forward-looking statements. When used in this document, the words such as “could”, “plan”, “estimate”, “expect”, “intend”, “may”, “potential”, “should”, and similar expressions are forward-looking statements. Although RWD believes that t

  3. Slide 3: LD SOP Project Status May 2017

    LD SOP PROJECT STATUS MAY 2017

  4. Slide 4: LD SOP Project – Status May 2017

    LD SOP PROJECT – STATUS MAY 2017 ► Australia’s Largest Brine SOP Deposit ► Drainable Resource Estimate - 153Mt of SOP (1) ► Resource Brine Grade Averaging 11.35kg SOP/m 3 of Brine (1) ► Shallow Drainable SOP Resource to 6 metres 7.5Mt grading 13.4kg SOP/m 3 Brine (1) ► Scoping Study Completed in 201

  5. Slide 5: LD SOP Project – Status May 2017

    LD SOP PROJECT – STATUS MAY 2017 ► Works approvals received for Pilot Ponds and Causeway on LD ► Four Pilot Ponds substantially completed plus three lined bulk evaporation ponds. ► Seepage and evaporation trials commenced – delayed by flooding of LD early 2017. 100+ Year Flooding event ► Environment

  6. Slide 6: Peer Comparison

    PEER COMPARISON Utilising CIM Brine Standard ?     Drainable SOP Resource 153 Mt 19.8 Mt 23.2 Mt ? 18.4 Mt Brine Resource SOP Grade kg/m3 11.4 13.6 8.3 8.7 8.2 Na:K (Waste: Ore Ratio) 15.2 8.9 ? 21.5 17.6 SOP Production Estimates 400 kt pa 75-300 kt pa 370 kt pa 200-400 kt pa 150-300 kt pa In-si

  7. Slide 7: Peer Comparison

    PEER COMPARISON Project from sealed road 355 km 78 km 590 km 195 km 168 km Project from gas pipeline 175 km 78 km 400 km 245 km 245 km Project by road from Port 776 or 1,371 km 700 or 862 km 2,000 km 968 km 940 km MoU in place with Port      Native Title Mining Agreement signed   (1 of 2) 

  8. Slide 8: Corporate Overview

    CORPORATE OVERVIEW Capital Structure 26 May 2017 ASX:RWD Price History (1 Year) Ordinary Shares on Issue 135.8m Options on Issue Nil Share Price $0.25 Undiluted Market Capitalisation $34.0m Cash & Equivalents1 A$5.2m Undiluted Enterprise Value A$28.8m 1. Cash includes $2.6M R&D refund due Major Shar

  9. Slide 9: LD SOP Project LD Pond and Brine Trench Layout Plans

    LD SOP PROJECT LD POND AND BRINE TRENCH LAYOUT PLANS 9

  10. Slide 10: Schematic Ponds Layout

    i } t Fawr sero pone | = 4 t , LD PROJECT Ref: PE801-00326/01 Rev. 0 Knight Piésold CONCEPT DESIGN Figure 4.1 SCHEMATIC PONDS LAYOUT

  11. Slide 11: Infiltration Trench Layout

    FIGURE 2 NOTES: ONCEPT DESIGN LD PROJECT Ref: PE801-00326/01 Rev. 0 is Figure 3.3 INFILTRATION TRENCH LAYOUT

  12. Slide 12: LD Plant and Development Site Plan

    LD PLANT AND DEVELOPMENT SITE PLAN Plant Site – Layout Plan 12

  13. Slide 13: LD Plant and Development Site Plan

    LD PLANT AND DEVELOPMENT SITE PLAN LD Project – Plant, Borefield and Access Site Plan 13

  14. Slide 14: LD 2017 Flood Event – Pilot Pond Area

    LD 2017 FLOOD EVENT – PILOT POND AREA 100+ YEAR EVENT LD Pilot Pond Site A LD Pilot Pond Site B February 2017 May 2017 14

  15. Slide 15: Competent Person Statement

    COMPETENT PERSON STATEMENT This information in this report that relates to Resource Estimation and hydrogeology is based on information compiled by Mr Robert Kinnell, a hydrogeologist and Competent Person who is a Member of The Australian Institute of Mining and Metallurgy and a Fellow of the Geolog

Reward Minerals — Shareholder Meeting (May 2017) on 6ix