Manitou BF SA · EURONEXT:MTU
Manitou BF SA — Manitou Group — Q2 2012 Earnings Presentation
10 slides from Manitou BF SA's earnings presentation, Jul 19, 2012
Slide 1: Q2'12 Revenue
Q2’12 Revenue Jean-Christophe Giroux, CEO Q2’12 Revenue | July 19, 2012 Page 1 Hervé Rochet, CFO
Slide 2: Disclaimer
Disclaimer This presentation includes only summary information and does not in any way purport to be comprehensive. None of the Company or any of its affiliates, directors, officers, advisors and employees accepts any obligation, liability , claim or remedy for any loss arising from any use of these
Slide 3: Highlights
Highlights • Q2 Revenue of €357m, +21% vs. Q2’11 & +13% seq. • H1 Revenue of €672m, +20% vs. H1’11 • Strong operational push to curb leadtimes • Backlog easing out as a result to 8,000 units • Expected softening of order intake • Dynamic adjustment of capacity & supply chain • Updated 2012 outlook p
Slide 4: Q2 revenue matrix
Q2 revenue matrix Q2’11 Revenue Q2’12 Revenue South North €m South North Am. APAM Tot. Am. APAM Tot. Eur. Eur. % tot Eur. Eur. 90 86 9 20 206 96 108 16 33 252 RTH 31% 29% 3% 7% 70% 27% 30% 4% 9% 71% 32 4 1 3 40 32 6 1 4 43 IMH 11% 1% 0% 1% 13% 9% 2% 0% 1% 12% 3 9 34 4 50 2 8 46 6 62 CE 1% 3% 11% 1%
Slide 5: Q2 2012 evolution
Q2 2012 evolution 1 year South. North. Am. APAM Total Vs. Q1’12 Europe Europe RTH +6% +25% +71% +62% +22% 8% 10% 28% 40% 14% IMH +2% +36% +14% +40% +9% 2% 5% 49% 41% 6% CE -25% -7% +35% +34% +24% 67% 25% 11% 21% 15% Total +4% +22% +42% +55% +21% 7% 11% 16% 37% 13% Contrasted Growth Q2’12 Revenue | J
Slide 6: Backlog and order intake
Backlog and order intake RTH IMH CE (nb of units) Q2 Q3 Q2 Q3 Q2 Q3 Backlog Mar. 31 5,457 1,956 2,347 + Order intake* 3,075 3,570 1,690 - Revenue 4,229 3,953 1,883 Backlog Jun. 30 4,303 1,573 2,154 Book-to-bill (months) 3.1m 1.2m 3.4m * Detail of order intake: Seasonality + - = - - - Re-stocking of
Slide 7: Backlog evolution (units)
Backlog evolution (units) 12 000 10 000 8 000 6 000 4 000 2 000 0 Q1'10 Q2'10 Q3'10 Q4'10 Q1'11 Q2'11 Q3'11 Q4'11 Q1'12 Q2'12 Order Intake Revenue Backlog Q2’12 Revenue | July 19, 2012 Page 7
Slide 8: The Festival
The Festival • 1400 guests from 80 countries • All stakeholders represented • Transparency & honesty… • … for adhesion & motivation • Also with internal impact • 99% satisfaction rate... • … with an amazing buzz A Promise for the Future Q2’12 Revenue | July 19, 2012 Page 8
Slide 9: Operational Review
Operational Review • RTH: Launch of MLT840 and TJ280 • IMH: Launch of MI CB forklift • CE: Launch of Yanmar machines • S&M: Orders forecast, marketing focus • CorpDev:Competitive watch and mapping • NewBus: Acceleration with Mining and Oil&Gas • Projects: Suppliers, supply chain, make or buy… Manito
Slide 10: Outlook
Outlook • Shifting market patterns - From long & steep macro cycles - To fluid & contrasted micro evolutions • Increasing reactivity, flexibility, adaptability - From an S&M approach - From an Operational capacity • Revised 2012 outlook - pending H1 earnings - Revenue up +10% vs +10-15% - Operating