  1. Slide 1: Bear Creek Dam Rehabilitation Project

    Bear Creek Dam Rehabilitation Project Presented by Susan Kelly July 15, 2009

  2. Slide 2: Bear Creek Dam Pre-Construction

    Bear Creek Dam Pre-Construction 2

  3. Slide 3: EIS: Preferred Alternative

    EIS: Preferred Alternative • Modify the dam and restore the 576-foot operating pool • Construct a roller-compacted concrete berm at the toe of the existing dam • Benefits: – Retains intended benefits of flood protection, water supply, recreation, and economic development – Provides protection from p

  4. Slide 4: Construction Report Update

    Construction Report Update Activity Status Site mobilization Complete Excavation Complete Dewatering system installation Complete Foundation treatment Complete Roller compacted concrete berm Complete Site restoration and demobilization Complete Project completion/return to service Complete Ribbon cu

  5. Slide 5: Slide 5

  6. Slide 6: Concrete Berm, Downstream Face

    Concrete Berm, Downstream Face 6

  7. Slide 7: Concrete Berm, Upstream Face

    Concrete Berm, Upstream Face 7

  8. Slide 8: Concrete Berm from Spillway

    Concrete Berm from Spillway 8

  9. Slide 9: Bear Creek Dam Post Construction

    Bear Creek Dam Post Construction (Rendering) 9

  10. Slide 10: Blue Ridge Dam Rehabilitation Project

    Blue Ridge Dam Rehabilitation Project Presented by Susan Kelly July 15, 2009

  11. Slide 11: Slide 11

  12. Slide 12: Background

    Background • Major components are damaged or deteriorating • Seismic concerns • Deep drawdown required to check condition every five years 12

  13. Slide 13: Scope of Work

    Scope of Work • Repair the penstock – Remove vertical reinforcing girder – Remove penstock bulge – Install a new steel liner • Seismic modifications – Reinforce the water intake tower – Install filter and replace riprap on upstream embankment – Install filter and add riprap on downstream embankment

  14. Slide 14: Proposed Drawdown

    Proposed Drawdown • Repairs will require a deep drawdown • Plans are to begin slowly drawing down the reservoir between mid-July and early September 2010 • The reservoir will be held under elevation 1630 for six to nine months • Assuming adequate rainfall, the reservoir will be refilled in late spri