Indian Oil Corp. Ltd. · NSE:IOC
Indian Oil — Corporate Update (May 2019)
55 slides from Indian Oil's corporate update, May 17, 2019

Slide 1: Annual Press Conference 2019
Annual Press Conference 2019 Indian Oil Corporation Ltd. 17th May 2019

Slide 2: Earning Trust as the Energy of India
Earning Trust as the Energy of India... Championing Clean fuels Strides in Renewable Energy Shifting to Green Economy thru Gas Keeping the energy flowing uninterrupted…

Slide 3: Ensuring Availability and inclusive growth
Ensuring Availability and inclusive growth Domestic Footfall of 15 Million per day LPG for All at ROs Rural Reach 425 Kg through 7864 55 Kg Kg 14.2 Kg KSKs Industrial 2 Million Refuelling Cylinders -1,750 flights rolled out per per day Advanced day Winter stocking - forward Defence locations

Slide 4: Bringing Innovative Solutions to Business
Bringing Innovative Solutions to Business Supply of ODC consignment ISO Containers in ATF through CRM: one International Logistics Trading stop waterways Desk solution Automation Reverse Indane Auction Nanocut Vendor on-boarding In house R&D TReDs for on GeM tech: IndJET; MSMEs IndMax; Octamax And m

Slide 5: Championing Clean fuels
Championing Clean fuels BS VI Projects on track – Pan-India roll out by 1.4.2020 Preparedness for MARPOL 2nd Generation Ethanol Project at Panipat Improving refinery efficiency and processes Refinery off gas harvesting project for hydrocarbon production Painted Storks nesting at Mathura Refinery

Slide 6: Strides in Renewable energy
Strides in Renewable energy LOIs issued to 85 parties 20 Retail Outlets identified for CBG dispensing Wind Capacity of 168 MW (cumulative) installed Solar Capacity of 44 MW (cumulative) installed

Slide 7: Strides in Renewable Energy
Strides in Renewable Energy World’s highest altitude Bottling Plant at Leh is now 100% Solar powered

Slide 8: Shifting to Green Economy
Shifting to Green Economy 40 CGDs under IOCL’s Ambit IndianOil (Standalone) 17 IndianOil-Adani Gas Pvt. Ltd. (IOAGPL) 19 (with Adani Gas Ltd.) Green Gas Ltd. (GGL) (with GAIL) 4 Inauguration of CNG station at Bokaro – GA won by IOCL on stand-alone basis JVA Signing for Indradhanush Gas Grid Ltd.

Slide 9: Kept the energy flowing in Kerala
Kept the energy flowing in Kerala .. Business Standard Report Kerala floods: As forces stepped up rescue ops, IOC kept ATF supply going At the Cochin Naval Base Airport, Indian Oil undertook 272 refuellings of rescue aircraft and choppers in a span of three days The floods that have devastated Keral

Slide 10: Fani preparedness
… and now in Odisha Fani preparedness No disruption at Paradip Refinery Uninterrupted Supply to Rescue Aircrafts RO Operating in BBSR Sufficient Inventory at ATF Stocking at No Paradip/ Jatni/ Jharsuguda/ Bhubaneswar AFS Dryouts Balasore Industry Demands Met Community Meals Fuel supply to customers

Slide 11: Upholding Operational Excellence in 2018-19
Upholding Operational Excellence in 2018-19

Slide 12: Crude Processing
Crude Processing • Highest-ever • Crude processed • Mathura Refinery ( 9.7 MMT) • Paradip Refinery (14.5 MMT) • Barauni Refinery (6.65 MMT) • Difficult Crude Processing (77%) • Two term contracts for US Crude Oil for 2019-20 • Nine New Crude Grades included in Indian Crude basket (180 grades now)

Slide 13: Refining Benchmarks
Refining Benchmarks • 1st ever equity crude from UAE • 90% of fuel quality upgradation projects completed • GRM of 5.41 $/ barrel Highest-ever Production of LPG 3.5 MMT ATF 3.9 MMT MS 10.8 MMT HSD 32.8 MMT 2% 3% 2%

Slide 14: Pipeline Operations
Pipeline Operations • Highest-ever • Crude pipeline throughput (51.36 MMT) • POL pipeline throughput (36.6 MMT) 3.8% • Gas pipeline throughput (1832 MMSCM) • Total pipeline (Crude + POL) network representing a capacity of 94.2 MMTPA 3.6% • Improving Energy Consumption Kcal/(MT*km) 20.1 16.4 15.1 (Up

Slide 15: Network Expansion
Network Expansion ❖ Projects/ Replacements Completed 94.2 MMTPA Liquid 21.69 MMSCMD Gas – Paradip-Haldia-Durgapur LPG Pipelines Capacity Pipelines Pipeline – Jaipur-Panipat Naptha Pipeline – 42”Crude Pipeline to CPCL – Kolkata ATF Pipeline – Panipat-Kohand LPG Pipeline – Last section of BKPL rerouti

Slide 16: Fuelling India's Growth
Fuelling India’s Growth 3.7% 4.1% Sale of LPG crossed 1 MMT per month for the first time in December 2018.

Slide 17: IndianOil Touch Points
IndianOil Touch Points Network Expansion by over 2,812 in 2018-19 ROs 313 KSKs 335 Terminals/ Depots 1 LPG Distributors 1800 AFS 9 Consumer Pumps 352 Over 50,984 Touch Points Automation of all operational ROs / KSKs completed

Slide 18: Marketing: New Plateaus
Marketing : New Plateaus Supply of BS VI grade fuels Monthly LPG sale surpassed commenced in NCT and 12 1 MMT contiguous districts LPG connections-more than 2 Cr Operating 24 AFSs (Highest No.) at Solarised ~ 5,000 Retail Outlets RCS Locations -installed capacity 71 MW

Slide 19: Focus on R&D
Focus on R&D Developing / Commercialising Indigenous Innovative Technologies 1000 effective World’s 1st CO2 patents as of to Lipid pilot 30.04.2019 plant IndeDiesel at Gujarat Refinery Nano-additized New Campus in for BS VI batteries Offing compliance Indane Nanocut Sale : 1247 MT 5 TPD (18-19) Bio-

Slide 20: New Launches
New Launches 3G Biofuel technology with DBT & Lanzatech, USA & Biomethanation plant for converting city waste of Faridabad into biogas

Slide 21: Support to Start-ups
Support to Start-ups Technology Process Re-engineering Business Process Re-engineering Bio-formulation Enhanced Fleet Management Electronic Leak Detection Emissions Reduction Projects Enhancing RO Automation under Phase 1 Fuel Cell based Research Automated TT Locking Deriving Fuel Substitutes Levera

Slide 22: Diversification
Diversification

Slide 23: Value creation in Petrochemicals
Value creation in Petrochemicals • Symbol Of Excellence In Plastics & Polymer Industries • More than 100 OEM approvals • Over 20 import substitute grades • Preferred Supplier to HUL, ITC, Tupperware, Samsonite etc • Venturing into deep downstream ❑ Plastic and Textile Park in Odisha Panipat Naphtha

Slide 24: Gas Business
Gas Business Data in MMT 3% 2% Note: Includes Internal Consumption 17% share in India’s R-LNG Segment

Slide 25: Gas Infrastructure
Gas Infrastructure City Gas Distribution • 40 Geographical Areas under ambit • 29 CGDs won solo/ thru JV in 9th & 10th rounds • CNG Station in Bokaro (9th round GA) commissioned on 23.2.2019 1 LNG Terminals • Ennore - Commissioned in March 2019 • Capacity booked in Dhamra LNG Terminal 2 Pipelines •

Slide 26: Ennore LNG Terminal
Ennore LNG Terminal (dedicated to nation on 06.03.2019)

Slide 27: Upstream Portfolio
Upstream Portfolio 67% Growth in Upstream Production

Slide 28: Recent Acquisitions
Recent Acquisitions Location Oman Location Israel Location Abu Dhabi Block Mukhaizna Block Block 32 Block Onshore Block 1 IOC Stake 17% IOC Stake 25% IOC Stake 50% Status Producing Status Exploration Status Exploration ..and Umatara Cluster, Assam a domestic discovered field where IndianOil is lead

Slide 29: Increasing Global Visibility
Increasing Global Visibility Contracts for export of ATF / MS / HSD on B2B basis with Puma Energy, Singapore and Unipect Pte Ltd., Singapore 7 training programmes at Dung Quat Refinery, Vietnam Manpower secondment MoU with Emirates National Oil Company (ENOC) New representative Office in Nepal in ad

Slide 30: Alternate Energy Space
Alternate Energy Space ❖ Highest Renewable Generation – 388 GWHr generation in 2018-19 ❖ Carbon Mitigation – Mitigated ~318 TMT equivalent CO2 in 2018-19

Slide 31: IndianOil's Largest Rooftop Solar Plant
IndianOil’s Largest Rooftop Solar Plant 2.75 MW at Panipat Refinery & Petrochemical Complex (commissioned 7.1.19)

Slide 32: Other futuristic projects
Other futuristic projects ❖ 2G Ethanol ❖Waste to fuel ⁻ Work commenced for 2G Ethanol ⁻ Three 5 TPD plants Varanasi operational Plant at Panipat ❖ Waste (Used Cooking Oil) to Bio-diesel. ⁻ Working on processing of UCO (through trans-esterification) for production of bio-diesel ❖ Other Avenues Waste

Slide 33: New Beginnings in Compressed Biogas
New Beginnings in Compressed Biogas Operating 14 TPD CBG plant at IOTL, Namakkal 290 TPD of Press Mud, Chicken litter, Dairy Effluent

Slide 34: Working on Plastic Neutrality
Working on Plastic Neutrality • Waste generated • Polymer • plastic segregated segregated • Processed Office, • Pelletized household, Recycler manufacturing IndianOil working towards facilitating the ecosystem Plastic processor, Compounder OEM • Polymer processed/ • Compounding converted to • Patent

Slide 35: Projects
Projects -—a

Slide 36: Major Projects Completed (18-19)
Major Projects Completed (18-19) Distillates Yield Improvement Polypropylene Plant at Paradip Paradip-Haldia-Durgapur LPG Jaipur- Panipat- Naptha Project (COKER) at Haldia Refinery Pipeline Pipeline Refinery Rs 3,150 Cr Rs 1,330 Cr Rs 611 Cr Rs 4,190 Cr #Feb 2019 #Dec’18 #Jan 2019 # Jun’18 Raze, reb

Slide 37: Major Projects under Implementation - Refineries
Major Projects under Implementation Refineries Fuel Quality Upgradation Fuel Quality Upgradation INDMAX Project BS-VI Projects - Refineries Project - Barauni Refinery Project - Gujarat Refinery at-Bongaigaon Refinery Rs 16,338 Cr Rs 1,774 Cr Rs 1,315 Cr Rs 2,582 Cr #Feb’20/ Aug’21 #Oct’19 #Jun’19 #N

Slide 38: Major Projects under Implementation - Pipelines
Major Projects under Implementation Pipelines Augmentation of Paradip – Jaipur– Panipat Naphtha Ennore -Trichy - Madurai LPG Paradip Hyderabad Pipeline Haldia – Durgapur LPG Pipeline along with Pipeline Project Pipeline and its extension up augmentation of Koyali- Rs 711 Cr Rs 3,338 Cr to Patna and

Slide 39: Major Projects under Implementation - Marketing
Major Projects under Implementation Marketing Grass root POL Terminal at Grass Root POL Terminal at Malkapur, Hyderabad Motihari, Bihar LPG Import Terminal & Jetty at Cochin, Kerala Rs 611 Cr Rs 522 Cr Rs 714 Cr #May’22 #Mar’21 Augmentation of LPG Import LPG Import Facility at Paradip, Odisha Termin

Slide 40: Moving Forward
Moving Forward …. 60 MMTPA West coast refinery Building Natural gas import and Brownfield transportation Commercialization expansions - 28 capacity of R&D MMTPA plus by 2030 Consolidating Core Accelerating Expanding footprints Raising Upstream Business Extended in attractive overseas Business Integr

Slide 41: Key Accolades
AIMA - Outstanding PSU of the year Vigilance Excellence Award' by the Hon'ble President of India Key Accolades FIPI - Human Resource Company of the Year

Slide 42: Social Consciousness
Social Consciousness

Slide 43: CSR Activities
CSR Activities Skill Development – Training programs through NSDCs - Jal-Jeevan: Clean Drinking Water across the country – Bore-wells & Hand pumps in identified villages – Skill Development Institute, Bhubaneshwar Education Healthcare – ICTM-IOC, Bhubaneshwar – AOD Hospital, Digboi – IndianOil Vidus

Slide 44: IndianOil Vidushi: A flagship CSR project
IndianOil Vidushi: A flagship CSR project 46 of the 56 girls coached at IndianOil Vidushi Centres in Bhubaneswar and Noida - cleared JEE Mains examination

Slide 45: Financials (To be updated)
Financials (To be updated)

Slide 46: Turnover
Turnover Rs. crore Turnover (Rs. crore) 2016-1 2017-1 Particular Var (%) 7 8 % 13.4 Petroleum 3,99,792 4,49,648 12.5% Petrochemicals 18,728 17,163 (8.4)% Gas 5,520 6,103 10.6% Exports 14,652 24,486 67.1% Turnover 4,38,692 4,97,400 13.4% Other Revenue 6,750 9,028 33.7% including subsidy Income from 4

Slide 47: Profits
19,106 2016-17 2017-18 —. APT ae —

Slide 48: Profits (Quarterly)
Profits (Quarterly)

Slide 49: Profitability for the year
Profitability for the year Key Indicators (Rs. crore) Deviations in Annual Profit 2016-17 2017-18 from Previous Year Net Profit/ (Loss) 19,106 21,346 Increase by Rs. 2,240 crore Major Reasons Contributing to the increase in Profit: Provisions for Contingency (6,975) 2,814 Increase by Rs. 9,789 crore

Slide 50: Under-Recoveries
Under-Recoveries Parameter 2015-16 2016-17 Rs. crore 2017-18 Under-Recovery on SKO 7,757 5,149 3,196 Claims thru DBTL – LPG 8,192 6,265 10,627 Total 15,949 11,414 13,823 All under-recoveries are fully compensated.

Slide 51: Leverage
Rs. crore co 1.10 1.00 0.90 40,000+ 0.88 : 0.60 0.7% 30,000 pe 0.4 20,000- ‘0.5 10,000: 3,090 3,445 3,448 — , ” ’ id +0.30 0 = 0.20 2015-16 2016-17 2017-18 7a eas terest Cost ™Borrowings ™Debt Equity Ratio

Slide 52: Contribution to Exchequer
Contribution to Exchequer Rs. crore

Slide 53: Evolving Human Capital
Evolving Human Capital Driver – Leveraging People’s Potential & Motivating Millennials Robust Induction & Onboarding Programme Saksham – Competency Development Programme A Great Place to Work Schemes for Upgrading professional skills - e-Learning Platform Mentoring & Reverse Mentoring Process Focus

Slide 54: Our Superstars
Our Superstars Accolades in the Asian Games (Sept’ 18) ❖ Mr. Rohan Bopanna and Mr. Divij Sharan - Gold medal in Tennis Men doubles ❖ Mr Aman Saini - Silver medal in Archery ❖ Ms. Manika Batra - Bronze medal in mixed doubles in TT ❖ Mr. A Sharath Kamal - Bronze medal in team & mixed doubles events in

Slide 55: Open Forum
Open Forum
Source: Internet Archive copy of iocl.com
More decks from Indian Oil Corp. Ltd.
Q4 FY2025-26 Earnings Presentation9 slides · May 19, 2026
Q3 FY2025-26 Earnings Presentation7 slides · February 2026
Investor Presentation (2026)31 slides · 2026
Q1 FY2026-27 Earnings Presentation7 slides · 2026
Q4 FY2025-26 Earnings Presentation8 slides · 2026
Investor Presentation (August 2025)7 slides · Oct 27, 2025