Merafe Resources Limited · JSE:MRF

Merafe Resources — Technical Presentation (November 2017)

32 slides from Merafe Resources's technical presentation, Nov 10, 2017

  1. Slide 1: Investor Site Visit - Magareng Mine - 10 November 2017

    INVESTOR SITE VISIT MAGARENG MINE - 10 NOVEMBER 2017

  2. Slide 2: Legal notice/disclaimer

    Legal notice/disclaimer This presentation is published solely for informational purposes and does not constitute investment, legal, tax or other advice nor is it to be relied upon in making an investment decision. Information contained herein has been taken from sources considered by Merafe Resource

  3. Slide 3: Itinerary

    Itinerary • 09:00 – 09:30 Arrival, welcome and Presentation • 09:30 – 09:45 Induction • 09:45 – 11:30 Change and depart for Underground visit • 11:30 – 11:45 Plant drive through • 11:45 – 12:00 Refresh from underground visit • 12:00 – 12:30 Lunch and Q&A • 12:30 – 13:00 LION smelter presentation • 1

  4. Slide 4: Presentation

    Presentation • HSEC • Background • Mine layout • Mining methodology • Ore processing and products 4 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  5. Slide 5: Safety: major risks and behaviours

    • Your safety is important to us • SAFEALLOYS • 9 Life saving behaviours • Fatal hazard protocols • Major Risks: – FOG/Strata Control – TMM – Electricity and Lockout – Conveyors – Fire/Explosion – Working at heights • Behaviour Based Safety System (Meerkat) • We Work Safe – One Day At A Time 5 Meraf

  6. Slide 6: Background: Location and geology

    Background • Location and geology 6 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  7. Slide 7: Background (cont.) - History of chrome mining

    Background (cont.) • History of chrome mining – World’s largest known layered intrusion (Bushveld Complex) – Thirteen chromite seams in the upper and lower critical zones 7-LG’s, 4-MG’s, 2-UG’s. – Chromite – discovered in S.A. in 1865 by Carl Mauch in the Hex River near Rustenburg. – Mining chromite

  8. Slide 8: Background (cont.) - Geology stratigraphy

    Background (cont.) • Geology - stratigraphy 8 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  9. Slide 9: Background (cont.) - Location

    Background (cont.) • Location 9 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  10. Slide 10: Background (cont.) - Thorncliffe, Helena, Magareng mines

    Background (cont.) • Thorncliffe mine: Started – 1997 • Rom 115 000 tons per month • Helena mine - Started – 2004 • Rom 110 000 tons per month • Magareng Mine – Started – 2008 • Rom 115 000 tons per month 10 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  11. Slide 11: Background - Chromite seams mined

    Background – Chromite seams mined • Mining the MG1 and UG2 seams on the Eastern and Western limb of the bushveld complex • The mining width varies from 170cm to 240cm • Dip (inclination) varies from 9° - 16° below the horizontal • Internal waste and lenses in the reef up to ±90cm • MG2 and other MG’

  12. Slide 12: Background (cont.) - Mine site 2008

    Background (cont.) • Mine site 2008 12 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  13. Slide 13: Background (cont.) - Opencast development

    Background (cont.) • Opencast development 13 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  14. Slide 14: Background (cont.) - Opencast stabilisation

    Background (cont.) • Opencast stabilisation 14 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  15. Slide 15: Background (cont.) - High walls and main decline development

    Background (cont.) • Completed high walls and start of main decline development 2010 15 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  16. Slide 16: Background (cont.) - Project timeline

    Background (cont.) • Started project in 2008 • First sinking commenced in 2010 • Mining ramp up and plant construction from 2012 • Production build up to capacity from 2014 • Current production on 115 000t run of mine and plant feed 16 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 No

  17. Slide 17: Life of Mine including Richmond (deeper reserves)

    Life of Mine including Richmond (deeper reserves) 17 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  18. Slide 18: Mine layout

    Mine layout • Trackless bord and pillar mine, all excavations on reef • Reef width of 1.7m and mining height of 2.0m • Main sinking comprising of 4 cluster declines, 6m wide • Stoping sinking comprising of 4 cluster declines, 6m wide • Stoping sections with 12 x 8m bords per section serviced by 2 st

  19. Slide 19: Mine layout (cont.)

    Mine layout (cont.) Adit / portal Ventilation shafts Declines – Ledging Vehicle Conveyor Chairlift Access ledging Sections of 12 Panels Panels 19 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  20. Slide 20: Mine layout (cont.)

    Mine layout (cont.) 20 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  21. Slide 21: Mining methodology

    Mining methodology • Triple decline shaft systems from surface • All development and mining done on Reef horizon • Low Profile Mechanised Room and Pillar Mining • Mechanised Drilling and Loading • Tips with vibratory feeders and herringbone Conveyor network system to transport ore • Monitoring Syste

  22. Slide 22: Basic mining equation

    Basic mining equation • Mining Cycle: – 3 shifts per day – 22 working days per month – One blast per day – end of day shift – Blast clearance/re entry of 2 hours – Production sections of 12-16 panels dedicated to a drill rig section: • Cleaning – 3,5 ton lhd • Drill and install support – remote auto

  23. Slide 23: Support installation

    Support installation 23 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  24. Slide 24: Drill rig - panel drilling

    Drill rig – panel drilling 24 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  25. Slide 25: Charged up panel for Blasting

    Charged up panel for Blasting 25 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  26. Slide 26: Load haul dumper

    Load haul dumper 26 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  27. Slide 27: Underground tip

    Underground tip 27 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  28. Slide 28: Underground conveyor

    Underground conveyor 28 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  29. Slide 29: Ore flow diagram

    ROM IS STORED ON A LIVE 1500 t STOCKPILE CRUSHED ROM IS STORED ON A 7000 t LIVE ROM FEED FROM UNDERGROUND AND CRUSHED STOCKPILE ROM IS FED INTO PREPARATION PLANT AND SORTED INTO LUMPY AND CHIPS Ore flow diagram SPIRALS BUILDING MILLING AND CFC BUILDING LUMPY AND CHIPS FRACTIONS ARE TREATED IN THE HM

  30. Slide 30: Chrome products produced

    Chrome products produced 30 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  31. Slide 31: Eastern Chrome Mines Production Capacity/month

    Eastern Chrome Mines Production Capacity/month 31 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

  32. Slide 32: Questions

    Questions 32 Merafe Resources Ltd | Investor Site Visit – Magareng Mine 10 November 2017

Merafe Resources — Technical Presentation (November 2017) on 6ix