Slide 1: 2013 Interim Results
2013 Interim Results 27 August 2013

Slide 2: Important Notice
Important Notice • This document has been prepared by Petrofac Limited (the Company) solely for use at presentations held in connection with the announcement of its results for the six months ended 30 June 2013. The information in this document has not been independently verified and no representati

Slide 3: Ayman Asfari, Group Chief Executive
Ayman Asfari Group Chief Executive

Slide 4: Headlines
Headlines • 2013 revenue and net profit significantly weighted towards 2H 2013, reflecting the phasing of project delivery • On course to deliver modest growth in net profit in 2013 and, given our high quality portfolio and strong bidding pipeline, we remain on track to achieve our 2015 earnings tar

Slide 5: ECOM – Key contract awards
ECOM – Key contract awards Strong ECOM order intake for 1H 2013 of US$4.9 billion (1H 2012: US$1.4 billion) • Upper Zakum, Abu Dhabi, US$2.9bn EPC contract to develop the UZ750 field development • Bab Compression, Abu Dhabi, US$500m expansion of compression facilities at OEC the Bab Field • Bab Habs

Slide 6: ECOM – Update on major projects (Onshore)
ECOM – Update on major projects Onshore Engineering • South Yoloten (aka Galkynysh) gas field development, Turkmenistan, Asab & Construction onshore oil field development, Abu Dhabi and El Merk gas processing facility, Algeria, commissioning in progress and completion remains scheduled for 2H 2013 •

Slide 7: ECOM – Update on major projects (Offshore)
ECOM – Update on major projects • UK business very robust with increased levels of activity from core clients such Offshore Projects & Operations as Apache, EnQuest and CNR • Laggan-Tormore, Shetland, is now midway through its construction phase and we remain on schedule to complete the project in 2

Slide 8: ECOM – increase in Petrofac Emirates interest
ECOM – increase in Petrofac Emirates interest • Following a strategic review, Mubadala decided to transfer some of their investments to the private sector • Opportunity arose to increase our economic interest in Petrofac Emirates to 75%, effective January 2013, for an acquisition cost of US$35 milli

Slide 9: ECOM – New business prospects
ECOM – New business prospects • Strong pipeline of bidding opportunities for onshore engineering and construction projects in our core markets for 2H 2013 and beyond • Anticipate continuing growth of Onshore Engineering & Construction backlog during 2013, before taking into account our increased eco

Slide 10: IES – Production Enhancement Contracts
IES – Update on major projects • Took over operation of Pánuco and offshore Arenque blocks in late March and early July 2013 following successful Production Enhancement Contracts transition • Magallanes and Santuario – achieved improvement in production since taking over operations in February 2012

Slide 11: IES – Risk Service Contracts
IES – Update on major projects • Berantai – 13 wells from the first phase of the development brought online • Berantai full field development, including FPSO topsides, Risk Service Contracts achieved in less than 21 months Berantai, Malaysia • In discussions with our partners on the second phase to

Slide 12: IES – Equity Upstream Investments
IES – Update on major projects Equity Upstream Investments • Commenced production from 3rd phase of development of Block PM304, West Desaru, in August 2013, only 18 months from approval of the FDP by Petronas • Drilled two new wells in 1H 2013 on Block PM304 as part of a near field appraisal program

Slide 13: IES – New business prospects
IES – New business prospects • Focus remains on delivering value from existing projects and building geographical hubs • Bidding on PECs in Indonesia and Malaysia, have signed an MoU to explore PEC opportunities in Kazakhstan and are working with a number of independent oil and gas companies to asse

Slide 14: Tim Weller, Chief Financial Officer
Tim Weller Chief Financial Officer

Slide 15: Income Statement
Income Statement US$m 1H 2013 1H 2012 Variance restated Revenue 2,794 3,187 12% Operating profit* 295 412 28% Profit before tax 300 413 27% Income tax expense (58) (89) 35% Profit for the period 242 324 25% Profit attributable to Petrofac Limited shareholders 243 326 25% EBITDA* 405 455 11% ROCE 25%

Slide 16: Backlog
Backlog • Backlog of US$14.3 billion at 30 June 2013 (Dec 2012: US$11.8 billion), reflecting strong order intake in 1H 2013 and increase in economic interest in Petrofac Emirates • Onshore Engineering & Construction backlog increased to US$7.8 billion (Dec 2012: US$5.1bn), improving visibility of fu

Slide 17: Cash flow and gross cash balances
Cash flow and gross cash balances • Net debt stood at US$370 million at 30 June 2013 reflecting: – Working capital outflows of US$485 million due to a decrease in trade payables, including a reduction in advances received from customers of US$151 million, and a decrease in accrued contract expenses

Slide 18: Onshore Engineering & Construction
Onshore Engineering & Construction • Revenue i31% – project phasing, including scheduling of recent awards and rephasing of In Salah southern fields development, result in revenues being weighted to 2H 2013 • US$2.2 billion of revenues in hand for H2 2013 and expect further revenue from contractual

Slide 19: Offshore Projects & Operations
Offshore Projects & Operations • Revenue h1% – 1H 2013 revenues broadly flat due to project phasing • Expect to deliver full year double-digit revenue growth, with US$1.0bn in hand for H2 2013 at 30 June 2013 • Net profit i61% – 1H 2012 benefited from substantial work from offshore capital projects;

Slide 20: Engineering & Consulting Services
Engineering & Consulting Services • Revenues h75% – strong growth in revenues reflecting a substantial increase in activity levels, including on a project in Malaysia and consolidation of RNZ from April 2013 • Net profit h20% – reflecting substantial increase in activity levels • Full year net profi

Slide 21: Integrated Energy Services
Integrated Energy Services • Revenue h32% – growth predominantly driven by an increasing contribution from PECs • Net profit i33% – 1H 2012 included a gain in relation to the sale of 75% of the share capital in the company holding the FPF1 of US$36 million • Excluding the FPF1 gain, net profit growt

Slide 22: Summary and outlook
Summary and outlook • As previously indicated, 2013 revenue and net profit significantly weighted towards the second half of the year, reflecting the phasing of project delivery • 30 June 2013 backlog of US$14.3 billion, greatly improves revenue visibility for next year and beyond • Given the qualit

Slide 23: Appendices
RX UO © Ee {e) hae 10) jae

Slide 24: Appendix 1: Group organisation structure
Appendix 1: Group organisation structure Divisions Engineering, Construction, Operations & Maintenance Integrated Energy Services (IES) (ECOM) Chief Executive, Andy Inglis Chief Executive, Marwan Chedid Reporting segments Onshore Engineering Engineering & Offshore Projects & Operations & Consulting

Slide 25: Key ECOM projects
Key ECOM projects Customer key: Original contract NOC/NOC led company/consortium Joint NOC/IOC company/consortium IOC/IOC led company/consortium value to Petrofac Asab onshore oil field development, Abu Dhabi US$2,300m El Merk gas processing facility, Algeria US$2,200m GASCO 4th NGL train, Abu Dhabi

Slide 26: Appendix 3: Key IES projects
Appendix 3: Key IES projects Production Enhancement Contracts (PEC) END DATE 2025 (+10 YR TRANSITION Ticleni, Romania PERIOD EXTENSION OPTION) TRANSITION Magallanes and Santuario, Mexico PERIOD 2037 TRANSITION Pánuco, Mexico * PERIOD 2043 TRANSITION 2043 Arenque, Mexico PERIOD Risk Service Contracts

Slide 27: Appendix 4: Effective tax rate
Appendix 4: Effective tax rate Tax charge by segment 1H 2013 FY 2012 Onshore Engineering & Construction 13% 13% Offshore Projects & Operations 37% 23% Engineering & Consulting Services 17% 13% Integrated Energy Services 33% 35% Group 19% 18% • Offshore Projects & Operations ETR higher due to geograp

Slide 28: Appendix 5: Segmental performance
Appendix 5: Segmental performance • Onshore Engineering & Construction earned 56% of revenue and 74% of net profit • Middle East and Africa: due to geographic diversification, represents only 37% of revenues in 1H 2013 • CIS and Asia: primarily relates to activity on South Yoloten in Turkmenistan an

Slide 29: Appendix 6: Employees
Appendix 6: Employees • More than 18,000 people in 7 key operating centres and 24 offices • EPC headcount includes the engineering offices in India, which although reported in Engineering & Consulting Services principally support Onshore Engineering & Construction activities • Approximately 5,300 em

Slide 30: Appendix 7: EPC risk management and accounting
30 Revenue recognition acceptance certificate Profit recognition Final Project risk Warranty phase acceptance Provisional certificate Appendix 7: EPC risk management and accounting 100% Robust Completion systems to facilitate Mechanical completion smooth startup Manage/support local construction con

Slide 31: Notes
Notes • EBITDA means earnings before interest, tax, depreciation and amortisation and is calculated as profit from operations before tax and finance costs, but after our share of results of associates, adjusted to add back charges for depreciation, amortisation and impairment. • Net profit (for the
Source: company website
More decks from Petrofac Limited
Investor Presentation (2025)22 slides · Aug 15, 2025
H1 2024 Earnings Presentation25 slides · Sep 30, 2024
FY2023 Earnings Presentation29 slides · May 31, 2024
H1 2023 Earnings Presentation27 slides · Aug 10, 2023
FY2022 Earnings Presentation33 slides · Apr 27, 2023
Investor Presentation (2023)20 slides · 2023