  1. Slide 1: Eneabba rare earths refinery

    1 Iluka Resources (ASX:ILU) Eneabba rare earths refinery Positive outcome of funding discussions and updated economics 6 December 2024

  2. Slide 2: Disclaimer

    Disclaimer 2 This release has been prepared by Iluka Resources Limited (Iluka). By accessing this release you acknowledge that you have read and understood the following statement. This release includes forward-looking statements reflecting Iluka’s current expectations. These statements are expresse

  3. Slide 3: Positive outcome of funding discussions to deliver Eneabba refinery

    Positive outcome of funding discussions to deliver Eneabba refinery 3 Refinery features $1,650m Loan terms non-recourse loan reflect shared risk From the Australian Government BBSY + 3.0%, flexible repayment terms Brownfield site, access Producing separated light to major utilities and heavy rare ea

  4. Slide 4: Additional funding arrangements

    Additional funding arrangements 4 Iluka’s partnership with the Australian Government encompasses key contributions from both parties, appropriate risk sharing, and the alignment of commercial and policy objectives Original funding – Additional funding1 – March 2022 December 2024 $1,250 million $400

  5. Slide 5: Production optionality and illustrative scenarios

    Production optionality and illustrative scenarios 5 Eneabba refinery potential feedstock options Illustrative scenarios assumptions Eneabba will be capable of processing a wide range of feedstocks Production and economic scenarios presented on basis of internal Iluka developments and secured that ar

  6. Slide 6: Project and equity returns

    Project and equity returns 6 Strong project economics and equity returns to Iluka based on a range of internally available feedstock (Scenario A); significant upside from improved utilisation over 35 year refinery longevity (Scenario B). Equity returns to Iluka reflect preferential cash flow waterfa

  7. Slide 7: Illustrative production scenarios

    Illustrative production scenarios 7 The Eneabba refinery is being developed as a multi-decade infrastructure asset capable of processing a range of feedstocks1 with optionality on feed to deliver highly valuable separated rare earth oxides NdPr and DyTb Rare earth concentrate feed (ktpa) NdPr (ktpa)

  8. Slide 8: Capital expenditure

    Capital expenditure 8 Capital estimate confirmed at $1.7-1.8 billion; Front End Engineering Design completed Growth, contingency and escalation account for ~25% of remaining capital spend Refinery capital April 2022 2024 expenditure FID estimate FEED estimate Iluka equity contribution and working ca

  9. Slide 9: Operating costs

    Operating costs 9 A secure, globally competitive, Western supplier of separated rare earth oxides, with full product provenance Resilient in the event of a low price environment Refining costs1 Labour, camp and admin $75-80m • Cracking, leaching and purification and separation and finishing costs ar

  10. Slide 10: Cash flow waterfall

    Cash flow waterfall 10 Strategic partnership cash flow waterfall preferences cash flow to Iluka equal to scheduled debt repayments Illustrative cash flow waterfall1 Project cash flows Cash flows waterfall priority Cash flows $m ILU cash flows Loan servicing Up to $81m p.a. preferential distribution

  11. Slide 11: Operational readiness

    11 Operational readiness Eneabba phase 2 plant

  12. Slide 12: Key personnel and operational readiness

    Key personnel and operational readiness 12 Iluka has processed and marketed industrial minerals for over 70 years The company is implementing operational readiness plans in line with the schedule for Eneabba’s commissioning, including detailed planning and personnel assignment Dan McGrath Organisati

  13. Slide 13: Refinery process flow

    Refinery process flow 13 The Eneabba refinery has been designed to allow maximum practicable flexibility in feed sources and rare earth oxide output while minimising cost and environmental impact The refinery will use sulfuric and nitric acid, based on process flow sheet in use at separation facilit

  14. Slide 14: Rare earth markets and offtake approach

    Rare earth markets and offtake approach F35 fighter jet

  15. Slide 15: Strong industry fundamentals

    Strong industry fundamentals 15 Global demand forecasts vary on market penetration of renewable energy technologies, substitution and magnet composition Additional NdPr oxide required over the next decade forecast to be ~35-130 thousand tonnes Materially higher amounts of DyTb required - Eneabba ref

  16. Slide 16: Supply chain currently dominated by vertically integrated China

    Supply chain currently dominated by vertically integrated China 16 China has vertically integrated its rare earth industry from oxides to metals, alloys, powders and magnets Pricing and other support mechanisms ensure market dominance across the value chain to ultimately support value add end use in

  17. Slide 17: Chinese state influence on rare earth prices

    Chinese state influence on rare earth prices 17 Rare earths are not exchange traded and there is no spot market. The Asian Metal Index is the only publicly available price index for rare earth oxides. The index is influenced by actions of the Chinese government and Chinese enterprises and not a refl

  18. Slide 18: Important contribution to sovereign capability and secure supply chains

    Important contribution to sovereign capability and secure supply chains 18 The Eneabba refinery is the first of its type in Australia and one of few facilities globally. It is critical infrastructure that establishes sovereign industry capability and on-shore value addition – supporting both nationa

  19. Slide 19: Marketing approach

    Marketing approach 19 Iluka is experienced in selling specialty minerals in non-exchange traded, opaque markets The marketing approach for Eneabba’s separated rare earth oxides will be based on supply of a sustainable, secure product with full provenance • To create a truly independent supply chain,

  20. Slide 20: Stockpile value

    Stockpile value 20 Rare earth price assumptions impact refinery value but also the value of alternate options such as monetising stockpile via concentrate sales Eneabba stockpile value sensitivity: NPV 8.25% (A$m)1 A$m $3,000 • At the current Asian Metal Index NdPr price (as at November 2024) the En

  21. Slide 21: Supplementary Information

    Supplementary Information Eneabba, Western Australia

  22. Slide 22: Project economics

    Project economics 22 1. Figures presented in real 2024 terms. Pricing assumes SCENARIO A SCENARIO B SCENARIO C Adamas Q4 2024 rare earths price forecasts and TZMI September 2024 mineral sands price forecasts 2. Average figures for 1-4 years and Life of mine (LOM) Eneabba stockpile + Scenario A + Ene

  23. Slide 23: Concentrate purchase costs

    Concentrate purchase costs 23 In addition to utilising Iluka’s unique rare earths stockpile, Eneabba Balranald concentrate value worked example will be a purchaser of concentrate feedstock from internal Iluka and 3rd party sources 2023 REO price Weighted average REO Balranald REO assemblage1 (US$/kg

  24. Slide 24: Pricing assumptions

    Pricing assumptions 24 Adamas Intelligence price forecast (Rare Earth Magnet Market Outlook to 2040, Q4 2024) US$/kg US$/kg (real 2024) (real 2024) Price forecast provider $250 $4,000 Adamas Intelligence: Adamas Intelligence are leading, independent $200 critical minerals industry experts. Their $3,

  25. Slide 25: Simplified Eneabba refinery flowsheet and circuit capacities

    Simplified Eneabba refinery flowsheet and circuit capacities 25 1 2 3 3 Cracking and leaching Purification 2 Separation and finishing • Blend of feed concentrate based on feed availability NdPr • Only selected circuits most relevant for modelling purposes shown • SX circuit capacities assume an aver

  26. Slide 26: Mineral Resource and Ore Reserves Compliance Statement

    Mineral Resource and Ore Reserves Compliance Statement 26 Mineral Resources and Ore Reserves Estimates As an Australian company with securities listed on the Australian Securities Exchange (ASX), Iluka is subject to Australian disclosure requirements and standards, including the requirements of the

  27. Slide 27: Mineral Resource and Ore Reserve

    Mineral Resource and Ore Reserve 27 MSP by-product stockpile Mineral Resource and Ore Reserve Selected TREO assemblages HM Assemblage2 Monazite Eneabba Balranald Wimmera Mineral Material In situ HM Clay Ilmenite Zircon Rutile + Lanthanum 22% 21% 18% Deposit Resource tonnes HM tonnes Grade Grade Grad

  28. Slide 28: For more information contact

    28 For more information contact Luke Woodgate, General Manager, Investor Relations and Corporate Affairs investor.relations@iluka.com