Roxgold — Investor Presentation (November 2017)
39 slides from Roxgold's investor presentation, Nov 27, 2017
Slide 1: Mining High Grade Gold in Burkina Faso
Mining High Grade Gold in Burkina Faso TSX: ROXG Investor Presentation | November 2017 TSX: ROXG 1
Slide 2: Cautionary Statement
Cautionary Statement This presentation contains forward-looking information. Forward looking information contained in this presentation includes, but is not limited to, statements with respect to: (i) the estimation of measured, inferred and indicated mineral resources and proven and probable minera
Slide 3: Roxgold – Compelling Investment in the Gold Sector
Roxgold – Compelling Investment in the Gold Sector Canadian Based – Best in Class West African Gold Miner High-Grade, Low-Cost Underground Gold Producer with Near-Term Expansion Potential ▪ High-grade at 17.1 grams per tonne1 compared to Mauritania Mali average grade of gold mines in Burkina Faso at
Slide 4: Roxgold – Why Invest?
Roxgold – Why Invest? Operations Expansion Team Growth ▪ Commercial production ▪ Estimated average gold ▪ Operational Proficiency ▪ Additional new targets declared in Oct 2016 production of 40,000 oz identified in 2017 ▪ Over 3,400,000 hours ▪ Produced ~169,000 oz per year at Bagassi South Lost Time
Slide 5: Operations
Operations 5
Slide 6: 55 Zone – Currently in Production
55 Zone – Currently in Production ▪ Measured & Indicated Resources1 at 738,000 oz at 17.1 grams per tonne (“g/t”) Au at 5.0 g/t cut-off ▪ 115,000 – 125,000 ounces production guidance in 2017 ▪ Well on track with ~92,000 oz produced as of Q3 2017 ▪ AISC2 guidance of $740 - $790 per ounce for 2017 ▪ D
Slide 7: Tracking to Increased 2017 Production Guidance; Cost Estimates Unchanged
Tracking to Increased 2017 Production Guidance; Cost Estimates Unchanged (oz Au) ▪ Guidance maintained for full year for Cash Operating Cost1 and AISC1 ▪ Significant investment in underground 125,000 development 115,000 115,000 105,000 Cash Operating Cost All-in Sustaining Cost Guidance Range Guidan
Slide 8: Key Financial & Operational Highlights
Key Financial & Operational Highlights Nine months ended September 30, 2017 Financial Highlights – Sept 30, 2017 Operational Highlights – Sept 30 2017 Cash flow from operations ~62M 98.9% recovery rate 91,970 oz produced or $0.17/share Cash on hand ~56M 14.5 g/t >3M hrs Reduction in LT debt ~33% hea
Slide 9: 55 Zone Developed Reserves
55 Zone Developed Reserves1 $44 $740 $790 $445 $490 $740 $790 2017 Block Remain % Devt Developed Nov-Dec 2018 2019 2020 Total 1 35,400 100% 35,400 7,900 24,200 3,300 35,400 2 55,300 100% 55,300 8,600 40,400 6,300 55,300 3 103,100 100% 103,100 24,800 40,900 37,400 103,100 4 66,000 52% 34,200 4,900 14
Slide 10: Expansion
SVL TL ee DW a ML LOTR EL EEL LOBED A, Expansion
Slide 11: Bagassi South – Positive Feasibility Study
Bagassi South – Positive Feasibility Study Base Case Highlights (100% basis, gold price of $1300/oz) Yaramoko ▪ Robust project economics Water ▪ $50M after-tax NPV5%, after-tax IRR 53.2% with a 1.8 year Storage Dam payback on initial capital ▪ ~40% increase in Yaramoko gold production Tailing ▪ Prov
Slide 12: Bagassi South – Timeline
Bagassi South – Timeline Q2 2017 ✓ Infill Drilling Program Complete Operating Cash Costs1 – LOM ($/oz) ✓ Hydrology & Geotechnical Studies ✓ Commence Permitting in Burkina Faso Cash Operating Cost $361 ✓ Commence Camp Expansion Total Cash Cost $426 Q3 2017 ✓ Resource Update ✓ Mine Planning/Optimizati
Slide 13: Yaramoko Production Profile – Reserves only
Yaramoko Production Profile – Reserves only Contained Mined 000s oz Au 180 160 140 Mined (Koz) Contained 120 100 Bagassi South 80 55 Zone 60 40 20 0 2017 2018 2019 2020 2021 2022 2023 1. See Appendix for 55 Zone and Bagassi South Mineral Reserve Notes TSX: ROXG 13
Slide 14: Growth
Growth 14
Slide 15: 55 Zone – 2017 Deep Drilling Program
Zone 55 - 2017 Deep Drilling Program 55 Zone Resource* Size Grade 5,200RL Measured & 738k 17.1 g/t Indicated ounces 347k 5,000RL Inferred 16.1 g/t ounces *As of December 31st, 2016 YRM-16-DD-426 4,800RL 20.1 g/t over 23.8 m 55 Zone Deep Drilling program: ▪ Program completed in early Q4 YRM-17-DD-440
Slide 16: Bagassi South – QV' Potential Additional Upside
Bagassi South – QV’ Potential Additional Upside Inferred Resource of 36,000 oz at 22.0 g/t Au West East Bagassi South drilling program: 5,200RL ▪ 10,000 meters along the QV’ YRM-17-DD-BGS-184 290.0 g/t over 0.8 m structure ▪ Commenced in Q3 5,100RL YRM-17-DD-BGS-181 ▪ Continuing into Q4 55.8 g/t ove
Slide 17: Bagassi South QV' – Drilling Update
Bagassi South QV’ – Drilling Update ▪ Infill drilling program showing good continuity of YRM-17-BGS-302 the shoot along the 8.2 g/t over 0.4 m 5,200RL lithological contact YRM-17-BGS-306A 12.0 g/t over 0.4 m ▪ Results received for holes YRM-17-BGS-300A YRM-17-BGS-290 to 313 13.2 g/t over 0.9 m YRM-1
Slide 18: Regional Geological Overview
Regional Geological Overview Siou 10 Km Niankongo ▪ Large regional land package Boni Shear North of approximately 230 km2, Yaramoko located on the Hounde Belt Boni Shear Central ▪ Majority of known anomalies Yaro and deposits are located 300 Zone along the Boni Shear regional Haho break and the seco
Slide 19: Yaramoko – Ground Geophysical Surveys 2017
Yaramoko – Ground Geophysical Surveys 2017 ▪ The 2017 ground geophysical program included 4 individual grids: Two IP surveys: ▪ Boni Shear IP grid ▪ Houko IP grid Boni Grid Two Pole-Dipole surveys: ▪ Bagassi PD grid Haho ▪ Haho PD grid Grid ▪ Drilling program of 4,500m completed along Bagassi Corrid
Slide 20: Yaramoko – Ground Geophysical IP Compilation
Yaramoko – Ground Geophysical IP Compilation ▪ The ground IP Compilation includes the two 2017 IP grids of Boni Shear and Houko along with the 2014 IP survey ▪ Several areas of regional disruption of Boni Shear structural fabric Anomalies ▪ Defined new targets in the footwall of 55 Boni Zone ▪ Poten
Slide 21: Yaramoko – Boni Shear IP Surveys 2017
Yaramoko – Boni Shear IP Surveys 2017 Niankongo ▪ Larger tonnage shear hosted targets ▪ More traditional deposit targets in Boni Shear Niankongo East West African greenstones Boni Central ▪ The Boni Shear Survey redefined the Boni Shear Central, Contact and Niankongo anomalies Boni Shear ▪ Addition
Slide 22: Yaramoko – Boni Shear Drill Targets
Yaramoko – Boni Shear Drill Targets ▪ Phase 1 drilling of 10,000m to begin in Q4 ▪ Drilling pad preparation currently on going in the field ▪ Drilled fences planning completed for two southern anomalies Boni ▪ Phase 1 drilling to be completed at 200m spacing Houko Boni Shear Contact Tarkwa Inlier TS
Slide 23: Upcoming Catalysts
Upcoming Catalysts Q4 2017 ▪ Commencement of regional drilling programs along the Boni Shear zone, Haho and other regional targets 2017 ▪ Initial results of QV’ infill drilling program & 2018 ▪ Commencement of Houko soil and auger program to follow- up on Q3 IP survey ▪ Commencement of early works i
Slide 24: Roxgold – Compelling Investment in the Gold Sector
Roxgold – Compelling Investment in the Gold Sector Canadian Based – Best in Class West African Gold Miner ▪ High-Grade, Low-Cost Underground Gold Producer with Near- Term Expansion Potential ▪ Strong cash flow generation from 55 Zone ▪ Expansion plan in place at Bagassi South ▪ Estimated average gol
Slide 25: Appendix
Appendix TSX: ROXG 25
Slide 26: Management Team
Management Team John Dorward Paul Criddle Natacha Garoute President & CEO COO CFO 20 years 18+ years 20 years development & operating operating & project mining finance mines experience development experience experience Former Roles: Former Roles: Former Roles: ▪ VP Business Dev. of ▪ COO Azimuth ▪
Slide 27: Finance Summary
Finance Summary Insiders Yaramoko Debt Facility & Mgmt Retail 5.1% 6.2% 18.1% ▪ Debt Facility of $60 Million 6.5% ▪ Interest rate of LIBOR plus 3.75% ▪ Hedging component of 65,000 ounces of gold over the 5 year life of the loan @US$ 1,052/oz 7.9% ▪ Project remains unencumbered by third party streams
Slide 28: 2017 Third Quarter Financial Highlights
2017 Third Quarter Financial Highlights 2017 Year to Date1 Q3 2017 Cash operating cost1 Cash balance Average realized gold price $1,286/oz (unaudited) at $445/oz produced Cash operating cost2 $445/oz or $190/t September 30, 2017 All-In Sustaining Cost1 ~US$56M Total cash cost2 $522/oz $794/oz sold S
Slide 29: Financial Information
Financial Information Q3 2017 YTD 2017 12 Month Financial Position Gold Poured (ounces) 28,410 91,970 Gold Sold (ounces)1 27,912 91,679 LTD reduced by ~33% since Dec 31, 2016 Average realized gold price (per oz) $1,286 $1,255 Revenue1 $36M $115M Adjusted earnings2 $9M $23M $80 $0.03 $0.06 $70 Adjust
Slide 30: People at Yaramoko
People at Yaramoko Head Grade Training and localisation has proven to be Yaramoko Employee Origin Distribution effective at Yaramoko: ▪ 87% Burkinabe employment 14% ▪ 49% of employees from the immediate area ▪ Tangible growth and benefit to the host community 49% 37% Local/Local Non Local Burkinabe
Slide 31: 2017 Social Programs
2017 Social Programs Community investment projects ▪ 30 projects submitted by groups from the community including seven projects for Women and eight projects for the benefit of Youth: creation of a community training center in Bagassi, improvement of the Bagassi potable water system, solar electrifi
Slide 32: Corporate Information
Corporate Information Covering Sell-Side Firm Analyst Capital Structure (as at September 30, 2017) BMO Andrew Breichmanas TSX: ROXG Canaccord Rahul Paul Listings OTC: ROGFF Cormark Tyron Breytenbach Cash ~US$56 million Echelon Wealth Partners Ryan Walker Common Shares Outstanding 371.6M GMP Ingrid R
Slide 33: 2016 Financial Performance
2016 Financial Performance Pre-commercial Commercial production Four production Three TOTAL months ended months ended seven months September 30, December 31, ended December 20161 2016 31, 2016 Operating Data Ore mined (tonnes) 61,040 72,561 133,601 Ore processed (tonnes) 82,590 61,265 143,855 Head g
Slide 34: 55 Zone Life of Mine Design
55 Zone Life of Mine Design LOM Plan April 2017 Mined Out 2016 ▪ Resource model 5168 L December 2016 5066 DD Drive DD Drives & Vent Intakes ▪ Proven & Probable DD Drives & Vent Intakes reserve updated to 4556L (760m) Single Decline, SingleExhaust Decline, Raise & Escape Ladderway ▪ Inferred material
Slide 35: Mineral Reserve and Mineral Resource Statement – 55 Zone
Mineral Reserve and Mineral Resource Statement – 55 Zone* As of December 31, 2016 Reserve grade largely maintained compared to BFS grade despite mined grade over the course of 2016 of 15.5 g/t. Proven Probable Proven and Probable Mineral Reserves Mineral Reserves Mineral Reserves Tonnes Grade Ounces
Slide 36: Mineral Resource Statement - Bagassi South
Mineral Resource Statement - Bagassi South* As of July 19, 2017 Measured Indicated Measured and Indicated Inferred Mineral Resources Mineral Resources Mineral Resources Mineral Resources Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces (000) g/t Au (000) (000) g/t Au (
Slide 37: 55 Zone Mineral Resource and Reserve Notes
55 Zone Mineral Resource Notes Notes: 1. Mineral Resources are reported compliance with National Instrument 43-101 (“NI 43-101”) with an effective date of December 31st, 2016. 2. Underground Mineral Resources are reported at gold grade cut-off of 5.0 g/t Au, based on a gold price of US$1,250/ounce.
Slide 38: Bagassi South Mineral Resource and Reserve Estimate Notes
Bagassi South Mineral Resource Estimate Notes: Notes: 1. Bagassi South Mineral Resources are reported in compliance with NI 43-101 with an effective date of July 19th, 2017. 2. Underground Mineral Resources are reported at gold grade cut-off of 5.0 g/t Au, based on a gold price of US$1,250/ounce of
Slide 39: Investor Relations Contact
Kelley Stamm Manager, Investor Relations & Communications 360 Bay Street, Suite 500 Toronto, ON M5H 2V6 kstamm@roxgold.com www.roxgold.com 416 203 6401 TSX: ROXG 39