  1. Slide 1: Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Delivering Growth and Shareholder Returns 10 November 2017 VEDANTA RESOURCES PLC – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  2. Slide 2: Cautionary Statement and Disclaimer

    Cautionary Statement and Disclaimer The views expressed here may contain information derived from publicly available sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness, reasonableness or reliability of this information. Any forwa

  3. Slide 3: Contents & Agenda

    Contents & Agenda Time Section Presenter Page 1050hrs Oil & Gas Sudhir Mathur, CEO - Oil & Gas 4 1105hrs Oil & Gas Q&A 15 1120hrs Zinc International Deshnee Naidoo, CEO – Zinc International 16 1135hrs Zinc India Sunil Duggal, CEO - Zinc India 25 1150hrs Zinc Q&A 34 1230hrs Lunch VEDANTA RESOURCES PL

  4. Slide 4: Oil & Gas

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Oil & Gas Sudhir Mathur – CEO, Oil & Gas 10 November 2017 VEDANTA RESOURCES PLC – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  5. Slide 5: Vision: Oil & Gas Business

    Vision: Oil & Gas Business  Contribute to 50% of India’s domestic crude oil production with volumes of 500kboepd and reserves of over 3bn barrels of oil equivalent  Operate diversified and sustainable portfolio  Deliver long-term value to Shareholders, Governments and Local Communities Key Levers

  6. Slide 6: Significant Policy Changes to Unlock India's Hydrocarbon Potential

    Significant Policy Changes to Unlock India’s Hydrocarbon Potential Untapped opportunity Positive policy measures  Over 80bn boe of ‘in place resources’  Hydrocarbon Exploration and Licensing Policy (HELP)  ~50% of the sedimentary basins to be appraised  Open Acreage Licensing Policy (OALP)  Onl

  7. Slide 7: Cairn Oil & Gas: Extremely Well Positioned for the India Opportunity

    Cairn Oil & Gas: Extremely Well Positioned for the India Opportunity Assets: Diverse and Prolific geological basins World Class Resource Base (as on Mar 17)  7 blocks with net acreage of ~35,000km2  Hydrocarbon Initially in Place of 7.5bn boe  3 core producing blocks - 1 onshore, 2 offshore  2P1

  8. Slide 8: Actively Pursuing Opportunities Under the New Open Acreage Licensing Policy

    Actively Pursuing Opportunities Under the New Open Acreage Licensing Policy India: Geology and Potential  Only 7 of 26 basins under commercial production  Discovered Reserves: 28 billion boe of Ultimate Reserves  Over 80 billion boe of ‘in place resources’  Potential in remaining 19 basins yet t

  9. Slide 9: Rejuvenated Exploration to add Over 700mmboe of Contingent Resources

    Rejuvenated Exploration to add Over 700mmboe of Contingent Resources Barmer Basin: Singular access to the prolific Basin spread over 3,000 sq. km. with established discoveries 1 Akli Rajasthan (Barmer Basin)  Basin provides access to multiple play types Thumbli: with 2 Tukaram, Raageshwari Oil, Gud

  10. Slide 10: Rejuvenated Exploration to add Over 700mmboe of Contingent Resources (cont'd)

    Rejuvenated Exploration to add Over 700mmboe of Contingent Resources (cont’d) Offshore Basin: Our efforts are centred around the prolific Krishna Godavari basin KG-OSN-2009/3 (KG Offshore) Ravva  Aim to establish 300mmboe of Contingent  Aim to establish 100 mmboe of Contingent Resources Resources

  11. Slide 11: $1bn Capex Initiated to Deliver 300 kboepd at $5 per boe

    $1bn Capex Initiated to Deliver 300 kboepd at $5 per boe Enhanced Execution Strategy Gross production Net capex (kboepd) ($mn)  Fundamental shift to ‘Integrated Project Development’ with in-built risk and reward mechanism to drive 275-300 300 300 incremental value from project schedule and recoveri

  12. Slide 12: Cairn Oil & Gas: One of Lowest Operating Costs Globally

    Cairn Oil & Gas: One of Lowest Operating Costs Globally  Consistent reduction in waterflood operating cost Rajasthan costs ($/boe) since FY15 driven by scope optimization, process Waterflood Polymer & Power 6.5 6.2 efficiencies and contract optimization 5.8 1.3 3.9 1.9  RJ waterflood operating cos

  13. Slide 13: Technology and Digitalization Enabling Business

    Technology and Digitalization Enabling Business  Implementation of EOR techniques  Multi stage fracking to improve well  World’s largest polymer flood in productivity and improve EUR Mangala  Enhanced well productivity through frac  Successfully tested ASP flood process design in the Mangala fi

  14. Slide 14: Summary

    Summary  Exploration program recommenced to add to the prospective and contingent resources with a focus on Onshore Barmer Basin, Offshore Basins and OALP rounds  Development Projects execution in progress with a gross investment of $1bn for incremental volumes of ~ 100 kboepd in the next 2-3 year

  15. Slide 15: Q & A Oil & Gas

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Q&A Oil & Gas 10 November 2017 VEDANTA RESOURCES PLC – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  16. Slide 16: Zinc International

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Zinc International Deshnee Naidoo – CEO, Zinc International 10 November 2017 VEDANTA – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  17. Slide 17: Gamsberg Video

    Gamsberg Video https://www.youtube.com/watch?v=-tcsgJpTIHk&feature=youtu.be VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY 17

  18. Slide 18: Zinc International Overview

    Zinc International Overview Established track record… …..Enabling key focus areas for growth Improved safety performance 1 Drive ‘best in class’ HSE Fundamental changes to operating philosophies 2 Develop quality project pipeline Delivered LoM extensions of all assets Achieve 1st quartile costs thro

  19. Slide 19: Zinc International Locality

    Zinc International Locality Vision is to be the safest, socially responsible 1mtpa integrated Zn producer; in the Q1 median of the global cost curve Skorpion Zinc (100% VEDL)  Open pit zinc mine and refinery  Largest integrated zinc operation in Windhoek Africa Botswana  LoM of 4 years Namibia 

  20. Slide 20: Gamsberg – Anchor for Zinc International Growth

    Gamsberg – Anchor for Zinc International Growth Mid CY 2018 Phase 1 – 250ktpa Time to Total Medium term Phase 2 – 200ktpa operation 600ktpa Long term Phase 3 – 150ktpa Gamsberg Project (Phase 1) Gamsberg U/G (Phase 3) Gamsberg North Gamsberg East U/G  Current project (open-pit mine, Resource Resour

  21. Slide 21: Gamsberg Project Progress – Site Activities in Full Swing

    Gamsberg Project Progress – Site Activities in Full Swing North pit Thickener pre-assembly test Transformer installed on site Plant civil footprint Mill shell on site Jaw Crusher Delivered to Site Tailings dam Mining (>50% Pre-strip Plant and Infra (~55% Tailings Facility & Digitalisation work compl

  22. Slide 22: BMM Operations Step Up & Growth Opportunity

    BMM Operations Step Up & Growth Opportunity BMM Operational Performance is Trending Positively… ..and can be Further Enhanced with Swartberg Phase 2 Production per year, Metal (Zn & Pb) in concentrate kt Swartberg Deeps Feed grade % Mined out area to 260m 120 >100 7,20 Includes Swartberg 110 7,00 de

  23. Slide 23: Skorpion Zinc's Increased LOM Certainty & U/G Potential

    Skorpion Zinc’s Increased LOM Certainty & U/G Potential The delivery of Pit 112 has created more certainty around SZ…. …With further potential at Pit 112 and the planned refinery conversion Production per year, Zn metal South North  Currently mined Skorpion orebody kt Current production Ex-pit grad

  24. Slide 24: ZI Outlook

    ZI Outlook FY18 FY19 FY20 Indicative Prod (kt) 150-160 240-260 410-430 Consolidated Outlook COP ($/t) <1,500 <1,200 <1,100 Project on track and progressing as per plan Gamsberg  First production by mid CY2018 and on budget for capex target of $400mn 250kt Production@  FY19 production expected to b

  25. Slide 25: Zinc India

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Zinc India Sunil Duggal – CEO, Zinc India 10 November 2017 VEDANTA – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  26. Slide 26: Zinc Market Overview

    Zinc Market Overview Supply Shortage Leading to Multi-year low spot TCs Declining stocks at LME & SHFE warehouses $/tonne mn tonne $/tonne 1.40 4,000 400 1.20 3,500 350 300 3,000 Spot TCs dipped 1.00 250 to $25/mt in 2,500 0.80 Oct’17 200 2,000 0.60 150 1,500 100 0.40 1,000 50 0.20 500 0 0.00 0 Oct

  27. Slide 27: Hindustan Zinc - A Sustainable Enterprise

    Hindustan Zinc - A Sustainable Enterprise 2nd largest zinc-lead miner globally; Core Strengths 4th largest zinc-lead smelter globally Mines with R&R base of 404.4 million On track for 1.2 million tonnes of MIC capacity by 2020; 1 tonnes; Mine life of 25+ years UG mines ramping up at 5 year CAGR of 3

  28. Slide 28: Portfolio of Tier-1 Assets

    Portfolio of Tier-1 Assets Rampura Agucha Mine Reserves 49.7mn tonne Resources 50.3mn tonne Chanderiya Smelting Complex Reserve Grade Zn 13.9%, Pb 1.9% Pyrometallurgical Lead Zinc Smelter Current Ore Capacity 6.15mtpa Pantnagar & Haridwar 105,000tpa zinc and 35,000 tpa lead Processing and refining o

  29. Slide 29: Strong Track Record of Growth

    Strong Track Record of Growth Reserves & Resources (mn tonne) – 2.5X Growth Mined Metal (‘000 tonne) – 3X Growth 404 880 887 889 907 390 840 870 365 375 830 348 769 332 735 106 110 113 145 151 313 88 92 299 272 629 86 572 84 232 532 210 295 78 261 267 283 67 178 223 239 409 60 165 197 216 364 146 18

  30. Slide 30: Mine Expansion Project Overview

    Mine Expansion Project Overview Mine expansions in sync with increasing R&R Maintaining First Quartile of Global Cost Curve  Five major projects to increase MIC capacity to 1.2mtpa (17.5mtpa  Continue to be in first quartile of global cost curve ore capacity), including RAM OC replacement  CoP he

  31. Slide 31: Silver Portfolio – Realising Potential of 1,000t

    Silver Portfolio – Realising Potential of 1,000t Silver Production 452 500+ 1,000 Ramp up FY2017 FY2018 2021 Ore to Metal Recovery (FY2017) Achieving 1,000 tonnes Key Focus Areas ORE CONCENTRATE METAL Mining Lead/Bulk Lead (452  850) Concentrates Smelting  Focus on silver-rich deposits  470 tonne

  32. Slide 32: Resource Driven Growth

    Resource Driven Growth Sustained Commitment to Exploration → Strong Track Record of R&R Addition 10 Year R&R Trend mn tonne 450 40 36.1 36.1  R&R 404mn tonne in FY2017 34.7 35 35.2 35.3 400 34.1 34.1 35 31.5  R&R estimation to the JORC 350 standard and audited by 30 27.5 international consultants

  33. Slide 33: Way Forward

    Way Forward 1.5mtpa Shaft and decline integration capacity Multi-level mining under Digital transformation to boost productivity planning New prospects & tenements 25+ years of mining R&R with potential of 1.2mtpa 1.2mtpa capacity Transition to underground mining progressing smoothly by FY2020 Shaft

  34. Slide 34: Q & A Zinc

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Q&A Zinc 10 November 2017 VEDANTA RESOURCES PLC – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  35. Slide 35: Capital Allocation Framework: Focus on Shareholder Returns

    Capital Allocation Framework: Focus on Shareholder Returns World class assets and operational excellence to deliver strong and sustainable cash flows Production growth and asset optimization Strong Maintain Grow Shareholder Returns Strong Balance Sheet Existing Businesses VEDANTA RESOURCES PLC – FY2

  36. Slide 36: Appendix

    Vedanta Resources Plc FY2018 Interim Results and Capital Markets Day Appendix VEDANTA RESOURCES PLC – ZINC–LEAD–SILVER | OIL & GAS | ALUMINIUM | COPPER | IRON ORE | POWER VEDANTA RESOURCES PLC – FY2018 INTERIM RESULTS AND CAPITAL MARKETS DAY

  37. Slide 37: Southern African Zinc Cluster: Unrivalled Opportunity for Long-Term LOM & Organic Growth

    Southern African Zinc Cluster: Unrivalled Opportunity for Long-Term LOM & Organic Growth Southern Namibia Cluster VZI R&R Movement Since Acquisition High value Resource Depletion Resources Reserves Base to enable long LOM 400 and expansions 26mt R&R @ 10.6% Zn+Pb 350  Total of 21.5mt of Metal in R&

Vedanta Resources — Investor Day (November 2017) on 6ix