Origin Energy Limited · ASX:ORG

Origin Energy — Corporate Update (July 2011)

19 slides from Origin Energy's corporate update, Jul 28, 2011

  1. Slide 1: Facsimile to ASX Company Announcements Office

    To Company Announceme A nts Office Facsimile 1 1300 135 638 8 For personal use only Company ASX Limited Date 2 28 July 2011 From Helen Hard dy Pages 1 19 Subject AUSTRALIA A PACIFIC LN NG: FINAL IN NVESTMENT DECISION Please find d attached a presentatio on to be mad de to investo ors and media today

  2. Slide 2: Australia Pacific LNG: Final Investment Decision

    For personal use only Australia Pacific LNG: Final Investment Decision First Phase CSG to LNG Project 28 July 2011

  3. Slide 3: Important Notice

    Important Notice This presentation does not constitute investment advice, or an inducement or recommendation to acquire or dispose of any securities in Origin, in any jurisdiction (including the USA). This presentation is for information purposes only, is in a summary form, and does not purport to b

  4. Slide 4: APLNG has approved a Final Investment Decision on the first phase

    APLNG has approved a Final Investment Decision on the first phase of its CSG to LNG project … For personal use only  Monetises large domestic gas reserves through international oil-linked energy prices  Leverages strong growth in Asian energy markets  Initiates development of first LNG train and

  5. Slide 5: Joint venture agreed to develop a 9 mtpa, US$20 billion CSG to LNG project

    The joint venture has agreed to commence the development of a 9 mtpa, US$20 billion CSG to LNG project … PROJECT OVERVIEW For personal use only Description: • CSG to LNG project based on Australia’s largest 2P CSG reserves base Size: • Two trains, each with a nominal production capacity of 4.5 mtpa

  6. Slide 6: Joint venture has successfully reached this milestone

    The joint venture has successfully reached this milestone following a methodical and considered approach For personal use only Timing Completed Milestones (Cal Yr) Compelling Project Benefits • Leverages strong growth in Asian energy  Origin and ConocoPhillips form APLNG JV Q4 2008 markets  Initia

  7. Slide 7: APLNG is well placed to execute all components of the project

    APLNG is well placed to successfully execute all components of the project For personal use only  Strong and aligned joint venture  Australia’s largest 2P CSG reserves base  Australia’s largest, and world’s largest CSG operators  ConocoPhillips owner of Optimised Cascade® Process  ConocoPhillip

  8. Slide 8: Strong, aligned joint venture: Origin, ConocoPhillips and Sinopec

    APLNG is underpinned by a strong, aligned joint venture that combines Origin’s leading position in Australian CSG development and ConocoPhillips’ extensive LNG and CSG capabilities … For personal use only • Australia’s largest integrated • Integrated energy company • Integrated energy and chemical c

  9. Slide 9: Sufficient gas to underpin two trains, with 3P reserves of 14,742 PJ

    APLNG has sufficient gas to underpin two trains, with 3P reserves of 14,742 PJ and an additional 10,050 PJ of contingent resources … For personal use only APLNG Reserves and Resources Upstream Gas Production Costs Upstream Production Costs Train 1 Train 2 3C = 10,050 Lower unit 2C = 4,041 Ramp and T

  10. Slide 10: Australia's longest history of CSG exploration and production

    With Australia’s longest history of CSG exploration and production … For personal use only • Leverages Origin’s 14 years’ CSG production experience • High value and high productivity fields prioritised for ramp-up period • Key upstream contracts include: - Supply and operation of drilling rigs - Ups

  11. Slide 11: Downstream facility uses ConocoPhillips Optimised Cascade Process

    The downstream facility will utilise ConocoPhillips’ proprietary Optimised Cascade® Process LNG technology … For personal use only • Bechtel, as part of their Global LNG Collaboration with ConocoPhillips, will be EPC contractor for the downstream program • The project will utilise ConocoPhillips’ Op

  12. Slide 12: Commitment to local communities and the environment

    APLNG continues its commitment to local communities and the environment to operate sustainably … For personal use only Supporting the Community • Social Impact Management Plan to identify community needs and direct investment • Boosting local skills via apprenticeships, scholarships and training • R

  13. Slide 13: Asian LNG markets are robust, with opportunities for long term contracting

    Asian LNG markets are robust, with opportunities for long term contracting For personal use only Asian LNG Supply and Demand LNG Contracts by project and buyer Mtpa mmtpa Tokyo Gas Pluto 1 160 Kansai Electric Gorgon Osaka Gas PNG LNG TEPCO 140 QCLNG Chubu Electric Uncontracted LNG Supply1 120 GLNG K

  14. Slide 14: Estimated capital costs for a 2-train project are US$20 billion

    Estimated capital costs for a 2-train project are US$20 billion from FID until start-up of the second train … For personal use only • Full 2-Train development: • US$20 billion, including US$2.5 billion of contingencies • First phase development (one train and infrastructure to support a second train

  15. Slide 15: Appropriate controls and risk mitigation plans are in place

    Appropriate controls and risk mitigation plans are in place … For personal use only Strong Management and •• Industry leaders engaged for all key contracts and services of the project Broad resourcing channels to obtain quality people with specialised skills Quality Teams • Integration and interfaci

  16. Slide 16: Origin will fund its share of project costs using existing and new facilities

    Origin will contribute to its share of project costs using a range of existing and new funding facilities … For personal use only • Initial funding requirement will be reduced by Sinopec’s gross contribution of $US1.8 billion for its 15% interest in APLNG (net US$1.5 billion benefit to ConocoPhillip

  17. Slide 17: Cash and committed undrawn facilities of $3.6 billion as at 30 June 2011

    Origin had cash and committed undrawn facilities of $3.6 billion1 as at 30 June 2011 … For personal use only Origin Debt and Bank Guarantee Maturity Profile as at 30 June 2011 • $2.3 billion was raised 2,500 through equity markets via a 1 for 5 pro rata renounceable 2,000 institutional and retail en

  18. Slide 18: FID will deliver significant value to Origin shareholders

    A final investment decision on the APLNG project will deliver significant value to Origin shareholders, underpinned by robust economics … For personal use only  Commercialisation of Australia’s largest 2P CSG reserves through international oil-linked energy prices  Leverages strong growth in Asian

  19. Slide 19: Thank you

    For personal use only Thank you Further Information Angus Guthrie Group Manager, Investor Relations Email: angus.guthrie@originenergy.com.au Office: +61 2 8345 5558 Mobile: + 61 417 864 255 Website www.originenergy.com.au 18 |

Origin Energy — Corporate Update (July 2011) on 6ix