Aboitiz Power — FY2020 Earnings Presentation

28 slides from Aboitiz Power's earnings presentation, Mar 10, 2021

  1. Slide 1: 2020 Full Year Results

    2020 Full Year Results 10 March 2021

  2. Slide 2: Advancing Despite Adversity through #PositiveEnergy

    Advancing Despite Adversity through #PositiveEnergy

  3. Slide 3: FY2020 Beneficial EBITDA Quarterly Breakdown

    Quarterly Breakdown FY2020 Beneficial EBITDA in PHP millions +19% vs 3Q2020 1% vs FY2019 *+39% vs 4Q2019 +5% Flat vs LY: -9% ● +10% higher availability ● +2% other income ● -7% lower demand due to COVID-19 ● -3% lower BCQ rates ● -1% lower water inflow 3

  4. Slide 4: FY2020 Core Income

    FY2020 Core Income EBITDA Net Interest Depcn. & Amort. Tax & Others Core Income Expense Php mn FY2019 FY2020 Change EBITDA 43,032 43452, 1% Less: Net Interest Expense 12,950 : 69 Depcn. & Amort. 10,051 Tax & Others 3,410 Core Income 16,621 Qo AboitizPower EPS 2.26 1.70 4

  5. Slide 5: FY2020 Net Income

    FY2020 Net Income Qo AboitizPower Php mn Core Income Net Income EPS Core Income Net Income FY2019 FY2020 Shanes 16,621 | 12,532 5% 17,323 oa a 272 2.35

  6. Slide 6: Balance Sheet Highlights

    Balance Sheet Highlights *Total Interest Bearing Debt / Total Equity 6

  7. Slide 7: Operating Highlights: Capacity Sales

    Operating Highlights: Capacity Sales Capacity Sales in MW 7% 7

  8. Slide 8: Operating Highlights: Revenue and Energy Sold

    Operating Highlights: Revenue and Energy Sold Revenue Energy Sold in PHP millions in GWh -1% -12% 8

  9. Slide 9: Operating Highlights: Gross Margin

    Operating Highlights: Gross Margin Quarterly Breakdown in PHP millions in PHP millions -12% +15% -23% +3% -21% in GWh -1% -3% in GWh 23% -2% 9

  10. Slide 10: Operating Highlights: Selling Prices (P/kWh)

    Operating Highlights: Selling Prices (P/kWh) -8% -48% Ave NEWC $83.78/MT in FY2019 vs $59.80/MT in FY2020 10

  11. Slide 11: Operating Highlights: Availability - FY2020

    Operating Highlights: Availability - FY2020 Higher than 82% in FY 2019 NERC – North American Electric Reliability Corporation 11

  12. Slide 12: Operating Highlights: WESM

    Operating Highlights: WESM Q2 Ave LWAP P7.23 (P/kWh) FY2019 Q4 Ave LWAP Ave P5.01 (P/kWh) LWAP Q1 Ave LWAP P4.43 (P/kWh) P4.95 Q3 Ave LWAP (P/kWh) P3.15 (P/kWh) Q2 Ave LWAP P2.17 (P/kWh) FY2020 Ave Q1 Ave LWAP LWAP P2.94 (P/kWh) P2.40 Q3 Ave LWAP Q4 Ave LWAP P2.54 (P/kWh) P1.93 (P/kWh) (P/kWh) 12

  13. Slide 13: Luzon and Visayas Average Weekly Peak Demand

    LUZON AND VISAYAS AVERAGE WEEKLY PEAK DEMAND Dec W4 0% Apr W1 -26% 2020 Ave. LuzVis Weekly Peak Demand 2019 Ave. LuzVis Weekly Peak Demand % Δ vs 2019 Luzon Weekly Peak Demand Visayas Weekly Peak Demand Beginning of ECQ Holy Week Independence Day Source: IEMOP Market Reports 13 13

  14. Slide 14: Operating Highlights: Water Level

    Operating Highlights: Water Level 14

  15. Slide 15: Operating Highlights: Distribution

    Operating Highlights: Distribution -8% Beneficial Power Sales in GWh Customer Type Peak Demand in GWh in MW -8% -15% 11% 15

  16. Slide 16: Operating Highlights: Distribution

    Operating Highlights: Distribution Gross Margin / kWh Feeder Loss 16

  17. Slide 17: Project Update

    Project Update Grid Project Capacity (Net) % Ownership Attributable Net Estimated Sellable Capacity Commercial Operation Date Luzon Dinginin Unit 1 (Coal – GNPD) 668 MW 70% 468 MW Q2 2021 Dinginin Unit 2 (Coal – GNPD) 668 MW 70% 468 MW Q4 2021 SNAP Magat Floating Solar 150 MW 50% 75 MW Ongoing devel

  18. Slide 18: GNPower Dinginin

    GNPower Dinginin 2 x 668 MW of Coal Power Plant View From Jetty 18 Unit 1 Synchronization Unit 1 Steam Turbine Generator

  19. Slide 19: TMI Hybrid Battery Energy Storage System

    TMI Hybrid Battery Energy Storage System (BESS) 49 MW 19

  20. Slide 20: SNAP Magat Battery Energy Storage System (BESS) 20 MW

    SNAP Magat Battery Energy Storage System (BESS) 20 MW 20

  21. Slide 21: Floating Solar

    Floating Solar 150 MW of Solar of Power 21

  22. Slide 22: MakBan and Tiwi Capacity Optimization Projects

    First Make-UP Well in Tiwi Make-UP Well MakBan Drilling Rig in Operation Drilling Sites in MakBan MakBan and Tiwi Capacity Optimization Projects 64 MW 22

  23. Slide 23: Southline Transmission Line Interconnection

    Includes 100% of Subsidiaries and Affiliates 1 - Budgeted Figure 2 - Actual Figure Southline Transmission Line Interconnection 23

  24. Slide 24: Capital expenditures (with partners)

    Capital expenditures (with partners) Includes 100% of Subsidiaries and Affiliates 1 - Budgeted Figure 2 - Actual Figure 24

  25. Slide 25: Dividend Payment

    Dividend Payment Payout Ratio: 1/2 of previous year’s consolidated net income 2021 Dividend Yield: Computed based on March 05, 2021 closing price 25

  26. Slide 26: AP ESG Assessment Ratings

    AP ESG Assessment Ratings Score Reference 2018 2019 2020 0 (lowest) - 100 (highest) SAM (S&P Global) The higher the better. 10 23 40 ↑ 1 (lowest) - 5 (highest) FTSE Russell The higher the better. -- 2.6 2.5 ↓ 0 (negligible) - 40+ (severe) Sustainalytics The lower the better. -- 37.3 34.1 ↑ CCC (lowe

  27. Slide 27: A Better Future with Cleanergy

    A Better Future with Cleanergy

  28. Slide 28: AboitizPower

    20 AboitizPower