Slide 1: South Flank
South Flank Steve Campbell General Manager South Flank 4 October 2022
Slide 2: Disclaimer
Disclaimer Forward-looking statements This presentation contains forward-looking statements, including: statements regarding our strategy, our values and how we define success; our expectations of a competitive advantage for our business or certain products; our commitment to generating social value
Slide 3: Acknowledgement of Country
Acknowledgement of Country Banjima Country South Flank
Slide 4: The world’s largest iron ore hub
The world’s largest iron ore hub Large, long-life, low-cost, expandable Project US$3.6 billion investment, delivered on time and Mining Area C excellence budget during global pandemic OHP3&4 Packsaddle OHP1&2 TLO1&2 PC1 PC2 145 Mtpa Hub 80 Mtpa South Flank operation, expanding overall Large You Mini
Slide 5: Inclusion and diversity embedded from the start
Inclusion and diversity embedded from the start South Flank presented a unique opportunity to shape a workforce reflective of the communities in which we operate • South Flank has been conceived as a truly diverse Female participation (% of workforce who identify as female) mining operation • How we
Slide 6: Partnering with our Indigenous stakeholders
Partnering with our Indigenous stakeholders Our success is underpinned by ongoing and sustainable collaboration with Banjima Traditional Owners Consultation • Relationships built over 20+ years with regular consultation through routine meetings, South Flank opening: and collaboration with Banjima Na
Slide 7: Excellence in project delivery
Excellence in project delivery Fastest ramp up for a WAIO development; payback achieved within 18 months Delivery Ramp-up Performance • New Integrated Project Team (IPT) approach • Achieved 75% nameplate capacity ahead of • Excellent safety outcome during execution where construction teams are integ
Slide 8: Modular approach to fabrication and maintenance
Modular approach to fabrication and maintenance Excellence by design: built to enable improved safety and shut down efficiencies • Project execution strategy sought to reduce risk (exposure hours and physical) associated with steelwork erection, without compromising quality, cost or productivity – m
Slide 9: Designed with the future in mind
Designed with the future in mind South Flank was delivered automation ready and all fleet is able to run in an autonomous environment Automation-ready mine design Autonomous blast hole drills Ability to remotely control aspects of enabling fast deployment of deployed from day 1 daily operations from
Slide 10: South Flank is at the heart of a large, high-quality resource
South Flank is at the heart of a large, high-quality resource Centralised 145 Mtpa Mining Area C (MAC) hub unlocks value • ~35% of WAIO’s total Mineral Resource is located within close proximity to the expanded MAC and South Flank hub Tandanya 11.7 km MAC Hub – all potential future sustaining mines
Slide 11: What you will be seeing today…
What you will be seeing today… A world class mining operation Mobile Equipment Maintenance Overland Conveyor System Vista pit (autonomous fleet) Ore Handling Plant 3 workshop Western Australia Iron Ore site tour 4 October 2022 11
Slide 12: Slide 12
Slide 13: Footnotes
Footnotes 1. Slide 4: The increased lump and grade estimates subsequent to the ramp up of South Flank excludes Yandi, which is expected to provide supply chain flexibility for several years. 2. Slide 5: Source: The Chamber of Minerals and Energy of WA (CME), Diversity in the Western Australian Resou