Trilogy Metals Inc. · TSX:TMQ

Trilogy Metals — Investor Presentation (September 2023)

46 slides from Trilogy Metals's investor presentation, September 2023

  1. Slide 1: Corporate Presentation | September 2023

    TSX TMQ | NYSE TMQ HIGH GRADE SAFE JURISDICTION SOLID PARTNERS Corporate Presentation | September 2023

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS This presentation includes certain "forward-looking information” and "forward-looking statements” (collectively "forward-looking statements”) within the meaning of applicable Canadian and United States securities legislation including the United States Private Securities L

  3. Slide 3: Technical Information and Cautionary Statements

    TECHNICAL INFORMATION AND CAUTIONARY STATEMENTS TECHNICAL REPORT AND QUALIFIED PERSONS The document referenced below provide supporting technical information for the Arctic project referenced throughout this presentation. Project Qualified Person(s) Most Recent Disclosure ARCTIC Kevin Murray, Ausenc

  4. Slide 4: Ambler Mining District

    AMBLER MINING DISTRICT1 COPPER ZINC GOLD SILVER billion pounds billion pounds million ounces million ounces ARCTIC 2.35 3.22 0.675 52.0 (INDICATED) ARCTIC 0.19 0.29 0.062 5.0 (INFERRED) BORNITE 6.51 (INFERRED) with Zinc and Precious Metals a Safe, Rule of Law Jurisdiction 50/50 Ambler Mining Distric

  5. Slide 5: Share Capitalization

    SHARE CAPITALIZATION Solid, Supportive Shareholder Base WELL FUNDED BALANCE SHEET TSX, NYSE | TMQ Cash ~US$4.2 Million1 Issued and Outstanding 155.3 M1 No Debt Options 13.0 M1 JV Cash ~US$72.8 Million Fully Diluted 172.0 M2 (TMQ’s Interest ~US$36.4 MAJOR SHAREHOLDERS3 Million) 1 Electrum Group ~21.0

  6. Slide 6: The Ambler Mining District Is More Than a High-Grade Copper District

    THE AMBLER MINING DISTRICT IS MORE THAN A HIGH-GRADE COPPER DISTRICT It is a Source of Essential Minerals Listed on the U.S. Critical Minerals List COBALT ZINC COPPER Used in electric motors, GERMANIUM batteries of electric Used in semiconductor vehicles Used in electric vehicle batteries chips Used

  7. Slide 7: Corporate Highlights – Partnerships

    CORPORATE HIGHLIGHTS – PARTNERSHIPS Strong Partnerships to Advance the Ambler Mining District in Alaska 1. Joint Venture 2. Local Native 3. Infrastructure Partnership Partnership Partnership with with South32 with NANA State of Alaska South32 contributed US$145 Agreement/Business AIDEA currently adv

  8. Slide 8: Joint Venture Partnership with South32

    JOINT VENTURE PARTNERSHIP with South32 South32 Limited Exercised its Option to Form a Joint Venture with Trilogy Ambler Metals LLC formation 50% ~$145 million 50% Upper Kobuk Mineral Projects South32 is a global diversified metals and $72.5 million of initially contributed cash is mining company wit

  9. Slide 9: Upper Kobuk Mineral Projects JV Area

    UPPER KOBUK MINERAL PROJECTS JV AREA Total Land Package of 190,929 Ha (471,796 Acres) TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 9

  10. Slide 10: Corporate Highlights – Partnerships

    CORPORATE HIGHLIGHTS – PARTNERSHIPS Strong Partnerships to Advance the Ambler Mining District in Alaska 1. Joint Venture 2. Local Native 3. Infrastructure Partnership Partnership Partnership with with South32 with NANA State of Alaska South32 contributed US$145 Agreement/Business AIDEA currently adv

  11. Slide 11: Ambler Mining District Strong Local Support for Mining

    AMBLER MINING DISTRICT Strong Local Support for Mining NANA has an established mining history in Northwest Alaska, with its partnership in the Red Dog Mine, one of world's largest producers of zinc Politically Stable Rule of Law Recognized Mineral Potential Resource Extractive Industries are the Lar

  12. Slide 12: Corporate Highlights – Partnerships

    CORPORATE HIGHLIGHTS – PARTNERSHIPS Strong Partnerships to Advance the Ambler Mining District in Alaska 1. Joint Venture 2. Local Native 3. Infrastructure Partnership Partnership Partnership with with South32 with NANA State of Alaska South32 contributed US$145 Agreement/Business Alaska Industrial D

  13. Slide 13: Transportation Plan

    TRANSPORTATION PLAN AIDEA Currently Advancing Road Access to Ambler Mining District Ambler Mining District 211 Truck Transfer Miles to Alaska Railroad Proposed Ambler 250 Miles Access Road Rail Transfer 345 to Miles Anchorage Port TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 13

  14. Slide 14: NEPA Road Permitting Process (EIS)

    NEPA ROAD PERMITTING PROCESS (EIS) Bureau of Land Management was the lead agency for road permitting AIDEA is the proponent Detailed engineering has commenced on the road $70M funding agreement for detailed engineering (50:50 split with Ambler Metals and AIDEA) TRUST | RESPECT | INTEGRITY TSX, NYSE

  15. Slide 15: Stakeholder Support for Ambler Access Road Project

    STAKEHOLDER SUPPORT FOR AMBLER ACCESS ROAD PROJECT The Ambler Access Road is supported by Upper Kobuk Region, the North Slope Borough and Northwest Arctic Borough, that have passed resolutions in favor of the road project. “ The Joint Record of Decision (JROD) and the processes it lays out ensure th

  16. Slide 16: Bi-Partisan Support for Ambler Access Road Project

    BI-PARTISAN SUPPORT FOR AMBLER ACCESS ROAD PROJECT Letters sent to letter to U.S. Interior Secretary Deb Haaland reiterating strong support for the Ambler Access Project “ This Congressionally-mandated access is essential to ensuring the economic stability of both Alaska and the nation. In Alaska al

  17. Slide 17: High-Grade String of Pearls

    HIGH-GRADE STRING OF PEARLS Ambler Mining District Hosts Deposits Rich in Copper, Zinc, Lead, Gold, Silver & Cobalt TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 17

  18. Slide 18: Reserves at the Arctic Project

    RESERVES AT THE ARCTIC PROJECT Probable Mineral Reserves PROBABLE1 MINERAL RESERVES Arctic 46,700,000 tonnes Resource @ ~3.7% Cu Eq. Outline Average Grades: 2.11% Cu 2.90% Zn 0.56% Pb 0.42 g/t Au 31.8 g/t Ag 1. See the Arctic Report (referenced on Slide 3) and the resource and reserve tables in Appe

  19. Slide 19: Arctic Project General Concept Plan

    ARCTIC PROJECT GENERAL CONCEPT PLAN Small Footprint Mine Site – Looking Northeast Conceptual drawing 1 km TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 19

  20. Slide 20: Arctic FS – Inputs & Economic Results

    ARCTIC FS – INPUTS & ECONOMIC RESULTS1 Spot Metal Prices Feasibility Inputs and Economic Results Base Case Metal Prices (September 1, 2023) Mine Life 13 Years 13 Years Mill Capacity 10,000 tpd 10,000 tpd Strip Ratio (Waste/Ore) 7.3:1 7.3:1 149M lbs Cu 149M lbs Cu 173M lbs Zn 173M lbs Zn Average Annu

  21. Slide 21: Arctic Producing Quality Concentrates

    ARCTIC PRODUCING QUALITY CONCENTRATES1 3 Separate High-Quality Concentrates COPPER CONCENTRATE ZINC CONCENTRATE • 92.1% recovery • 88.5% recovery • 30.33% concentrate grade • 53.73% concentrate grade • Cu payable 96.5% • Zn payable 85% • Ag 161 g/t (4.67 oz); Ag payable 90% • No significant penalty

  22. Slide 22: Arctic Boasts Robust Economic Metrics

    ARCTIC BOASTS ROBUST ECONOMIC METRICS Profitability Index, After-Tax IRR and After-Tax NPV Benchmarking ARCTIC (Trilogy Metals)(3) Chart by Data source: Wood Mackenzie, RBC database and company disclosure. Note: Project metrics shown on 100% basis. 1. Profitability index calculated as after-tax NPV

  23. Slide 23: Arctic: Evolution of Basket Price

    ARCTIC: EVOLUTION OF BASKET PRICE Arctic Revenue Per Tonne of Probable Reserves (US$/t ore)1 $400.00 $360.00 $320.00 Copper Zinc Lead Gold Silver $280.00 $240.00 $200.00 $160.00 $120.00 $80.00 Mine Site Cash Cost $40.00 $0.00 1. Based on Arctic Mineral Reserves with an effective date of November 15,

  24. Slide 24: No Federal Lands – Easier to Permit

    NO FEDERAL LANDS – EASIER TO PERMIT Requires Federal, State and Borough Approvals ▶ 404 Wetlands Permit from the ▶ All other significant permits issued by the State of Alaska: US Army Corps of Engineers Mine Operating Permit Dam Operating Permit is the only significant Federal Air Quality Permit Wat

  25. Slide 25: NEPA Mine Permitting Process (EIS)

    NEPA MINE PERMITTING PROCESS (EIS) 24-30 MONTHS 13 YEARS Mine permitting expected as next step Army Corp of Engineers (USACE) is expected to be the lead agency TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 25

  26. Slide 26: Comparison of the Ambler VMS Belt with Other Known Belts

    COMPARISON OF THE AMBLER VMS BELT WITH OTHER KNOWN BELTS Multi-Billion Pound Copper VMS Districts of the World 1 1 1 2 2 2 Dashed lines represent area of influence of proximal-scale alteration about each deposit 1. Source: Franklin et al., 2005, Volcanic-associated massive sulphides, Econ.Geol., Dat

  27. Slide 27: District Exploration: Pearls on a String

    DISTRICT EXPLORATION: PEARLS ON A STRING 1 1 1 2 1.See the Arctic Report & Bornite Report (referenced on Slide 3) and the resource and reserve tables in Appendix for additional information, including details with respect to grade, quantity and metal or mineral content. See also Technical Information

  28. Slide 28: Numerous Electromagnetic Anomalies

    NUMEROUS ELECTROMAGNETIC ANOMALIES TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 28

  29. Slide 29: Bornite

    BORNITE1 Testing Northern Extension 6.514 billion pounds of Inferred Copper 77 Million lbsResource Cobalt Mineral Resources for the Bornite Deposit (effective date, January 26, 2023) Cut-off Tonnes Average Grade Contained Metal Class Type/Area Cu (%) (Mt) Cu (%) Cu (Mlb) In-Pit 0.50 170.4 1.15 4,303

  30. Slide 30: Trilogy's Mineral Resources Compared to Its Peers

    TRILOGY’S MINERAL RESOURCES COMPARED TO ITS PEERS1 Chart by Measured & Indicated Resources (bn lb Cu Eq.) Inferred Resources (bn lb Cu Eq.) Resource Grade (% Cu Eq.) ARCTIC BORNITE 2 1. Peer group data as per company filings. Following long-term prices used to calculate Cu Eq - Au: US$1,650/oz, Ag:

  31. Slide 31: Upper Kobuk Mineral Projects – Relatively Underexplored

    UPPER KOBUK MINERAL PROJECTS – RELATIVELY UNDEREXPLORED 197,342 Meters Drilled Since 1957 TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 31

  32. Slide 32: Upcoming Catalysts

    UPCOMING CATALYSTS News Flow Optimization of Arctic engineering studies by Ambler Metals Commencement of permitting of Arctic Project TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 32

  33. Slide 33: Taikuu!

    TAIKUU! TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 33

  34. Slide 34: Appendix

    TRUST | RESPECT | INTEGRITY APPENDIX TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ

  35. Slide 35: Why Copper?

    WHY COPPER? Copper is critical to the global transition to clean energy 10 Mt SUPPLY SHORTFALL BY 2040 Source: Wood Mackenzie online article, March 23, 2021 TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 35

  36. Slide 36: Management Team

    MANAGEMENT TEAM CORPORATE EXPERIENCE BIO TONY GIARDINI ▪ Kinross Gold Former President of Ivanhoe Mines Ltd. from May 2019 to March 2020. Former ▪ Ivanhoe Mines Executive Vice President and Chief Financial Officer of Kinross Gold Corporation President, CEO and Director from December 2012 to April 20

  37. Slide 37: Board of Directors

    BOARD OF DIRECTORS CORPORATE EXPERIENCE BIO JANICE STAIRS ▪ Namibia Critical Over 30 years of experience working with companies involved in the resource sector Metals including positions held with Namibia Critical Metals Inc., Endeavour Mining Chair ▪ Endeavour Mining Corporation and Etruscan Resour

  38. Slide 38: Board of Directors (continued)

    BOARD OF DIRECTORS (continued) CORPORATE EXPERIENCE BIO GREGORY A. LANG ▪ NovaGold President and Chief Executive Officer of NOVAGOLD RESOURCES INC. Over 35 Resources years of diverse experience in mine operations, project development and Director ▪ Barrick Gold evaluations, including experience as P

  39. Slide 39: Ambler Mining District Industrial Access Project (AMDIAP)

    AMBLER MINING DISTRICT Industrial Access Project (AMDIAP) TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 39

  40. Slide 40: Ambler Mining District

    AMBLER MINING DISTRICT TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 40

  41. Slide 41: Ambler Access Road Project Timeline

    AMBLER ACCESS ROAD PROJECT TIMELINE JAN 2021 FEB 2021 FEB 2022 MAY 2022 SEPT 2022 NOV 2022 MAY 2023 AIDEA Ambler Metals United States DOI motion for USBLM published USBLM stated USBLM stated received right- entered into a Department of remand a Notice of Intent draft SEIS draft SEIS of-way for the D

  42. Slide 42: Port of Alaska - Anchorage

    PORT OF ALASKA - ANCHORAGE Concentrates Loaded Directly into Ship Hold Good for the Environment Saves Money Better Green Solution TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 42

  43. Slide 43: Mine Design Update by Wood Engineering

    MINE DESIGN UPDATE by WOOD ENGINEERING Topo Surface Section Talc Zone 2023 FS 2 2020 FS Section 1 See the Arctic Report (referenced on Slide 3) and the resource and reserve tables in Appendix for additional information, including details with respect to grade, quantity and metal or mineral content.

  44. Slide 44: Mineral Resource Summary Table as of November 30, 2022 under Regulation S-K 1300

    MINERAL RESOURCE SUMMARY TABLE AS OF NOVEMBER 30, 2022 UNDER REGULATION S-K 1300 Average Grade Contained Metal Content Project Resource Tonnage Cu Pb Zn Au Ag Cu Pb Zn Au Ag Alaska Category (Mt) (%) (%) (%) (g/t) (g/t) (Mlb) (Mlb) (Mlb) (koz) (Moz) Arctic – 50% Attributable Inferred 2.25 1.92 0.70 2

  45. Slide 45: Mineral Reserve Estimate as of November 30, 2022 for the Arctic Project

    MINERAL RESERVE ESTIMATE AS OF NOVEMBER 30, 2022 FOR THE ARCTIC PROJECT, ALASKA USA UNDER REGULATION S-K 1300 Tonnage Average Grade Classification Mt Cu (%) Pb (%) Zn (%) Au (g/t) Ag (g/t) Probable Mineral Reserves – 50% 23.35 2.11 0.56 2.90 0.42 31.8 Attributable Interest Notes: 1. Mineral Reserves

  46. Slide 46: NYSE American, TSX: TMQ www.trilogymetals.com

    TRUST | RESPECT | INTEGRITY Corporate Office Suite 1150 – 609 Granville Street Vancouver, British Columbia, V7Y 1G5 Canada Phone +1 (604) 638-8088 NYSE American, TSX: TMQ www.trilogymetals.com TRUST | RESPECT | INTEGRITY TSX, NYSE | TMQ 46