Tennessee Valley Authority · NYSE:TVC

Tennessee Valley Authority — Investor Presentation (January 2016)

106 slides from Tennessee Valley Authority's investor presentation, Jan 20, 2016

  1. Slide 1: Regional Energy Resource Council

    Slide 1: Regional Energy Resource Council

    Regional Energy Resource Council January 20-21, 2016 Memphis, Tennessee

  2. Slide 2: Regional Energy Resource Council | 2

    Slide 2: Regional Energy Resource Council | 2

    Regional Energy Resource Council | 2

  3. Slide 3: Term 2 RERC Members

    Slide 3: Term 2 RERC Members

    Term 2 RERC Members Lance Brown Wes Kelley Joe Satterfield Partnership for Affordable Clean Energy Columbia (TN) Power & Water Systems Blue Ridge Electric Members Cooperative (ret’d) Anne Davis Pedro Mago Southern Environmental Law Center Mississippi State University Jack Simmons Tennessee Valley Pu

  4. Slide 4: Safety Moment: Building Emergency Plan

    Slide 4: Safety Moment: Building Emergency Plan

    Safety Moment Building Emergency Plan Regional Energy Resource Council | 4

  5. Slide 5: Today's Meeting

    Slide 5: Today's Meeting

    TM Today’s Meeting

  6. Slide 6: Meeting Purpose

    Slide 6: Meeting Purpose

    Meeting Purpose • Welcome New Term and FACA/RERC Orientation • TVA Update and Policy Update • Information and Advice on Coal Combustion Residuals Impoundment Closure Alternatives • Public Input Listening Session • Field Trip: Tour Allen Fossil Plant/impoundments Regional Energy Resource Council | 6

  7. Slide 7: Agenda – January 20, 2016

    Slide 7: Agenda – January 20, 2016

    Agenda – January 20, 2016 10:00 Welcome and Introductions Dus Rogers, Chairman Joe Hoagland/ DFO Council Members Safety Moment Jo Anne Lavender, Facilitator 10:15 Meeting Purpose Hoagland 10:20 Overview of Agenda Lavender 10:25 FACA / RERC Orientation Kelly Love, OGC 10:30 RERC and TVA Update Hoagla

  8. Slide 8: Agenda – January 20, 2016 (cont'd)

    Slide 8: Agenda – January 20, 2016 (cont'd)

    Agenda – January 20, 2016 (cont’d) 1:10 Orientation – Coal Combustion Residuals (CCR) Scott Turnbow 1:45 Modeling Impoundment Closure Options: Bruce Hensel Electric Power Research Institute (EPRI) 2:30 Break 2:45 Overview: CCR Impoundment Closure Draft EIS Amy Henry 3:05 Preliminary Discussion Counc

  9. Slide 9: Agenda – January 21, 2016

    Slide 9: Agenda – January 21, 2016

    Agenda – January 21, 2016 7:30 Breakfast 8:30 Allen Fossil Plant Field Trip Council 11:30 Lunch 12:30 Welcome, Review of Day 1 Hoagland/ Lavender 12:45 CCR Impoundment Closure Draft EIS Henry 1:15 CCR Discussion and Advice to TVA Council / Lavender facilitate 2:15 Break 2:30 CCR Discussion and Advic

  10. Slide 10: The Federal Advisory Committee Act and the Regional Energy Resource Council

    Slide 10: The Federal Advisory Committee Act and the Regional Energy Resource Council

    The Federal Advisory Committee Act and The Regional Energy Resource Council FACA Briefing—Second Term Kelly Love, Attorney Office of General Counsel

  11. Slide 11: TVA's Regional Energy Resource Council

    Slide 11: TVA's Regional Energy Resource Council

    TVA’s Regional Energy Resource Council - Created by TVA “to provide advice on its energy resource activities and the priorities among competing objectives and values” - TVA’s energy resource activities include: > Constructing and operating various supply-side resources, including fossil- fueled powe

  12. Slide 12: Key Provisions of RERC Charter

    Slide 12: Key Provisions of RERC Charter

    Key Provisions of RERC Charter - Council provides advice only > Advice reported to the TVA Board’s External Relations Committee - Term of Council is two years > Second term expires July 31, 2017 - Approximately two meetings per year - Designated Federal Officer (DFO): Joe Hoagland, Vice President, S

  13. Slide 13: RERC Meeting Protocols

    Slide 13: RERC Meeting Protocols

    RERC Meeting Protocols  Agenda prepared and approved by the Designated Federal Officer (DFO) in Agenda consultation with Council Chair  Agenda distributed to Council and published in the Federal Register prior to each meeting  Topics may be submitted to the DFO by any member of the Council, or no

  14. Slide 14: DFO Briefing

    Slide 14: DFO Briefing

    DFO Briefing Joe Hoagland, Designated Federal Officer

  15. Slide 15: Term 1 RERC (2013-2015) Recap

    Slide 15: Term 1 RERC (2013-2015) Recap

    Term 1 RERC (2013-2015) Recap Topics Covered Common Themes  Introduction to TVA  Competitive Rates  TVA’s 2015 Integrated Resource Plan  Declining Demand — Strategies and Scenarios  Balanced Portfolio — Evaluation Criteria — Public Comments  Environmental Regulation  The Cost of Electricity 

  16. Slide 16: Term 1 RERC Advice

    Slide 16: Term 1 RERC Advice

    Term 1 RERC Advice ‘While never sacrificing reliability and ‘As the marketplace shifts to increasing load safety, the Council recognizes and endorses side resources and end use customer TVA’s focus on financial discipline, and interactions, collaboration between TVA, providing for affordable costs b

  17. Slide 17: Term 2 RERC (2015-2017) Preview

    Slide 17: Term 2 RERC (2015-2017) Preview

    Term 2 RERC (2015-2017) Preview Term 2 Proposed Topics • Environmental Regulations • Coal Combustion Residuals • Clean Power Plan • Distributed Energy Resources and the Evolving Utility Marketplace • Economic Development • Updates on various TVA Projects Regional Energy Resource Council | 17

  18. Slide 18: TVA Update

    Slide 18: TVA Update

    TVA Update • Renewables Program Update • Watts Bar Unit 2 • Recent water management and flood mitigation • Raccoon Mountain • eScore Regional Energy Resource Council | 18

  19. Slide 19: National Direction of Energy

    Slide 19: National Direction of Energy

    National Direction of Energy • Coal decreasing • 52% in 2000 down to 39% in 2013 • Increase of Natural gas and Renewables • Natural gas 16% in 2000, up to 27% in 2013 • Renewables 9% in 2000, up to 13% in 2013 Electricity generation by fuel Source: EIA, http://www.eia.gov/forecasts/aeo/pdf/0383(2015

  20. Slide 20: TVA's Capacity and Energy

    Slide 20: TVA's Capacity and Energy

    TVA’s Capacity and Energy Regional Energy Resource Council | 20

  21. Slide 21: TVA Future – Continued Cleaner Energy

    Slide 21: TVA Future – Continued Cleaner Energy

    TVA Future – Continued Cleaner Energy 120 110 100 Millions of Tons CO2 90 80 70 60 Forecast 50 40 1995 Calendar Year 2020 TVA is projected to reduce CO2 emissions 40% below 2005 levels by 2020 Regional Energy Resource Council | 21

  22. Slide 22: The Evolving Utility Paradigm

    Slide 22: The Evolving Utility Paradigm

    The Evolving Utility Paradigm Power System that is Highly Flexible, Resilient and Connected and Optimizes Energy Resources Regional Energy Resource Council | 22

  23. Slide 23: Break Time

    Slide 23: Break Time

    BREAK TIME

  24. Slide 24: Policy Update

    Slide 24: Policy Update

    Policy Update Brenda Brickhouse, Vice President Environment and Energy Policy

  25. Slide 25: Key expectations regarding environmental policy and requirements

    Slide 25: Key expectations regarding environmental policy and requirements

    Key expectations regarding environmental policy and requirements • Rulemaking activities expected to increase • Outgoing administration pushing measures through approval processes • States working to implement or adopt federal requirements. • Many environmental laws require periodic reviews • Expect

  26. Slide 26: Recent actions and planning implications

    Slide 26: Recent actions and planning implications

    Recent actions and planning implications • Recent actions • Air – Ozone Standard, Cross State Air Pollution Rule • Carbon – Clean Power Plan • Water – Cooling Water Intakes, Waters of the US, Effluent Limitation Guidelines • Waste – Coal Combustion Residuals • Key Fleet Planning Impacts: • Ozone Sta

  27. Slide 27: Clean Power Plan State Plan Decision Tree

    Slide 27: Clean Power Plan State Plan Decision Tree

    Clean Power Plan State Plan Decision Tree Regional Energy Resource Council | 27

  28. Slide 28: Observations on initial state Clean Power Plan decisions

    Slide 28: Observations on initial state Clean Power Plan decisions

    Observations on initial state Clean Power Plan decisions MASS (tons) RATE (lbs/MWh) Allocation Assumptions Critical Fewer assumptions in analyses Incremental nuclear not as big of Incremental nuclear provides large volumes compliance tool of Emission Reduction Credits New Natural Gas Plants do not s

  29. Slide 29: TVA and the Clean Power Plan

    Slide 29: TVA and the Clean Power Plan

    TVA and the Clean Power Plan State Plans enable tailoring compliance to our state/system realities • Political pressures could hamper compliance planning • Long range impacts still hard to quantify until state plans solidify Fair allocation of compliance burden or compliance credit • Applicable in K

  30. Slide 30: TVA Coal Combustion Residuals Management

    Slide 30: TVA Coal Combustion Residuals Management

    TVA Coal Combustion Residuals Management  TVA is continuing to modernize our ash management and convert to dry storage  EPA’s final “nonhazardous” waste rule governs ash ponds, landfills, groundwater monitoring, etc.  TVA’s program, including closing impoundments, facilitating compliance with the

  31. Slide 31: Questions?

    Slide 31: Questions?

    Questions? Regional Energy Resource Council | 31

  32. Slide 32: Break for Lunch

    Slide 32: Break for Lunch

    Break for Lunch

  33. Slide 33: Introduce Advice Topic

    Slide 33: Introduce Advice Topic

    Introduce Advice Topic Jo Anne Lavender

  34. Slide 34: RERC Advice Topic

    Slide 34: RERC Advice Topic

    RERC Advice Topic Coal Combustion Residuals (CCR) Impoundment Closure Alternatives • CCR Overview • EPRI: Modeling CCR Impoundment Closure Options • CCR Impoundment Closure Draft EIS • Allen Fossil Plant Tour Regional Energy Resource Council | 34

  35. Slide 35: RERC Advice Questions

    Slide 35: RERC Advice Questions

    RERC Advice Questions 1. What do you think about TVA seeking public comment on these closure alternatives including holding meetings in communities near coal‐fired plants? 2. TVA has evaluated multiple criteria (listed below) in the Draft EIS. Is there anything important that we missed? • Volume of

  36. Slide 36: Overview Coal Combustion Residuals

    Slide 36: Overview Coal Combustion Residuals

    Overview Coal Combustion Residuals Scott Turnbow, General Manager Strategy and Engineering Civil Projects & CCP Management

  37. Slide 37: CCR Overview

    Slide 37: CCR Overview

    CCR Overview • CCR Overview Regional Energy Resource Council | 37

  38. Slide 38: CCR Overview

    Slide 38: CCR Overview

    CCR Overview Wet Process Dry Process Regional Energy Resource Council 38

  39. Slide 39: CCR Overview

    Slide 39: CCR Overview

    CCR Overview 410 410 EXISTING GROUND 400 400 UPPER 390 390 CLAY DIKE 12’ 12’ UPPER 3’ Clay Cap CLAY DIKE 380’ (TYP.) 380’ (TYP.) Dry 380 380 2.5H:1V 2.5H:1V (TYP.) (TYP.) LOWER LOWER 15’ 370 ASH 370 CLAY CLAY DIKE DIKE FILL Storage 360 FILL RIP-RAP STABILITY BERM 360 350 350 NORMAL SUMMER POOL NORMA

  40. Slide 40: Initial Programmatic Approach

    Slide 40: Initial Programmatic Approach

    Initial Programmatic Approach Dry Storage Phase 1 – Facility Review - Records Review/Staff Interviews Closure of Wet CCP Facilities - Site Condition Review Water Treatment & - Recommendations for Future Analysis, Studies, and Management Program Improvements Wet‐to‐Dry CCP Process Conversion - Final

  41. Slide 41: Bull Run: Phase 2 Assessment

    Slide 41: Bull Run: Phase 2 Assessment

    Bull Run: Phase 2 Assessment Regional Energy Resource Council 41

  42. Slide 42: Bull Run: Gypsum Stack Toe (before)

    Slide 42: Bull Run: Gypsum Stack Toe (before)

    Bull Run: Gypsum Stack Toe (before) Regional Energy Resource Council 42

  43. Slide 43: Bull Run: Phase 3 Remediation

    Slide 43: Bull Run: Phase 3 Remediation

    Bull Run: Phase 3 Remediation Regional Energy Resource Council 43

  44. Slide 44: Bull Run: Gypsum Stack Toe (after)

    Slide 44: Bull Run: Gypsum Stack Toe (after)

    Bull Run: Gypsum Stack Toe (after) Regional Energy Resource Council | 44

  45. Slide 45: Instrumentation Monitoring

    Slide 45: Instrumentation Monitoring

    Instrumentation Monitoring Advanced Technology Impoundment Monitoring • Monitors in real time, the health and stability of all TVA CCP facilities. • The ATIM center provides multiple screens and computers for simultaneous analysis and risk management of CCP facilities. • The ATIM center provides a l

  46. Slide 46: Instrumentation Monitoring

    Slide 46: Instrumentation Monitoring

    Instrumentation Monitoring Advanced Technology Impoundment Monitoring Regional Energy Resource Council 46

  47. Slide 47: Instrumentation Monitoring

    Slide 47: Instrumentation Monitoring

    Instrumentation Monitoring Advanced Technology Impoundment Monitoring Instrumentation Automation • 307 piezometers • 82 slope inclinometers • 10 weather stations • 8 River Level Gauges • 13 Pond Level Gauges Manual Instrumentation – Quality Control • 707 Piezometers • Variable Monitoring for QC of A

  48. Slide 48: CCR Dewatering Facilities

    Slide 48: CCR Dewatering Facilities

    CCR Dewatering Facilities DFA Conversion Dry Storage  Completed KIF & BRF Closure of Wet CCP Facilities  PAF U3 in Planning Water Treatment & Management Gypsum Dewater Wet‐to‐Dry CCP Process Conversion  Completed KIF & BRF CCP Facility Stabilization / Remediation  PAF U3 in Planning Bottom Ash D

  49. Slide 49: CCR Landfills - New

    Slide 49: CCR Landfills - New

    CCR Landfills - New Dry Storage Closure of Wet CCP Facilities Water Treatment & Management Wet‐to‐Dry CCP Process Conversion CCP Facility Stabilization / Remediation Regional Energy Resource Council 49

  50. Slide 50: CCR Landfills – New: Gallatin Construction

    Slide 50: CCR Landfills – New: Gallatin Construction

    CCR Landfills – New Gallatin Construction Regional Energy Resource Council | 50

  51. Slide 51: CCR Rule Overview

    Slide 51: CCR Rule Overview

    CCR Rule Overview • TVA commits to convert to dry CCR process (2009) • Establishes technical approach in anticipation of CCR Rule (2009-2015) Dry Storage • Rule Effective: October 19, 2015 Closure of Wet • Rule is “Self-Implementing” CCP Facilities - State does not enforce Water Treatment & Manageme

  52. Slide 52: Strategic Field Work Closure Timeline

    Slide 52: Strategic Field Work Closure Timeline

    Strategic Field Work Closure Timeline CCR Rule Categorical Distribution Regional Energy Resource Council 52

  53. Slide 53: Allen Fossil Plant CCR Rule Applicability

    Slide 53: Allen Fossil Plant CCR Rule Applicability

    Allen Fossil Plant CCR Rule Applicability Regional Energy Resource Council 53

  54. Slide 54: Bull Run Fossil Plant CCR Rule Applicability

    Slide 54: Bull Run Fossil Plant CCR Rule Applicability

    Bull Run Fossil Plant CCR Rule Applicability Regional Energy Resource Council 54

  55. Slide 55: CCR Rule: Implementation Timeline

    Slide 55: CCR Rule: Implementation Timeline

    CCR Rule: Implementation Timeline 6 Months Internet, Recordkeeping, Inspections, Air Criteria, Legacy Sites 8 Months Impoundment Markers & Notice of Closure Intent 9 Months Annual Inspections 18 Months Structural Integrity, H&H Analysis, & Closure Packages 24 Months Emergency Action Plans 30 Months

  56. Slide 56: CCR Closed Sites: Widows Creek Gypsum Stack

    Slide 56: CCR Closed Sites: Widows Creek Gypsum Stack

    CCR Closed Sites Widows Creek Gypsum Stack Dry Storage Closure of Wet CCP Facilities Water Treatment & Management Wet‐to‐Dry CCP Process Conversion CCP Facility Stabilization / Remediation Regional Energy Resource Council | 56

  57. Slide 57: Questions?

    Slide 57: Questions?

    Questions? Regional Energy Resource Council | 57

  58. Slide 58: Relative Impact Framework: Closure in Place vs Excavate & Redispose

    Slide 58: Relative Impact Framework: Closure in Place vs Excavate & Redispose

    Relative Impact Framework Closure in Place vs Excavate & Redispose Bruce Hensel Senior Technical Leader TVA Regional Energy Resource Council Meeting January 20, 2016 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  59. Slide 59: Agenda

    Slide 59: Agenda

    Agenda Relative Impact Background Framework Observations Overview / Examples 59 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  60. Slide 60: Relative Impact of Closure Alternatives Based on Multiple Exposure Pathways

    Slide 60: Relative Impact of Closure Alternatives Based on Multiple Exposure Pathways

    Relative Impact of Closure Alternatives Based on Multiple Exposure Pathways 60 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  61. Slide 61: Approach

    Slide 61: Approach

    Approach • Baseline Data Scenarios • Closure in Place • Excavate & Redispose Assembly • Air Relative Pathways • Safety • GW, SW, Etc. Impacts Outcome • Concentrations Integrate • Accidents Metrics • Material consumption Results Model • Simple/analytical Sensitivity • Advanced/numerical Approach Anal

  62. Slide 62: Pathways, Parameters, & Metrics

    Slide 62: Pathways, Parameters, & Metrics

    Pathways, Parameters, & Metrics Time-weighted average Constituents of Groundwater Time above benchmark Concern Concentration above benchmark Time-weighted average Constituents of Surface Water Time above benchmark Concern Concentration above benchmark Particulate Matter Annual Average upto 2.5 µm (P

  63. Slide 63: Pathways, Parameters, & Metrics (Continued)

    Slide 63: Pathways, Parameters, & Metrics (Continued)

    Pathways, Parameters, & Metrics (Continued) Greenhouse gas Mass emitted emissions Energy used BTUs used Green & NOx Sustainable Mass emitted emissions Remediation SOx Mass emitted emissions PM10 Mass emitted emissions 63 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  64. Slide 64: Pathways & Metrics (Continued)

    Slide 64: Pathways & Metrics (Continued)

    Pathways & Metrics (Continued) Worker injuries On Site Worker fatalities Safety Truck crashes with injuries Off Site Truck crashes with fatalities 64 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  65. Slide 65: Example of a Site Scenario

    Slide 65: Example of a Site Scenario

    Example of a Site Scenario Not to Scale  Other Key Site Data – Surface impoundment area, volume – Length of time surface impoundment is in service – Aquifer dimensions, groundwater flow rate – River depth, discharge – Construction equipment, number of workers, distances for material transport 65 ©

  66. Slide 66: Time Frames Need to be Calculated

    Slide 66: Time Frames Need to be Calculated

    Time Frames Need to be Calculated Example Key driver for groundwater pathway relative impact 66 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  67. Slide 67: Example of Integrated Results

    Slide 67: Example of Integrated Results

    Example of Integrated Results Positive Impact Negative Impact Percentage of Baseline (log scale) 1 10 100 1,000 10,000 100,000 1,000,000 10,000,000 Baseline In‐place Groundwater Excavate & Redispose Surface Water Air Annual Mean Air Daily Maximum GSR Safety Example • Baseline = Current Conditions •

  68. Slide 68: Groundwater Pathway Analysis

    Slide 68: Groundwater Pathway Analysis

    Groundwater Pathway Analysis  Key parameters  Key alternatives – Source concentration – Constituents potentially released – Downward mass flux (infiltration) – Non-intersecting or intersecting groundwater – Attenuation factor – Type of cap for close-in-place – Distance to receptor / monitoring  R

  69. Slide 69: Example Groundwater Model Results

    Slide 69: Example Groundwater Model Results

    Example Groundwater Model Results Example, Non‐Intersecting groundwater 100% Predicted Groundwater Concentration as a Percentage of Leachate Concentration 80% Baseline 60% Closure‐in‐Place Excavate and Redispose 40% 20% 0% 0 20 40 60 80 100 120 140 Time (years) Example: Intersecting GW 100% Predicte

  70. Slide 70: Surface Water Pathway Analysis

    Slide 70: Surface Water Pathway Analysis

    Surface Water Pathway Analysis  Key parameters  Alternatives – Groundwater flux – Constituents – River discharge – River or lake  Calculated using mixing equation or  Relative impact drivers: mass-balance approach – Impoundment volume / time to excavate Surface Water Pathway Percentage of Baseli

  71. Slide 71: Air Pathway Analysis

    Slide 71: Air Pathway Analysis

    Air Pathway Analysis  Key parameters  Alternatives – Impoundment acreage / volume – Method / route of transportation – Distance to receptor (from landfill, haul  Relative impact drivers road, and impoundment) – Trips per day between impoundment – Dust control measures and landfill – Volume / freq

  72. Slide 72: Green & Sustainable Remediation Pathway Analysis

    Slide 72: Green & Sustainable Remediation Pathway Analysis

    Green & Sustainable Remediation Pathway Analysis  Key parameters  Alternatives – Impoundment acreage / volume – Method / route of transportation – Distance to landfill – Type of cap – Impoundment cap, landfill liner materials – Type of landfill liner  Moderate modeling effort using SiteWise™  Re

  73. Slide 73: Safety Pathway Analysis

    Slide 73: Safety Pathway Analysis

    Safety Pathway Analysis  Key parameters  Alternatives – Impoundment acreage / volume – Method / route of transportation – Distance to landfill  Relative impact drivers – Distance of sourced material to site – Impoundment volume  Moderate modeling effort using SiteWise™ – Distance to landfill and

  74. Slide 74: Framework Summary

    Slide 74: Framework Summary

    Framework Summary  Evaluates relative impact of Closure In-Place versus Closure by Removal scenarios for multiple local pathways that may be affected. Pathways include: – Groundwater and surface water, typically assumed to be impacted – Air, green & sustainable remediation, and safety, typically as

  75. Slide 75: Observations from Framework Testing

    Slide 75: Observations from Framework Testing

    Observations from Framework Testing  Groundwater and surface water Non- – Closure In-Place and Excavate & Intersecting Groundwater Redispose can both provide a benefit relative to an impacted current condition. – The benefit from Closure In-Place Example may be reduced if groundwater intersects the

  76. Slide 76: Observations from Framework Testing

    Slide 76: Observations from Framework Testing

    Observations from Framework Testing  Air, Green & Sustainable Remediation, and Safety – Closure In-Place and Excavate & Redispose typically result in negative impacts to air quality and green & sustainable remediation, relative to baseline. – Both scenarios also increase the potential for worker an

  77. Slide 77: Questions?

    Slide 77: Questions?

    Questions? 77 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  78. Slide 78: Together…Shaping the Future of Electricity

    Slide 78: Together…Shaping the Future of Electricity

    Together…Shaping the Future of Electricity 78 © 2015 2016 Electric Power Research Institute, Inc. All rights reserved.

  79. Slide 79: Break Time

    Slide 79: Break Time

    BREAK TIME

  80. Slide 80: Coal Combustion Residual Impoundment Closure Draft EIS

    Slide 80: Coal Combustion Residual Impoundment Closure Draft EIS

    Coal Combustion Residual Impoundment Closure Draft EIS Amy Henry NEPA Program and Valley Projects Manager

  81. Slide 81: CCR Impoundment Closure Environmental Impact Statement (EIS)

    Slide 81: CCR Impoundment Closure Environmental Impact Statement (EIS)

    CCR Impoundment Closure Environmental Impact Statement (EIS) Part I: Programmatic review of closure methods • Closure-by-Removal • Closure-in-Place • No Action Part II: Site-Specific reviews At 6 plants, TVA proposes to close 10 ponds by 2018 Allen Bull Run Colbert John Sevier Kingston Widows Creek

  82. Slide 82: Evaluation Criteria

    Slide 82: Evaluation Criteria

    Evaluation Criteria - Volume of CCR materials - Mode and duration of transport (borrow/fill) activities - Schedule of closure - Stability (static, seismic) - Risk to human health & safety (workers, motorists) - Effects to wetlands and adjacent environmental resources - Environmental Justice - Cost R

  83. Slide 83: Screening for Site-Specific Closure Alternatives

    Slide 83: Screening for Site-Specific Closure Alternatives

    Screening for Site-Specific Closure Alternatives Regional Energy Resource Council | 83

  84. Slide 84: Draft EIS: Preliminary Results

    Slide 84: Draft EIS: Preliminary Results

    Draft EIS: Preliminary Results - EPRI model an analytical tool - Both closure methods protective of environment if done properly - Depending on CCR volume, close-by-removal results in greater adverse impacts to some resources - No significant impacts identified in site-specific reviews Regional Ener

  85. Slide 85: Questions?

    Slide 85: Questions?

    Questions? Regional Energy Resource Council | 85

  86. Slide 86: Preliminary Council Discussion

    Slide 86: Preliminary Council Discussion

    Preliminary Council Discussion

  87. Slide 87: Break Time

    Slide 87: Break Time

    BREAK TIME

  88. Slide 88: Public Comment Period

    Slide 88: Public Comment Period

    Public Comment Period • Public participation is appreciated • This is a listening session; responses are typically not provided

  89. Slide 89: Wrap-Up Day 1

    Slide 89: Wrap-Up Day 1

    TM Wrap-Up Day 1

  90. Slide 90: Regional Energy Resource Council

    Slide 90: Regional Energy Resource Council

    Regional Energy Resource Council January 20-21, 2016 Memphis, Tennessee

  91. Slide 91: Agenda – January 21, 2016

    Slide 91: Agenda – January 21, 2016

    Agenda – January 21, 2016 7:30 Breakfast 8:30 Allen Fossil Plant Field Trip Council 11:30 Lunch 12:30 Welcome, Review of Day 1 Hoagland/ Lavender 12:45 CCR Impoundment Closure Draft EIS Henry 1:15 CCR Discussion and Advice to TVA Council / Lavender facilitate 2:15 Break 2:30 CCR Discussion and Advic

  92. Slide 92: Recap from Day 1

    Slide 92: Recap from Day 1

    Recap from Day 1 Joe Hoagland Designated Federal Officer

  93. Slide 93: Coal Combustion Residual Impoundment Closure Draft EIS

    Slide 93: Coal Combustion Residual Impoundment Closure Draft EIS

    Coal Combustion Residual Impoundment Closure Draft EIS Amy Henry NEPA Program and Valley Projects Manager

  94. Slide 94: Coal Combustion Residual (CCR) Impoundment Closure

    Slide 94: Coal Combustion Residual (CCR) Impoundment Closure

    Coal Combustion Residual (CCR) Impoundment Closure TVA CCR impoundments in Kentucky, Tennessee, and Alabama. Bottom ash impoundment Bull Run Fossil Plant 2009 ‐ TVA began to convert wet ash impoundments to dry storage. 2015 ‐ EPA CCR Rule established national criteria and schedules for the managemen

  95. Slide 95: National Environmental Policy Act (NEPA)

    Slide 95: National Environmental Policy Act (NEPA)

    National Environmental Policy Act (NEPA) Federal law that requires federal agencies to evaluate the potential environmental impacts of proposed actions, plans, and policies Planning Process • Alternatives • Public Input Analyze Potential Environmental Effects Decision-making Tool • NEPA does not req

  96. Slide 96: CCR Impoundment Closure Environmental Impact Statement (EIS)

    Slide 96: CCR Impoundment Closure Environmental Impact Statement (EIS)

    CCR Impoundment Closure Environmental Impact Statement (EIS) Purpose and Need • Address the potential impacts of closing CCR impoundments across the TVA system • Assist TVA in complying with EPA’s CCR Rule Part I: Programmatic review of three alternatives Part II: Site-specific review of 10 proposed

  97. Slide 97: Evaluation Criteria

    Slide 97: Evaluation Criteria

    Evaluation Criteria - Volume of CCR materials - Mode and duration of transport (borrow/fill) activities - Schedule of closure - Stability (static, seismic) - Risk to human health & safety (workers, motorists) - Effects to wetlands and adjacent environmental resources - Environmental Justice - Cost R

  98. Slide 98: Draft EIS: Preliminary Results

    Slide 98: Draft EIS: Preliminary Results

    Draft EIS: Preliminary Results • Both closure methods protective of environment if done properly • Depending on CCR volume, close-by-removal results in greater adverse impacts to some resources Resource Close‐in‐Place Close‐by‐Removal Groundwater ↑ ↑↑↑ Transportation ↓ ↓↓↓↓ Public Health & Safety

  99. Slide 99: Public Review of Draft EIS

    Slide 99: Public Review of Draft EIS

    Public Review of Draft EIS Comment period Dec 30 – February 24 How to comment: • TVA’s website https://www.tva.com/nepa under “Open for Comment” • Attend a public open house session: - 10 open house meetings in communities near TVA coal plants - January 12-February 10 • Email CCR@tva.gov • US Mail A

  100. Slide 100: EIS Next Steps

    Slide 100: EIS Next Steps

    EIS Next Steps • Collect public comments December 30, 2015 – February 24, 2016 • Evaluate and respond to comments in the Final EIS • Issue Final EIS Spring 2016 • Issue TVA Record of Decision Summer 2016 Regional Energy Resource Council | 100

  101. Slide 101: Questions?

    Slide 101: Questions?

    Questions? Regional Energy Resource Council | 101

  102. Slide 102: Council Discussion and Advice

    Slide 102: Council Discussion and Advice

    Council Discussion and Advice

  103. Slide 103: Break Time

    Slide 103: Break Time

    BREAK TIME

  104. Slide 104: RERC Advice Questions

    Slide 104: RERC Advice Questions

    RERC Advice Questions 1. What do you think about TVA seeking public comment on these closure alternatives including holding meetings in communities near coal‐fired plants? 2. TVA has evaluated multiple criteria (listed below) in the Draft EIS. Is there anything important that we missed? • Volume of

  105. Slide 105: Wrap Up and Adjourn

    Slide 105: Wrap Up and Adjourn

    TM Wrap Up and Adjourn

  106. Slide 106: Thank you and please travel safely!

    Slide 106: Thank you and please travel safely!

    Thank you and please travel safely!

Source: Internet Archive copy of tva.com

More decks from Tennessee Valley Authority

All 156 Tennessee Valley Authority decks