Slide 1: Exchange filing cover letter for audited results
Dept. of Corporate Services – Corporate Relationship, National Stock Exchange of India BSE Limited, Limited, Phiroze Jeejeebhoy Towers, Dalal Street, Listing Department, Mumbai - 400 001. Exchange Plaza, C-1, Block ‘G’ Bandra-Kurla Complex, Bandra (East), Mumbai - 400 051. Scrip Code : 509496 Scrip
Slide 2: Cemindia Projects Limited Investor Presentation – Q4 FY26
Cemindia Projects Limited Investor Presentation – Q4 FY26 | April 2026
Slide 3: Contents
Contents 1 Consolidated Performance Highlights – Q4 FY26 and FY26 2 About Cemindia Projects Limited 3 ESG Annexures STRICTLY CONFIDENTIAL
Slide 4: Consolidated Performance Highlights (Q4 FY26 and FY26)
Consolidated Performance Highlights (Q4 FY26 and FY26) STRICTLY CONFIDENTIAL
Slide 5: Consolidated Performance Highlights – Q4 FY26
Consolidated Performance Highlights – Q4 FY26 Revenue EBITDA and PAT and EBITDA Margin (%)* PAT Margin (%)* 17% 2,973 66% 15.1%* 114% 450 10.7%* 271 2,532 8.1%* 4.5%* 242 113 Q4 FY25 Q4 FY26 Q4 FY25 Q4 FY26 Q4 FY25 Q4 FY26 Delivered strong Q4 financials across Revenue, EBITDA and PAT reflecting su
Slide 6: Consolidated Performance Highlights – FY26
Consolidated Performance Highlights – FY26 Revenue EBITDA and PAT and EBITDA Margin (%)* PAT Margin (%)* 10,061 9% 28% 60% 11.9%* 10.2%* 1,199 9,246 939 5.9%* 4.0%* 598 373 FY25 FY26 FY25 FY26 FY25 FY26 Record financial performance with Robust orderbook visibility reflecting disciplined execution
Slide 7: About Cemindia Projects Limited (CPL)
About Cemindia Projects Limited (CPL) STRICTLY CONFIDENTIAL
Slide 8: Diversified Portfolio and Strong Order Book
Diversified Portfolio and Strong Order Book Expansive Project Footprint Across India & Emerging Global Markets Orderbook Details Key Financial Metrics Operating Metrics FY26 FY25 ₹24,545 Cr1 ₹10,061 Cr ₹9,246 Cr Orderbook Revenue Revenue ↑ 9% YoY ↑ 17% YoY UAE ₹14,821 Cr ₹1,199 Cr ₹939 Cr Orders sec
Slide 9: Diversified Portfolio & Strong Order Book
Diversified Portfolio & Strong Order Book Break up of Orderbook Contracts secured in Q4 FY26 Remaining Contract Order Book S.No Sectors Order Value Major orders secured during the quarter Value Share1 (₹ Cr) (₹ Cr) 1 Maritime Structures 8,180 33.3% Construction of road project at Munger, Bihar 3,098
Slide 10: Areas of Operations
Areas of Operations Urban Infra, MRTS & Industrial Structures & Data Center 1 Maritime Structures 2 3 4 Airports Buildings • Jetty, Dolphins, Berths • Elevated Metro (10 projects) • Institutional • EPC of Data Center infrastructure • Commercial • Shell and Core • Ship lift, Dry Dock, Wet Basin • Und
Slide 11: Areas of Operations
Areas of Operations Hydro, Dams, Foundation & Highways, Bridges & Water & Waste 5 Tunnels & Irrigation 6 7 8 Water Specialist Engineering Flyovers • Dam and Power House • Diaphragm Wall • National Highways • Micro Tunneling • Tunnels • Ground Improvement • River Bridges • Civil work for Sewerage Pla
Slide 12: Maritime Structures
Maritime Structures West container terminal in Sri Lanka Major Projects under execution Marine project in Bangladesh LNG Jetty works in Abu Dhabi Near Shore Reclamation and Shore Balance Outer Harbour Works in Andhra Protection for Greenfield Vadhvan Port Pradesh in Maharashtra Third Berth
Slide 13: Urban Infrastructure, MRTS and Airports
Urban Infrastructure, MRTS and Airports Mumbai underground metro in Maharashtra Major Projects under execution Underground tunneling and stations for Infrastructure works at Jaipur metros in Chennai, Bengaluru, Pune, International Airport in Rajasthan Mumbai and Kolkata Construction of station
Slide 14: Industrial Structures and Buildings
Industrial Structures and Buildings Circuit bench of Calcutta High Court in West Bengal Major Projects under execution Redevelopment of Residential colony at Multistoried commercial building in Uttar Kasturba Nagar in New Delhi – PH I and PH II Pradesh Thal Sena Bhawan in Delhi Aerospace mus
Slide 15: Highway, Bridges and Flyovers / Data Center
Highway, Bridges and Flyovers / Data Center Ganga Expressway road project in Uttar Pradesh Highways, Bridges and Flyovers Major Projects under execution Six laning road project in Uttar Pradesh Road project in Bihar ₹3,207 crore Customers Adani Road Transport Limited Data Center Major Projects
Slide 16: Hydro, Dams, Tunnels and Irrigation
Hydro, Dams, Tunnels and Irrigation Sivok Rangpo Railway tunnels in West Bengal and Sikkim Major Projects under execution Railway tunnels in West Bengal and Sikkim Civil & Hydro-Mechanical Works of 500 MW Hydel Power, Pumped Storage Project in Andhra Pradesh Water conveyor system of lined grav
Slide 17: Foundation and Specialist Engineering / Water and Wastewater
Foundation and Specialist Engineering / Water and Wasterwater Brahmaputra riverfront development in Assam Foundation and Specialist Engineering Major Projects under execution Civil Works for Yard-BB5 in Odisha Piling work at Khavda in Gujarat ₹499 Customers crore The Dhamra Port Company Limite
Slide 18: Technology Adoption: Strong Equipment fleet
Technology Adoption : Strong Equipment fleet Strategic Equipment Base across diversified orderbook to strengthen execution capabilities Micro Tunnel Boring Tunnel Boring Machines Trench Cutter Cranes Hydraulic Piling Rig Machines 7 Nos. 3 Nos. 5 Nos. 120 Nos. 49 Nos. Jackup Barge Batching Plant Twin
Slide 19: Robust Financial Performance: Consolidated Profit & Loss
Robust Financial Performance : Consolidated Profit & Loss Particulars Unit FY24 FY25* FY26* FY26 Insights Revenue from operations ₹ Cr 7,896 9,246 10,061 Other income ₹ Cr 78 77 177 Total income ₹ Cr 7,974 9,323 10,238 80+ No. of Projects Cost of construction materials consumed ₹ Cr 2,944 3,224 3,35
Slide 20: Robust Financial Performance: Consolidated Balance Sheet
Robust Financial Performance : Consolidated Balance Sheet Particulars Unit FY24 FY25* FY26* FY26 Insights Assets Non-Current Assets Property, plant and equipment ₹ Cr 1,056 1,033 1,114 Right-of-use-assets 25 38 48 Capital work-in-progress ₹ Cr ₹ Cr 10 21 22 ₹ 7,087 Cr Investment Properties ₹ Cr - 6
Slide 21: Credit Rating: Improving Credit Profile with efficiency in operations
Credit Rating: Improving Credit Profile with efficiency in operations Key Rating Upgrade highlights: Rating Significant ramp-up in scale of Rating Track March 2019 March 2025 March 2026 operations reflecting revenue CAGR of Agency Record ~30% in last 6 years 6 Strong diversified orderbook provid
Slide 22: India's Decade: Infrastructure Megatrend driving massive capex cycle
India’s Decade: Infrastructure Megatrend driving massive capex cycle Capex Allocation under Union Budget India’s infrastructure upcycle offers massive opportunity for Cemindia ↑ by 6x since FY14 In ₹lakh Cr 12.2 ₹111 lakh Cr investment under NIP & Gati Shakti: 90+ years of proven execution in exec
Slide 23: Cemindia Projects: Key Investment Highlights
Cemindia Projects: Key Investment Highlights Decades of Execution Strength & Strategic Infrastructure Tailwinds position Cemindia as India’s Major Infrastructure Player 1 Infrastructure • Urban Expansion : Rapid urbanization is creating demand for transport, utilities in Tier-1 & 2 cities Megatrend
Slide 24: ESG
ESG STRICTLY CONFIDENTIAL
Slide 25: Strong ESG Initiatives and Achievements
Strong ESG Initiatives and Achievements ESG Initiatives Taken Achievements ESG Initiatives Taken Achievements 1 4 Installed Organic Waste Use of Renewable Energy Annual reduction of 15,583 kg of manure was generated Composter (OWC) for (Solar Panels – Topcon) 39.12 tons CO₂e emissions processing bio
Slide 26: ISO Certifications and Awards
ISO Certifications and Awards ISO 9001:2015 ISO 14001:2015 ISO 45001:2018 Chennai Underground Metro (Quality Management Systems) (Environmental Management Systems) (Occupational health and safety) (NSC Trophy and Certificate) National Safety Council EHS Award – World Safety Organisation – Internatio
Slide 27: ESG: Board of Directors
ESG : Board of Directors 100% Chaired Chaired IDs by by Board of Directors IDs NID Statutory Committees Independent Directors 50% - Audit 🗹 Comprised of only Independent Directors - Nomination & Remuneration 🗹 80% of 🗹 Statutory Committees - Stakeholder Relationship Chaired by Independent…
Slide 28: Thank You
Cemindia Since 1931 Thank You