  1. Slide 1: The Next Australian High-Grade Iron Ore Miner

    For personal use only THE NEXT AUSTRALIAN HIGH-GRADE IRON ORE MINER Corporate Presentation August 2020 F E N I X R E S O U R C E S L I M I T E D ( A S X : F E X )

  2. Slide 2: Important Disclosure

    Important Disclosure Disclaimer For personal use only • The material in this presentation has been prepared by Fenix Resources Limited (“Fenix”) and is general background information on Fenix. This information is given in summary form and does not purport to be complete. Information in this presenta

  3. Slide 3: Company Overview

    For personal use only Company Overview F E N I X R E S O U R C E S L I M I T E D ( A S X : F E X )

  4. Slide 4: Why invest in Fenix

    Why invest in Fenix The Next Australian High-Grade Iron Ore Miner For personal use only • 100% owner of the high-grade (64.2%) Iron Ridge iron ore deposit in WA’s Mid West • All tenements granted; Mining Proposal and Mine Closure Plan approved World Class WA High-Grade 64.2% Iron • Mining Co-Operati

  5. Slide 5: Corporate Overview

    Corporate Overview For personal use only Capital Structure & Pricing Share Price History Ordinary shares on issue 285.8m Volume (m) ClosePrice Vendor Performance Shares 1 97.5m 20 14 Employee Performance Rights 1 1.5m 18 Unlisted Options 2 79.0m 12 Daily ClosingPrice (cents pershare) Share Price (17

  6. Slide 6: Iron Ridge Project

    For personal use only Iron Ridge Project F E N I X R E S O U R C E S L I M I T E D ( A S X : F E X )

  7. Slide 7: Iron Ridge Project

    Iron Ridge Project High Grade Iron Ore Project in the Midwest For personal use only • Fenix acquired the right to 100% of the project in May 2018 and completed the transaction in November 2018. • Mineral Resource Estimate1 of 10.5 Mt @ 64.2% Fe, which represents some of the highest grade iron ore in

  8. Slide 8: Simple Geology & Standard Open Pit Mining

    Simple Geology & Standard Open Pit Mining • Mineralisation at Iron Ridge starts at surface and plunges gently For personal use only to the south-west along strike with mineralisation continuing to a depth of up to 230m below surface. Current optimised open pit goes to a maximum depth of 155m • Consi

  9. Slide 9: Uncomplicated Processing of Premium DSO

    Uncomplicated Processing of Premium DSO • Low deleterious elements, well within acceptable limits For personal use only • No beneficiation is required, simple DSO material • Anticipated to produce premium >65% Fe lump and >63% Fe fines products at 25-30% lump ratio over the life-of-mine • Processing

  10. Slide 10: Established Infrastructure Path

    Established Infrastructure Path Low Capex contract mining & For personal use only trucking concept facilitated by key project characteristics Good Roads Sealed highway runs within ~15km of project. 490km (by road) to Geraldton Port Trucking Joint Venture Fenix formed a strategic alliance, via a 50/5

  11. Slide 11: Feasibility Study Highlights

    Feasibility Study Highlights The Feasibility Study (“FS”), released on 4 November 2019, Operating Metric Unit Feasibility Study For personal use only reveals a high-grade and high-quality Project that provides Processing Capacity Mtpa 1.25 strong returns over a moderate mine life Average Strip Ratio

  12. Slide 12: Improving Macroeconomic Factors

    Improving Macroeconomic Factors Feasibility Study Current Spot Price Since the announcement of the Feasibility Study on 4 November Variance (%) For personal use only Assumptions (17 August 2020) 2019, both the A$ index iron ore price and diesel price have moved 62% Fe index price (US$) $78.00 $122.9

  13. Slide 13: Capital & Operating Expenses

    Capital & Operating Expenses For personal use only Capex Opex Commercial Pre Start-up Year 1 Capital Operating Cost (A$/dmt) LOM Average Cost Capital Cost (A$m) Production Initial Capex Total Capex Capital Cost Cost Cost Mining & Processing 20.87 Roads 2.76 - 2.76 1.89 4.65 Road Haulage 43.27 Infras

  14. Slide 14: ~21 Months of Successful Project Development

    ~21 Months of Successful Project Development From acquiring Iron Ridge in November 2018, Fenix has rapidly developed the Project including two Mineral Resource Upgrades, For personal use only delivering a successful Feasibility Study, executing a Native Title agreement and obtaining approval of the

  15. Slide 15: 2020 Project Development Progress and Target Timeline

    2020 Project Development Progress and Target Timeline For personal use only All required approvals to mine obtained Fenix is currently finalising project permitting and is in the process of securing product offtake Aug-20 Native Title Agreement First Shipment Early 2021 Aug-20 Approval of Mining Pro

  16. Slide 16: Corporate Strategy

    Corporate Strategy Ideally placed to generate value from a high quality project For personal use only Aim to supply premium- Plan to commercialise Iron grade products to the steel Ridge and build a trusted industry customer base Focused management and Board of Directors with industry specific and co

  17. Slide 17: Fenix Resources: The Next Australian High-Grade Iron Ore Miner

    Fenix Resources For personal use only The Next Australian High-Grade Iron Ore Miner Fenix Resources is Rapidly Developing its High-Grade Iron Ridge Project High-Grade 64.2% Iron Very Low Upfront Rapid Time to First World Class WA Ore Resource Capex Shipment Mining Jurisdiction F E N I X R E S O U R

  18. Slide 18: Annexures

    For personal use only Annexures F E N I X R E S O U R C E S L I M I T E D ( A S X : F E X )

  19. Slide 19: Iron Ore Pricing

    Iron Ore Pricing Iron Ridge production attracts a premium Iron Ore price given its excellent quality For personal use only Iron Ore Price (CFR Qingdao) Total Chinese Iron Ore Port Inventory (Mt) 62% CFR Qingdao Equivalent (US$/dmt) 65% CFR Qingdao Equivalent (US$/dmt) $140 120 $130 115 $120 110 Port

  20. Slide 20: Mineral Resource & Ore Reserve

    Mineral Resource & Ore Reserve For personal use only ✓ Resource update in August 2019 delivered a significant increase in overall Resource confidence, with the Indicated Mineral Resource increasing by 51% ✓ High grade overall Resource of 10.5Mt @ 64.2% Fe Tonnes Fe Al2O3 LOI P SiO2 TiO2 Mt % % % % %

  21. Slide 21: Contact

    For personal use only Contact Rob Brierley Managing Director rob@fenixresources.com.au F E N I X R E S O U R C E S L I M I T E D ( A S X : F E X )