Boral Ltd.

Boral — Corporate Update (July 2016)

23 slides from Boral's corporate update, Jul 7, 2016

  1. Slide 1: Boral Deer Park Operations

    Build something great™ ® Boral Deer Park Operations Deer Park Quarry Environmental Review Committee 7 July 2016

  2. Slide 2: Agenda

    Build something great™ ® Agenda Deer Park Quarry Environmental Review Committee- 7 July 2016  Welcome, introductions and apologies (5.00pm - 10 mins)  Previous minutes and actions (10 mins)  Deer Park Quarry Plant Replacement Project (5 mins)  Environment - Dust presentation and discussion (20 m

  3. Slide 3: Boral personnel

    Build something great™ ® Boral personnel Deer Park Quarry Environmental Review Committee - 7 July 2016  Paul Hodges Quarry Manager- Deer Park  Michael Suddes (Apology) Operations Manager- Concrete West  David Karstens Plant Manager- Asphalt  Luke Brown Deer Park Replacement Quarry Project Sponso

  4. Slide 4: Previous meeting minutes and actions

    Build something great™ ® Previous meeting minutes and actions Julia Preston, Stakeholder Relations Advisor (Southern Region) No. Action Responsibility Due date 1 Communication to Owner/Operator Contractors regarding safe PH/JP This meeting driving practices 2 Baseline status update by Dr Richard Str

  5. Slide 5: Deer Park Quarry Plant Replacement Project Update

    Build something great™ ® Deer Park Quarry Plant Replacement Project Update Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project

  6. Slide 6: Deer Park Quarry Replacement Project

    Build something great™ ® Deer Park Quarry Replacement Project Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project  Replacement Plant Project Next Steps:  Concrete foundations work 80% complete, Construction commenced, on-track to be completed by mid 2017.  Bund planting to commence

  7. Slide 7: Deer Park Quarry Replacement Project

    Build something great™ ® Deer Park Quarry Replacement Project Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project  Construction Dust Management: Monitor 2- PM10 4/4 Exceedance logged in SIMS. Details to Average for period = 12.6 ug/m3 follow. Monitor 1 no exceedance Monitor 1- PM10 r

  8. Slide 8: Deer Park Quarry Replacement Project

    Build something great™ ® Deer Park Quarry Replacement Project Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project 4/4 OS2 Monitor 24hr average = 67 ug/m3 (limit = 60 ug/m3) Monitors triggered during the day. Site team reviewed monitor to understand problem (Photo’s to follow) OS1 DPQP

  9. Slide 9: Deer Park Quarry Replacement Project

    Build something great™ ® Deer Park Quarry Replacement Project Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project SP Ausnet Establishing road around perimeter of site Photo from 4/4

  10. Slide 10: Boral Operations Reports - Concrete

    Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Concrete Michael Suddes, Operations Manager, Concrete West

  11. Slide 11: Boral Operations Reports - Asphalt

    Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Asphalt David Karstens, Plant Manager- Asphalt

  12. Slide 12: Boral Operations Reports - Quarries

    Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Quarries Paul Hodges, Quarry Manager, Boral Deer Park Quarry

  13. Slide 13: Quarry – Monitoring Locations

    Build something great™ ® Quarry – Monitoring Locations Deer Park Quarry Environmental Review Committee - 7 July 2016 Dust Monitors Blast Monitors A B

  14. Slide 14: Quarry – Ambient Air- Ash

    Build something great™ ® Quarry – Ambient Air- Ash Deer Park Quarry Environmental Review Committee - 7 July 2016

  15. Slide 15: Quarry – Blast Reports- Air Vibrations

    Build something great™ ® Quarry – Blast Reports- Air Vibrations Deer Park Quarry Environmental Review Committee - 7 July 2016

  16. Slide 16: Quarry – Blast Reports- Ground Vibrations

    Build something great™ ® Quarry – Blast Reports- Ground Vibrations Deer Park Quarry Environmental Review Committee - 7 July 2016

  17. Slide 17: Quarry – Blast Reports- Environmental

    Build something great™ ® Quarry – Blast Reports- Environmental Deer Park Quarry Environmental Review Committee - 7 July 2016

  18. Slide 18: Underspeed on CV T06

    (Deer Park Quarry Vic) Underspeed on CV T06 For more details contact: Abs Nouh Abdullah.Nouh@boral.com.au B E AFTER F O R E Transport Inventory Motion Waiting Over Production Over Processing Defects Concern Cause Countermeasure Outcome After a review of a recent CV T06 Slipping / overloaded due Inst

  19. Slide 19: Deer Park Quarry – Production Cost and Hazard Reduction

    Deer Park Quarry – Production Cost and Hazard Reduction CV T3A For more details contact: Les Jensen – 0401 894 353 les.jensen@boral.com.au BEFORE AFTER Transport Inventory Motion Waiting Over Production Over Processing Defects Concern Cause Countermeasure Outcome Material building up inside guard 20

  20. Slide 20: Environment

    Build something great™ ® Environment Patrick Boyce, HSE - Quarries, Boral

  21. Slide 21: General business and community news

    Build something great™ ® Boral Deer Park Operations General business and community news Julia Preston, Stakeholder Relations Advisor (Southern Region)

  22. Slide 22: General business

    Build something great™ ® General business Julia Preston, Stakeholder Relations Advisor (Southern Region)  Review of Environment Review Committees (Meta Finnimore, Department of Economic Development, Jobs, Transport and Resources)  Next meeting- Thursday 17 November 2016, 5.00pm

  23. Slide 23: Thank you for your attendance

    ® THANK YOU FOR YOUR ATTENDANCE  Boral Deer Park contacts  deerparkenquiries@boral.com.au  Quarry – 9363 7850  Asphalt – 9360 4255  Concrete – 9361 2196  Julia Preston– Stakeholder Relations Advisor 03 9981 2925 or julia.preston@boral.com.au  Paul Jackson – Stakeholder Relations Manager 02 90