Elia Group SA/NV · EURONEXT:ELI

Elia Group SA/NV — Investor Presentation (February 2019)

9 slides from Elia Group SA/NV's investor presentation, Feb 26, 2019

  1. Slide 1: WG Belgian Grid: Revision of the Federal Grid Code

    WG Belgian Grid Revision of the Federal Grid Code

  2. Slide 2: Federal Grid Code – Current Status

    Federal Grid Code – Current Status ? Council of State Council of Adaptation by CREG’s Adaptation by Finalization (30d) Ministers Elia’s proposal DG énergie advice DG énergie by cabinet Comité de Inspector of concertation Finance 2017 18/05/18 01/08/18 28/09/18 10/12/18 ? March ‘19 ? April ‘19 ? • Th

  3. Slide 3: Main impacts if no FGC by 27/4 as foreseen

    Main impacts if no FGC by 27/4 as foreseen Impacts related to connection Impacts related to T&Cs and requirements methodologies No national T&C’s and other T&C’s and other requirements for new regulated documents regulated documents assets while RfG stemming from EU NC stemming from FGC applies as f

  4. Slide 4: No national requirements for new assets

    No national requirements for new assets  Risk: As far as there is no decision taken according to Art. 7.4* of RfG/DCC, to specify which asset is considered as existing, units “bought” after May 2018 will have to comply to new requirements as from 27/4  Risk already identified in 2018 and led to th

  5. Slide 5: New/existing @ Regional Level

    New/existing @ Regional Level Current status: • CWaPE : • Une unité est considérée comme existante “si le propriétaire de cette unité a conclu un contrat définitif et contraignant pour l’achat du composant principal de production au plus tard deux mois après la date de publication sur le site intern

  6. Slide 6: General Requirements – Status & Next steps

    General Requirements – Status & Next steps Context • According to RfG Art 7.4 (& DCC & HVDC), General Requirements were submitted by Elia and Synergrid on 17/5/2018 in // with FGC and ABCD Limits • @ Federal Level: no decision has been taken on 17/11/18 on Gen. Req. as the non exhaustive requirement

  7. Slide 7: General Requirements – Main comments from regional regulators

    General Requirements – Main comments from regional regulators • Legal / related to competences: • Legal applicability and link between General Requirements and C10/11 • On federal level: No approval Legal applicability Connection of production Connection of demand units decision of General Requireme

  8. Slide 8: General Requirements – Main comments from regional regulators

    General Requirements – Main comments from regional regulators • Requests for clarification/need to be more specific: • mandatory provision to RSO of technical capabilities when they exceed min. requirement  Clarify that those capabilities should be put at disposal of TSO/DSO if no technical/economi

  9. Slide 9: Many thanks for your attention!

    Many thanks for your attention! ELIA SYSTEM OPERATOR Boulevard de l'Empereur 20 1000 Brussels +32 2 546 70 11 info@ elia.be www.elia.be An Elia Group company

Elia Group — Investor Presentation (February 2019) on 6ix