  1. Slide 1: Welcome: Longwood to Lakeshore Project

    Welcome Longwood to Lakeshore Project Virtual Community Open House #2

  2. Slide 2: Land acknowledgement

    Land acknowledgement Hydro One acknowledges that the Longwood to Lakeshore Project is proposed on the ancestral lands of the Anishinaabe and is now home to many diverse First Nations, Inuit and Métis people. Hydro One understands that Indigenous Nations have been here since time immemorial and are s

  3. Slide 3: Speakers and Panelists

    Speakers and Panelists Maalika Kara Craig Prewett Paul Dalmazzi Community Relations Strategic Projects Environmental Services Kyle Ellis Kelly Williams Candida D’Costa Real Estate Indigenous Relations Transmission Planning, IESO • 3

  4. Slide 4: Community Open House #2: Overview

    Community Open House #2: Overview • Explain the need for the project • Provide an update on the Environmental Assessment (EA) process • Share the route alternative identification process • Provide information on the process to select a preferred route • Present the three route alternatives, includin

  5. Slide 5: Key organizations

    Key organizations Building infrastructure to meet the energy needs of today and tomorrow involves a number of partners, including: Ministry of the Environment, Conservation and Parks Builds, owns, operates Oversees planning to Legislative Authority for Regulates the electricity and maintains ensure

  6. Slide 6: How the system works

    How the system works Ontario Power Generation and Private Generation Companies Generation Step-up Transformer Station Hydro One or Licensed Transmitter Transmission Lines 115,000 volts Transmission Lines Transformer Distribution 115,000-500,000 volts, Station Station Hydro One or Local Distribution

  7. Slide 7: Electricity needs in Southwest Ontario

    Electricity needs in Southwest Ontario

  8. Slide 8: Longwood to Lakeshore Project

    Longwood to Lakeshore Project Fall 2021 The IESO identified the need for one single-circuit 500 kilovolt transmission line between Longwood Transformer Station (TS) in the Municipality of Strathroy-Caradoc and Lakeshore TS in the Municipality of Lakeshore to be in-service by 2030 or sooner. Spring 2

  9. Slide 9: What is a Class Environmental Assessment?

    What is a Class Environmental Assessment? Steps of a Class EA • Engage with Indigenous communities, the public, municipalities, interest groups and government agencies (continues throughout the process) How is a Class EA different from a • Collect environmental information Comprehensive EA? • Identi

  10. Slide 10: Developing the route alternatives

    Developing the route alternatives Routing criteria were identified and prioritized with input from Indigenous communities, government agencies, and interest groups with local knowledge. A GIS/computer model of preliminary route alternatives was developed using the routing criteria. Preliminary route

  11. Slide 11: Developing the route alternatives

    Developing the route alternatives Three viable route alternatives, each with variations labelled A, B or C, have been identified for the new transmission lines. Each route includes two transmission lines. Each transmission line requires a 60m right-of-way.

  12. Slide 12: Examples of studies

    Examples of studies Examples of field studies and data to be collected as input to the evaluation of the alternative routes include: Wildlife and wildlife habitat: Cultural heritage areas: Groundwater and source water: Completing field studies Assessing existing data to Identifying source water prot

  13. Slide 13: Example evaluation criteria

    Example evaluation criteria The preferred route will be selected based on an evaluation process that balances project specific criteria in four categories. • 13

  14. Slide 14: Project development timeline

    Project development timeline* • 14

  15. Slide 15: Your questions and comments

    Your questions and comments Maalika Kara Craig Prewett Paul Dalmazzi Community Relations Strategic Projects Environmental Services Kyle Ellis Kelly Williams Candida D’Costa Real Estate Indigenous Relations Transmission Planning, IESO • 15

  16. Slide 16: Transmission corridors

    Transmission corridors The right-of-way for a 500 kV transmission line is 60 metres. While design work is still in early stages, we expect that the transmission towers will be: • 35 to 45 metres tall • approximately seven to nine metres square at the base Sample image for • between 275 to 335 metres

  17. Slide 17: Your questions and comments

    Your questions and comments Maalika Kara Craig Prewett Paul Dalmazzi Community Relations Strategic Projects Environmental Services Kyle Ellis Kelly Williams Candida D’Costa Real Estate Indigenous Relations Transmission Planning, IESO • 17

  18. Slide 18: Thank you

    Thank you Your input is important to us and will be considered in the evaluation of the route alternatives. To provide comments or to be added to the project contact list, please call or email: 1.877.345.6799 Community.Relations@HydroOne.com For the most up-to-date project information, visit our pro