Boral Ltd.

Boral — Corporate Update (June 2016)

23 slides from Boral's corporate update, June 2016

  1. Slide 1: Community Consultative Committee June 2016

    Community Consultative Committee June 2016

  2. Slide 2: Agenda item 3 - Correspondence

    Agenda item 3 - Correspondence  Department of planning and environment – Compliance audit - Request for action plan to be prepared  Geoff Clark – feedback on weather station report  Department of planning and environment - Request to undertake donations of materials via truck which was approved 

  3. Slide 3: Agenda item 4 – Operations

    Agenda item 4 – Operations  Overburden removal will be completed in June 16 until 2018  Primary crusher now progressing towards the east  Commissioning of site completed  Focus over last 3 months on the establishment of standards around safety, environment, housekeeping and performance. - Pedest

  4. Slide 4: Agenda item 5 – OH&S Performance

    Agenda item 5 – OH&S Performance  No loss time injuries at Peppertree through construction, commissioning or operations  Zero harm achieved for last 3 months  Site remains the top performer in safety reporting for the Metro business 4

  5. Slide 5: Incidents (EPL period June 2014 – July 2015)

    Agenda Item 6 - Environmental Performance Incidents (EPL period June 2014 – July 2015) 5

  6. Slide 6: Agenda item 6 – Environmental Performance: Complaints

    Agenda item 6 – Environmental Performance Complaints 6

  7. Slide 7: Environmental Performance – Air

    Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month Not In compliance at Site 1 and 3 7

  8. Slide 8: Environmental Performance – Air

    Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month In compliance 8

  9. Slide 9: Environmental Performance – Air

    Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month Not In compliance due to dust recorded in July and October 2015. However of the insoluble solids Ash content is nearly 50%. 9

  10. Slide 10: Environmental Performance – Air

    Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month Not in compliance – westerly winds and over burden activities 10

  11. Slide 11: Air – Particulate Matter <10 microns

    Agenda item 6 – Environmental Performance Air – Particulate Matter <10 microns (EPL period July 2014 – July 2015) PM10 below annual average goal 4 peaks above the daily average in dec 2016, due to truck movement 11

  12. Slide 12: Air - Total Suspended Particulates

    Agenda item 6 – Environmental Performance Air - Total Suspended Particulates (EPL period July 2014 – July 2015) TSP below Annual average goal 12

  13. Slide 13: Noise - quarterly noise monitoring January 2016 (daytime)

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring January 2016 All sensitive receiver sites monitored In compliance – daytime Predicted Site Noise Level Receiver Date Contribution Operational Criteria (dB(A)) EPL ID Name LAeq, 15 minute (dB(A)) daytime 16 Pace 2nd February

  14. Slide 14: Noise - quarterly noise monitoring January 2016 (evening)

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring January 2016 All sensitive receiver sites monitored In compliance - evening Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID Name Leq, 15 minute (dB(A)) evening 3rd February 2016 2 Ordasi 27 3

  15. Slide 15: Noise - quarterly noise monitoring (evening 1 min)

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring January 2016 All sensitive receiver sites monitored In compliance – evening 1min Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID Name LA1, 1 minute (dB(A)) evening 4th February 2016 29 2 Orda

  16. Slide 16: Blast monitoring (EPL 2014-2015)

    Agenda item 6 – Environmental Performance Blast monitoring (EPL 2014-2015) Overpressure 140 120 100 80 north west boundary north east boundary 60 683 Marulan sth road 40 Pace criteria 5% 20 criteria 100% 0 23-Oct-2015 3-Sep-2015 31-Jan-2016 15-Jul-2015 10-May-2016 12-Dec-2015 21-Mar-2016 29-Jun-2016

  17. Slide 17: Blast monitoring (EPL 2015-2016)

    Agenda item 6 – Environmental Performance Blast monitoring (EPL 2015-2016) All in compliance 17

  18. Slide 18: Environmental Performance – Heritage

    Agenda item 6 – Environmental Performance Heritage 18

  19. Slide 19: Environmental Performance – Ecology

    Agenda item 6 – Environmental Performance Ecology 19

  20. Slide 20: Stakeholder Engagement

    Agenda item 6 – Stakeholder Engagement  HASP project  Apple day festival  Outward Bound 2016 program  CVA schools program 20

  21. Slide 21: Plans for the next three months

    Agenda item 7 – Plans for the next three months  Maintain zero harm  Complete the site improvement works – walkways, parts storage etc  Close out remaining overburden contract (End of June)  Maintain processing performance  Continue to develop preventative maintenance scheme further 21

  22. Slide 22: Agenda item 8 – General Business

    Agenda item 8 – General Business  Weather station queries - Review of data provided for the last 12 months  Peppertree Modifications - Has been on exhibition - 5 submissions from the community - OEH, EPA and Council supportive with conditions  Marulan South Limestone update - Still being prepared

  23. Slide 23: END

    END 23